Council Regulation (EC) No 3287/94 of 22 December 1994 on pre-shipment inspections for exports from the Community

Type Regulation
Publication 1994-12-31
State In force
Text As published
Department Council of the European Union
Source EUR-Lex
articles 10

This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.

Reform history JSON API
31.12.1994 EN Official Journal of the European Communities L 349/79

COUNCIL REGULATION (EC) No 3287/94

of 22 December 1994

on pre-shipment inspections for exports from the Community

THE COUNCIL OF THE EUROPEAN UNION;

Having regard to the Treaty establishing the European Community, and in particular Article 113 thereof,

Having regard to the proposal from the Commission,

Having regard to the opinion of the European Parliament(1),

Whereas a number of developing countries have recourse to so-called pre-shipment inspection programmes in order to ensure a proper distribution of limited foreign currency resources to importers and in order to combat such practices as over- and under-invoicing and fraud; whereas these developing countries have charged private companies with this task, which includes a check on quality, as well as price of the goods intended for export to the territory of these countries;

Whereas the Community recognizes the right of the developing countries to have recourse to pre-shipment inspection; whereas, however, pre-shipment inspection can give rise to abusive interference in the price freely agreed between parties to a contract and to other practices which form unnecessary obstacles to trade; whereas, therefore, efforts should be made through cooperation and technical assistance to reduce the need for pre-shipment inspection;

Whereas the Uruguay Round Final Act, signed on 15 April 1994 in Marakesh (Morocco), establishes an Agreement on pre-shipment inspection between members of the World Trade Organization (‘WTO Agreement’); whereas this Agreement has been approved and needs to be put into effect for the Community;

Whereas Community legislation provides exporters with additional assurance that pre-shipment inspection activities are indeed carried out according to the provisions of the WTO Agreement and thus do not constitute a barrier to trade;

Whereas, to this end, pre-shipment inspection activities carried out in the Community should be made subject to certain conditions;

Whereas, in view of the maintenance of uniform principles of export policy of the Community it is necessary that the activities of pre-shipment inspection entities be regulated along uniform lines;

Whereas there is good reason to simplify procedures as much as possible, in particular with respect to the review of prices; whereas exemptions, however, are not provided by the WTO Agreement and such exemption can thus be applied only with the agreement of the pre-shipment inspection entities;

Whereas a quick and effective procedure for the settlement of disputes between exporters and pre-shipment inspection entities should be instituted; whereas such a procedure is provided by the WTO Agreement;

Whereas disputes concerning non-compliance with conditions or non-observance of procedures by pre-shipment inspection entities should be settled with the third countries making use of such entities in accordance with the relevant Community and WTO procedures;

Whereas Article 3 (3) of the WTO Agreement provides for technical assistance to third countries,

HAS ADOPTED THIS REGULATION:

Article 1

This Regulation applies to activities carried out on the customs territory of the European Community by pre-shipment inspection entities which, for the account of governments of public entities, of third countries, carry out controls on the quality, quantity or price, including exchange rate and financial terms, of goods destined for export to the territory of these third countries (‘pre-shipment inspection programmes’).

Article 2

1.

The activities of pre-shipment inspection entities as defined in Article 1 are subject to a procedure for prior notification on a generic basis under the conditions set out in this Regulation.

2.

In their notification, the pre-shipment entities shall communicate to the Commission the provisions, with the exception of remuneration, of contracts agreed with governments or public entities of third countries for the account of which the pre-shipment inspection programmes have been put in place. They shall subsequently notify all modifications regarding conditions for control to the Commission. They shall also indicate which measures they have taken to comply with the conditions set out in this Regulation.

3.

The Commission shall copy all the notifications received to the Member States.

Article 3

The notification of activities mentioned in Article 2 shall cover the following activities:

Article 4

Pre-shipment inspection entities, when carrying out their activities, shall meet the following conditions:

The pre-shipment inspection entity shall carry out the appropriate controls in a time span that avoids unreasonable delays. It shall also, following receipt of the final documents and completion of the inspection, within five working days, either issue a Clean Report of Findings or provide a detailed written explanation specifying the reasons for non-issuance. In the latter case exporters shall be given the opportunity to present their views in writing and, if exporters so request, arrange for reinspection at the earliest mutually convenient date.

Pre-shipment inspection entities shall also undertake, whenever so requested by the exporter, prior to the date of physical inspection, a preliminary verification of price and, where applicable, of currency exchange rate, on the basis of the contract between exporter and importer, the pro forma invoice and, where applicable, the application for import authorization. They shall, after a preliminary verification has taken place, immediately inform exporters in writing either of their acceptance or of their detailed reasons for non-acceptance of the price and/or currency exchange rate.

In order to avoid delays in payment, pre-shipment inspection entities shall send to exporters or to designated representatives or the exporters a Clean Report of Findings as expeditiously as possible. They shall also, in the event of a clerical error in the Clean Report of Findings, correct the error and forward the corrected information to the appropriate parties as expeditiously as possible.

Pre-shipment inspection entities shall treat all information provided by exporters as business confidential, to the extent that such information is not already published, generally available to third parties, or otherwise in the public domain. Such business confidential information shall be shared with the governments contracting or mandating the entity only to the extent that such information is customarily required for letters of credit or other forms of payment or for customs, import licensing or exchange control purposes.

Article 5

Pre-shipment inspection entities, when carrying out their activity with respect to price verification, shall meet the following conditions:

Article 6

If, as a result of its obligations towards the government or a public entity of a third country, the pre-shipment inspection entity does not observe the conditions set out in Articles 4 and 5 of this Regulation, if the entity does not comply with the procedures set out in Article 7, or if there is any other reason to believe that the WTO Agreement is not respected, recourse may be had to any appropriate procedure, including the procedure laid down by Regulation (EEC) No 2641/84 under the conditions set out therein(2).

Article 7

If pre-shipment inspection entities and exporters cannot resolve their disputes otherwise and at the earliest two working days after submission of the grievances in accordance with the provisions of paragraph (d) of Article 4, the following procedure shall normally be applied:

Article 8

Each Member State shall:

The Community and the Member States, if requested, may provide user countries with technical assistance related to pre-shipment inspection; normally such assistance should be aimed at removing the circumstances which have led these countries to resort to pre-shipment inspection.

Article 9

The Commission will inform the Secretariat of the WTO of this Regulation and any modification thereof.

Article 10

This Regulation shall enter into force on 1 January 1995.

This Regulation is binding in its entirety and directly applicable in all Member States.

Done at Brussels, 22 December 1994.

For the Council

The President

H. SEEHOFER

(1)  Opinion delivered on 14 December 1994 (not yet published in the Official Journal).

(2)  OJ No L 252, 20. 9. 1984, p. 1.

Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.

This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence. EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.