The London Luton Airport Expansion Development Consent Order 2025

Type Statutory-Instrument
Publication 2025-04-03
State In force
Department King's Printer of Acts of Parliament
Reform history JSON API PDF

Made: 3rd April 2025

Coming into force: 24th April 2025

The Secretary of State, in exercise of the powers conferred by sections 114[^f00004], 115[^f00005], 117[^f00006], 120[^f00007], 122[^f00008], 123[^f00009], 127[^f00010] 131[^f00011], 135, 138[^f00012], 147[^f00013], 154 and 229 of, and paragraphs 1 to 4, 10 to 14 17, 22, 26, 33, 36 and 37 of Part 1 of Schedule 5 to, the 2008 Act, makes the following Order—

PART 1 — PRELIMINARY

Citation and commencement

1

This Order may be cited as the London Luton Airport Expansion Development Consent Order 2025 and comes into force on 24th April 2025.

Interpretation

2

PART 2 — PRINCIPAL POWERS

Development consent etc. granted by the Order

3

Maintenance of authorised development

4

The undertaker may at any time maintain the authorised development, except to the extent that this Order, or an agreement made under this Order, provides otherwise.

Maintenance of drainage works

5

Limits of works

6

Benefit of Order

7

Subject to article 8 (consent to transfer benefit of Order), the provisions of this Order conferring powers on the undertaker have effect solely for the benefit of the undertaker.