The Electricity (Standards of Performance) Regulations 2010
Made: 8th March 2010
Coming into force: 1st April 2010
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART I — General
Citation, commencement and transitional provisions
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocation
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
General interpretation
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART II — Supply restoration standards of performance for electricity distributors
Interpretation of the normal and severe weather restoration standards
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Supply restoration: normal conditions
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Supply restoration: normal conditions – 5,000 or more customers' premises interrupted
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Supply restoration: severe weather conditions
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Supply restoration: rota disconnection
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Supply restoration: Highlands and Islands
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exemptions from the normal and severe weather restoration standards
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Supply restoration: multiple interruptions
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART III — Other individual standards of performance for electricity distributors
Distributor's fuse
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Estimate of charges for connection
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Notice of supply interruption
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Voltage complaint
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART IV — Individual standards of performance for relevant suppliers
Charges and payments
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART V — Individual standards of performance for electricity suppliers
Meter disputes
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Pre-payment meters
18
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART VI — Common obligations
Appointments
19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Disputes
20
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Payments
21
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exemptions
22
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Timing of notification
23
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Notice of rights
24
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART VII — Overall standards of performance
Information to be given to customers about overall performance
25
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 1 — Data for the Purpose of Calculating Payments
PART I — Prescribed periods and prescribed sums applicable to all relevant operators
| (1) | (2) | (3) | (4) |
|---|---|---|---|
| Regulation | Prescribed period | Prescribed sum domestic customer | Prescribed sum non-domestic customer |
| 5(2)(a) | 18 hours | £54 | £108 |
| 5(2)(b) | £27 | £27 | |
| 6(2)(a) | 24 hours | £54 | £108 |
| 6(2)(b) | £27 | £27 | |
| 7(4)(a) | 24 hours | £27 | £27 |
| 7(4)(b) | £27 | £27 | |
| 7(5)(a) | 48 hours | £27 | £27 |
| 7(5)(b) | £27 | £27 | |
| 7(6)(a) | £27 | £27 | |
| 7(6)(b) | £27 | £27 | |
| 8(2) | 24 hours | £54 | £108 |
| 9(2)(a) | 18 hours | £54 | £108 |
| 9(2)(b) | £27 | £27 | |
| 11(4) | £54 | £54 | |
| 12(3) | three hours on a working day | £22 | £22 |
| 12(3) | four hours on any other day | £22 | £22 |
| ... | |||
| ... | |||
| 14(4) | two days | £22 | £44 |
| 14(5) | five days | £22 | £44 |
| 14(6) | two days | £22 | £44 |
| 15(2) | seven working days | £22 | £22 |
| 15(4)(a) | £22 | £22 | |
| 15(4)(b) | five working days | £22 | £22 |
| 16(2)(a) | five working days | £22 | £22 |
| 16(2)(b) | five working days | £22 | £22 |
| 16(2)(c) | five working days | £22 | £22 |
| 17(2) | seven working days | £22 | £22 |
| 17(4)(a) | £22 | £22 | |
| 17(4)(b) | five working days | £22 | £22 |
| 18(3) | three hours on a working day | £22 | £22 |
| 18(3) | four hours on any other day | £22 | £22 |
| 19(2) | £22 | £22 | |
| 19(3) | £22 | £22 | |
| 21(4) | 10 working days | £22 | £22 |
| 21(5) | 10 working days | £22 | £22 |
| 21(6) | 10 working days | £22 | £22 |
PART II
7.00 am and 7.00 pm on each working day and 9.00 am and 5.00 pm on any other day
PART III
This sets out, for each designated electricity distributor, eight and thirteen times the mean daily faults at distribution higher voltage, the category 3 threshold number of customers and the upper-threshold number of customers.
| (1) | (2) | (3) | (4) | (5) |
|---|---|---|---|---|
| Designated electricity distributor | Eight times the mean daily faults at distribution higher voltage | Thirteen times the mean daily faults at distribution higher voltage | Category 3 threshold number of customers | Upper- threshold number of customers |
| Central Networks West plc | 65 | 105 | 347,000 | 595,000 |
| Central Networks East plc | 68 | 110 | 445,000 | 763,000 |
| Electricity North West Limited | 49 | 80 | 256,000 | 439,000 |
| Northern Electric Distribution Limited | 37 | 59 | 218,000 | 374,000 |
| Yorkshire Electricity Distribution plc | 37 | 60 | 362,000 | 621,000 |
| Western Power Distribution (South West) plc | 59 | 97 | 278,000 | 476,000 |
| Western Power Distribution (South Wales) plc | 45 | 73 | 214,000 | 367,000 |
| EDF Energy Networks (LPN) plc | 19 | 31 | 305,000 | 523,000 |
| EDF Energy Networks (SPN) plc | 48 | 78 | 307,000 | 527,000 |
| EDF Energy Networks (EPN) plc | 85 | 139 | 561,000 | 962,000 |
| SP Distribution Limited | 76 | 124 | 228,000 | 392,000 |
| SP Manweb plc | 68 | 110 | 172,000 | 296,000 |
| Scottish Hydro-Electric Power Distribution Limited | 56 | 91 | 129,000 | 220,000 |
| Southern Electric Power Distribution plc | 66 | 107 | 412,000 | 706,000 |
SCHEDULE 2 — Standards of Performance – Practice and Procedure for Determinations
Determination of disputes
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Timetable for the determination of individual disputes
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure for the determination of individual disputes
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Determination of multiple disputes
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Timetable for determination of multiple disputes
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure for the determination of multiple disputes
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Written statements
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Production of documents and other evidence
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Oral hearings
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Customer representatives for multiple disputes
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Collection of information in multiple disputes
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Payment to customers
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Set–off
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Costs
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed
The seal of the Gas and Electricity Markets Authority here affixed is authenticated by the signature of
Steve Smith — A member of the Authority — 2010-03-02
I consent
Philip A. Hunt — Minister of State — 2010-03-08
Explanatory note
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Footnotes
[^f00001]: The Gas and Electricity Markets Authority was established under section 1(1) of the Utilities Act 2000 (c.27).
[^f00002]: 1989 c.29: section 39 was amended by paragraph 32 of Schedule 6 to the Utilities Act 2000 (c.27) sections 39A and 39B were inserted by section 54(2) of the Utilities Act 2000 and section 42A was inserted by section 58 of the Utilities Act.
[^f00003]: The National Consumer Council was established under section 1(1) of the Consumers, Estate Agents and Redress Act 2007 (c.17).
[^f00004]: S.I. 2005/1019 as amended by S.I 2007/2093.
[^f00005]: 2000 c.27.
[^f00006]: 2004 c.20.
[^f00007]: 1989 c.29: paragraph 1A of Schedule 7 was amended by Schedule 5 of the Utilities Act 2000.
[^f00008]: 2004 c.36.
[^f00009]: 1989 c.29.
[^f00010]: 1989 c.29: section 51(2) of the Utilities Act 2000 substituted a new Schedule 6 into the Act.
[^f00011]: 1989 c.29: section 16A(1) was inserted by section 44 of the Utilities Act 2000.
[^f00012]: 1989 c.29: section 19(1) was amended by section 46(2) of the Utilities Act 2000.
[^f00013]: 1989 c.29: section 19(2) was amended by section 46(3) of the Utilities Act 2000.
[^f00014]: 1989 c.29: section 16A was inserted by section 44 of the Utilities Act 2000.
[^f00015]: 1989 c.29: section 29 was amended by paragraph 30 of Schedule 6 to the Utilities Act 2000.
[^f00016]: 1989 c.29: section 51(2) of the Utilities Act 2000 substituted a new Schedule 6 into the Act.
[^f00017]: 1989 c.29: section 39B(1) was inserted by section 54(2) of the Utilities Act 2000.
[^f00018]: 1989 c.29.
[^f00019]: 2004 c.36.
[^f00020]: 1989 c.29: section 51(2) of the Utilities Act 2000 substituted a new Schedule 6 into the Act.
[^f00021]: 1989 c.29: Schedule 7 was amended by section 52 of the Utilities Act 2000.
[^f00022]: 1989 c.29: section 39A(5) was amended by section 54(2) of the Utilities Act 2000.
[^f00023]: 1989 c.29: section 39(4) was amended by paragraph 32 of Schedule 6 to the Utilities Act 2000 (c.27).
[^f00024]: 1989 c.29: section 40 was amended by sections 20(2), 56(7) and Schedule 2 to the Competition and Service (Utilities) Act 1992 (c.43), paragraph 33 of Schedule 6 and Schedule 8 to the Utilities Act 2000.
7.00 am and 7.00 pm on each working day and 9.00 am and 5.00 pm on any other day
This sets out, for each designated electricity distributor, eight and thirteen times the mean daily faults at distribution higher voltage, the category 3 threshold number of customers and the upper-threshold number of customers.
| (1) | (2) | (3) | (4) | (5) |
|---|---|---|---|---|
| Designated electricity distributor | Eight times the mean daily faults at distribution higher voltage | Thirteen times the mean daily faults at distribution higher voltage | Category 3 threshold number of customers | Upper- threshold number of customers |
| Central Networks West plc | 65 | 105 | 347,000 | 595,000 |
| Central Networks East plc | 68 | 110 | 445,000 | 763,000 |
| Electricity North West Limited | 49 | 80 | 256,000 | 439,000 |
| Northern Electric Distribution Limited | 37 | 59 | 218,000 | 374,000 |
| Yorkshire Electricity Distribution plc | 37 | 60 | 362,000 | 621,000 |
| Western Power Distribution (South West) plc | 59 | 97 | 278,000 | 476,000 |
| Western Power Distribution (South Wales) plc | 45 | 73 | 214,000 | 367,000 |
| EDF Energy Networks (LPN) plc | 19 | 31 | 305,000 | 523,000 |
| EDF Energy Networks (SPN) plc | 48 | 78 | 307,000 | 527,000 |
| EDF Energy Networks (EPN) plc | 85 | 139 | 561,000 | 962,000 |
| SP Distribution Limited | 76 | 124 | 228,000 | 392,000 |
| SP Manweb plc | 68 | 110 | 172,000 | 296,000 |
| Scottish Hydro-Electric Power Distribution Limited | 56 | 91 | 129,000 | 220,000 |
| Southern Electric Power Distribution plc | 66 | 107 | 412,000 | 706,000 |
Determination of disputes
Timetable for the determination of individual disputes
Procedure for the determination of individual disputes
Determination of multiple disputes
Timetable for determination of multiple disputes
Procedure for the determination of multiple disputes
Written statements
Production of documents and other evidence
Oral hearings
Customer representatives for multiple disputes
Collection of information in multiple disputes
Payment to customers
Set–off
Costs