The Building (Approved Inspectors etc.) Regulations 2010

Type Statutory-Instrument
Publication 2010-09-06
State In force
Department King's Printer of Acts of Parliament
Reform history JSON API PDF

Made: 6th September 2010

Laid before Parliament: 9th September 2010

Coming into force: 1st October 2010

The Secretary of State is a Minister designated for the purposes of section 2(2) of the European Communities Act 1972 in relation to matters relating to the environment.

The Secretary of State makes the following Regulations in exercise of the powers conferred by section 2(2) of the European Communities Act 1972 and by sections 1(1), 2A, 16(9), 17(1) and (6), 35, 47(1) to (5), 49(1) and (5), 50(1), (4), (6) and (7), 51(1) and (2), 51A(2), (3), (5) and (6), 52(1) to (3), 53(2) and (4), 54(1) to (3) and (5), 56(1) and (2) and 126 of, paragraphs 1, 2, 3, 4, 4A, 7, 8, 9, 10 and 11(1)(a) of Schedule 1 to and Schedule 4 to the Building Act 1984 :

PART 1 — General

Citation and commencement

1

These Regulations may be cited as the Building (Approved Inspectors etc.) Regulations 2010 and shall come into force on 1st October 2010.

Interpretation

2

PART 2 — Grant and Withdrawal of Approval

Designation of bodies to approve inspectors

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Approval of inspectors

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Manner of approval or designation

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Termination of approval or designation

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lists of approvals and designations

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART 3 — Supervision of Work by Approvers

Functions of approved inspectors

8

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Independence of approved inspectors

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting initial notice

10

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting amendment notice

11

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Approved inspector's consultation with the fire and rescue authority

12

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Approved inspector's consultation with the fire and rescue authority

13

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting plans certificate

14

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Effect of plans certificate

15

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting final certificate

16

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Events causing initial notice to cease to be in force

17

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Cancellation of initial notice

18

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Local authority powers in relation to partly completed work

19

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART 4 — Application of Provisions of the Principal Regulations

Application of regulations 20, 27, 29, 37, 41, 42, 43 and 44 of the Principal Regulations

20

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART 5 — Public Bodies

Approval of public bodies

21

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting public body's notice

22

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Public body's consultation with the fire and rescue authority

23

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Public body's consultation with the sewerage undertaker

24

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting public body's plans certificate

25

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Effect of public body's plans certificate

26

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Form, grounds and period for rejecting public body's final certificate

27

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Events causing public body's notice to cease to be in force

28

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART 6 — Certificates Relating to Deposited Plans

Certificates given under section 16(9) of the Act

29

as they do in relation to the approval of inspectors and the designation of bodies to approve inspectors respectively.

PART 7 — Miscellaneous Provisions

Register of notices and certificates

30

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Contravention of certain regulations not to be an offence

31

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Electronic service of documents

32

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Transitional provisions: interpretation

33

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Transitional provisions: work already started before 1st October 2010

34

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Transitional provisions: work for which notification is not required

35

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Transitional provisions: notice given or plans deposited before 1st October 2010

36

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Transitional and saving provisions: earlier Building Regulations

37

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Revocations and consequential amendments

38

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 1 — Forms

SCHEDULE 2 — Grounds for Rejecting an Initial Notice, an Amendment Notice, or a Plans Certificate Combined with an Initial Notice

Deficiencies in initial notice

Form

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Wrong local authority

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Capacity of approved inspector

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Deficiencies in information

Information about the proposed work

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Notice of approval

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lack of declaration or undertakings

Insurance

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fire and rescue authority

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sewerage undertaker

8

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Independence

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Deficiencies in the proposed work

Drain connection

10

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Local enactments

11

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Overlap with earlier notice

Earlier notice

12

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 3 — Grounds for Rejecting a Plans Certificate, or a Plans Certificate Combined with an Initial Notice

Deficiencies in form and information

Form

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Work

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Plans

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Absence of power to give certificate

No initial notice

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Capacity of approved inspector

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lack of declarations

Insurance

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fire and rescue authority

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sewerage undertaker

8

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Independence

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 4 — Grounds for Rejecting a Final Certificate

Deficiencies in form and information

Form

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Work

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Absence of power to give certificate

No initial notice

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Capacity of approved inspector

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lack of declarations

Insurance

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Independence

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 5 — Grounds for Rejecting a Public Body's Notice, or a Combined Public Body's Notice and Plans Certificate

Deficiencies in public body’s notice

Form

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Wrong local authority

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Capacity of public body

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Deficiencies in information

Information about the proposed work

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lack of undertaking

Fire and rescue authority

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sewerage undertaker

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Deficiencies in the proposed work

Drain connection

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Local enactments

8

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 6 — Grounds for Rejecting a Public Body's Plans Certificate, or a Combined Public Body's Notice and Plans Certificate

Deficiencies in form and information

Form

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Work

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Plans

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Absence of power to give certificate

No public body’s notice

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Capacity of public body

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lack of declaration

Fire and rescue authority

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sewerage undertaker

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 7 — Grounds for Rejecting a Public Body's Final Certificate

Deficiencies in form and information

Form

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Work

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Absence of power to give certificate

Capacity of public body

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

No proper signature

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Lack of declaration

Fire and rescue authority

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Sewerage undertaker

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 8 — Revocation of Regulations

Title Reference Extent of revocation
The Building (Approved Inspectors etc.) Regulations 2000 S.I. 2000/2532 The whole Regulations.
The Building (Approved Inspectors etc.) (Amendment) Regulations 2001 S.I. 2001/3336 The whole Regulations.
The Building (Approved Inspectors etc.) (Amendment) Regulations 2002 S.I. 2002/2872 The whole Regulations.
The Building (Approved Inspectors etc.) (Amendment) Regulations 2004 S.I. 2004/1466 The whole Regulations.
The Energy Performance of Buildings (Certificates and Inspections) (England and Wales) (Amendment No. 2) Regulations 2008 S.I. 2008/2363 Regulation 4.

SCHEDULE 9 — Consequential Amendments

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Signed

Signed by authority of the Secretary of State

Andrew Stunell — Parliamentary Under Secretary of State — 2010-09-06

Explanatory note

(This note is not part of the Regulations

Footnotes