The Electricity (Connection Standards of Performance) Regulations 2010
Made: 17th August 2010
Coming into force: 1st October 2010
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Part 1 — General provisions
Citation and commencement
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Part 2 — Services and standards for metered connections
Provision of budget estimates
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Provision of quotations: single LV service demand connections and small project demand connections
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Provision of quotations: other than single LV service demand connections and small project demand connections
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Provision of quotations: quotation accuracy scheme
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Post-acceptance scheduling and completion of works: single LV service demand connections and small project demand connections
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Post-acceptance scheduling and completion of works, and energisation: other than single LV service demand connections and small project demand connections
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Part 3 — Services and standards for unmetered connections
Fault repairs
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Provision of quotations for new works
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Completion of new works
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Part 4 — Governance and other issues
Disputes
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Payments
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exemptions
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Extensions of time
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Timing of notification
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Notice of rights
18
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 1 — Data for the Purpose of Calculating Payments
Prescribed periods and prescribed sums applicable to all electricity distributors
| (1) Regulation | (2) Prescribed Period | (3) Prescribed Sum | (4) Payment Date |
|---|---|---|---|
| 4(2) | 10 working days | £50 | the working day on which the budget estimate should have been dispatched |
| 4(3) | 20 working days | £50 | the working day on which the budget estimate should have been dispatched |
| 5(2) | 5 working days | £10 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 5(3) | 15 working days | £10 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 6(2) | 25 working days | £50 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 6(3) | 35 working days | £100 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 6(4) | 65 working days | £150 for each working day after the end of the prescribed period up to and including the day on which the quotation is dispatched | the working day on which the quotation is dispatched |
| 7(3) | not applicable | £250 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
| 7(4) | not applicable | £500 | the working day on which the quotation is found, in accordance with the quotation accuracy scheme, to have been inaccurate or incomplete |
| 8(2) | 7 working days | £10 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 8(3) | the agreed date | £25 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(2) | 7 working days | £50 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 9(3) | 10 working days | £100 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 9(4) | 15 working days | £150 for each working day after the end of the prescribed period up to and including the day on which contact occurs | the working day on which contact occurs |
| 9(5) | the agreed date | £20 for each working day after the agreed date up to and including the day on which the works at the premises are commenced | the working day on which the works at the premises are commenced |
| 9(6) | the agreed date | £100 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(7) | the agreed date | £150 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(8) | the agreed date | £200 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 9(9) | the agreed date | £100 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
| 9(10) | the agreed date | £150 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
| 9(11) | the agreed date | £200 for each working day after the agreed date up to and including the day on which energisation occurs | the working day on which energisation occurs |
| 10(2) | 2 hours | £50 | the working day after the day on which the emergency attendance should have taken place |
| 10(3) | 2 calendar days | £10 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 10(4) | 10 working days | £10 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 10(5) | 20 working days | £10 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 10(6) | 25 working days | £10 for each working day after the end of the prescribed period up to and including the day on which the fault rectification works are completed | the working day on which the fault rectification works are completed |
| 11(2) | 25 working days | £10 for each working day after the end of the prescribed period up to and including the day the quotation is dispatched | the working day on which the quotation is dispatched |
| 12(2) | the agreed date | £10 for each working day after the agreed date up to and including the day on which the works are completed | the working day on which the works are completed |
| 12(3) | 35 working days | £10 for each working day after the end of the prescribed period up to and including the day on which the works are completed | the working day on which the works are completed |
| 14(1) | 10 working days | £50 | not applicable |
SCHEDULE 2 — Practice and Procedure for Determinations
Determination of disputes
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Timetable for the determination of individual disputes
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure for the determination of individual disputes
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Determination of multiple disputes
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Timetable for determination of multiple disputes
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure for the determination of multiple disputes
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Written statements
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Production of documents and other evidence
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Oral hearings
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Customer representatives for multiple disputes
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Collection of information in multiple disputes
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Payment to customers
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Set-off
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Costs
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed
The seal of the Gas and Electricity Markets Authority here affixed is authenticated by the signature of
Steve Smith — A member of the Authority — 2010-07-08
I consent
Charles Hendry — Minister of State — 2010-08-17
Explanatory note
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Footnotes
[^f00001]: The Gas and Electricity Markets Authority was established under section 1(1) of the Utilities Act 2000 (c.27).
[^f00002]: 1989 c.29: sections 39A and 39B were inserted by section 54(2) of the Utilities Act 2000 and section 40B was inserted by section 56 of the Utilities Act 2000.
[^f00003]: The National Consumer Council was established under section 1(1) of the Consumers, Estate Agents and Redress Act 2007 (c.17).
[^f00004]: 2000 c.27.
[^f00005]: 1989 c.29: section 16A was inserted by section 44 of the Utilities Act 2000.
[^f00006]: 2007 (c.17).
[^f00007]: 1991 c.22.
[^f00008]: 1989 c.29.
[^f00009]: 1989 c.29.
[^f00010]: 1989 c.29.
[^f00011]: 1989 c.29.
[^f00012]: 2004 c.36.
[^f00013]: S.I. 2010/698.
[^f00014]: 2004 c.18.
Prescribed periods and prescribed sums applicable to all electricity distributors