Directive (EU) 2019/944 of the European Parliament and of the Council of 5 June 2019 on common rules for the internal market for electricity and amending Directive 2012/27/EU (recast) (Text with EEA relevance.)

Type Directive
Publication 2019-06-14
Last updated 2025-10-12
State In force
Department Council of the European Union, European Parliament
Source EUR-Lex
articles 81
Reform history JSON API
3.

Transmission system operators shall be organised in a legal form as referred to in Annex I to Directive (EU) 2017/1132 of the European Parliament and of the Council ([^E0012]).

4.

The transmission system operator shall not, in its corporate identity, communication, branding and premises, create confusion with respect to the separate identity of the vertically integrated undertaking or any part thereof.

5.

The transmission system operator shall not share IT systems or equipment, physical premises and security access systems with any part of the vertically integrated undertaking nor use the same consultants or external contractors for IT systems or equipment, and security access systems.

6.

The accounts of transmission system operators shall be audited by an auditor other than the one auditing the vertically integrated undertaking or any part thereof.

Article 47

Independence of the transmission system operator
1.

Without prejudice to the decisions of the Supervisory Body under Article 49, the transmission system operator shall have:

  • (a) effective decision-making rights, independent from the vertically integrated undertaking, with respect to assets necessary to operate, maintain or develop the transmission system; and
  • (b) the power to raise money on the capital market in particular through borrowing and capital increase.
2.

The transmission system operator shall at all times act so as to ensure it has the resources it needs in order to carry out the activity of transmission properly and efficiently and develop and maintain an efficient, secure and economic transmission system.

3.

Subsidiaries of the vertically integrated undertaking performing functions of generation or supply shall not have any direct or indirect shareholding in the transmission system operator. The transmission system operator shall neither have any direct or indirect shareholding in any subsidiary of the vertically integrated undertaking performing functions of generation or supply, nor receive dividends or other financial benefits from that subsidiary.

4.

The overall management structure and the corporate statutes of the transmission system operator shall ensure effective independence of the transmission system operator in accordance with this Section. The vertically integrated undertaking shall not determine, directly or indirectly, the competitive behaviour of the transmission system operator in relation to the day-to-day activities of the transmission system operator and management of the network, or in relation to activities necessary for the preparation of the ten-year network development plan developed pursuant to Article 51.

5.

In fulfilling their tasks in Article 40 and Article 46(2) of this Directive, and in complying with obligations set out in Articles 16, 18, 19 and 50 of Regulation (EU) 2019/943, transmission system operators shall not discriminate against different persons or entities and shall not restrict, distort or prevent competition in generation or supply.

6.

Any commercial and financial relations between the vertically integrated undertaking and the transmission system operator, including loans from the transmission system operator to the vertically integrated undertaking, shall comply with market conditions. The transmission system operator shall keep detailed records of such commercial and financial relations and make them available to the regulatory authority upon request.

7.

The transmission system operator shall submit for approval by the regulatory authority all commercial and financial agreements with the vertically integrated undertaking.

8.

The transmission system operator shall inform the regulatory authority of the financial resources, referred to in point (d) of Article 46(1), available for future investment projects and/or for the replacement of existing assets.

9.

The vertically integrated undertaking shall refrain from any action impeding or prejudicing the transmission system operator from complying with its obligations in this Chapter and shall not require the transmission system operator to seek permission from the vertically integrated undertaking in fulfilling those obligations.

10.

An undertaking which has been certified by the regulatory authority as being in accordance with the requirements of this Chapter shall be approved and designated as a transmission system operator by the Member State concerned. The certification procedure in either Article 52 of this Directive and Article 51 of Regulation (EU) 2019/943 or in Article 53 of this Directive shall apply.

Article 48

Independence of the staff and the management of the transmission system operator
1.

Decisions regarding the appointment and renewal, working conditions including remuneration, and termination of the term of office of the persons responsible for the management and/or members of the administrative bodies of the transmission system operator shall be taken by the Supervisory Body of the transmission system operator appointed in accordance with Article 49.

2.

The identity and the conditions governing the term, the duration and the termination of office of the persons nominated by the Supervisory Body for appointment or renewal as persons responsible for the executive management and/or as members of the administrative bodies of the transmission system operator, and the reasons for any proposed decision terminating such term of office, shall be notified to the regulatory authority. Those conditions and the decisions referred to in paragraph 1 shall become binding only if the regulatory authority has raised no objections within three weeks of notification.

The regulatory authority may object to the decisions referred to in paragraph 1 where:

  • (a) doubts arise as to the professional independence of a nominated person responsible for the management and/or member of the administrative bodies; or
  • (b) in the case of premature termination of a term of office, doubts exist regarding the justification of such premature termination.
3.

No professional position or responsibility, interest or business relationship, directly or indirectly, with the vertically integrated undertaking or any part of it or its controlling shareholders other than the transmission system operator shall be exercised for a period of three years before the appointment of the persons responsible for the management and/or members of the administrative bodies of the transmission system operator who are subject to this paragraph.

4.

The persons responsible for the management and/or members of the administrative bodies, and employees of the transmission system operator shall have no other professional position or responsibility, interest or business relationship, directly or indirectly, with another part of the vertically integrated undertaking or with its controlling shareholders.

5.

The persons responsible for the management and/or members of the administrative bodies, and employees of the transmission system operator shall hold no interest in or receive any financial benefit, directly or indirectly, from any part of the vertically integrated undertaking other than the transmission system operator. Their remuneration shall not depend on activities or results of the vertically integrated undertaking other than those of the transmission system operator.

6.

Effective rights of appeal to the regulatory authority shall be guaranteed for any complaints by the persons responsible for the management and/or members of the administrative bodies of the transmission system operator against premature terminations of their term of office.

7.

After termination of their term of office in the transmission system operator, the persons responsible for its management and/or members of its administrative bodies shall have no professional position or responsibility, interest or business relationship with any part of the vertically integrated undertaking other than the transmission system operator, or with its controlling shareholders for a period of not less than four years.

8.

Paragraph 3 shall apply to the majority of the persons responsible for the management and/or members of the administrative bodies of the transmission system operator.

The persons responsible for the management and/or members of the administrative bodies of the transmission system operator who are not subject to paragraph 3 shall have exercised no management or other relevant activity in the vertically integrated undertaking for a period of at least six months before their appointment.

The first subparagraph of this paragraph and paragraphs 4 to 7 shall be applicable to all the persons belonging to the executive management and to those directly reporting to them on matters related to the operation, maintenance or development of the network.

Article 49

Supervisory Body
1.

The transmission system operator shall have a Supervisory Body which shall be in charge of taking decisions which may have a significant impact on the value of the assets of the shareholders within the transmission system operator, in particular decisions regarding the approval of the annual and longer-term financial plans, the level of indebtedness of the transmission system operator and the amount of dividends distributed to shareholders. The decisions falling under the remit of the Supervisory Body shall exclude those that are related to the day-to-day activities of the transmission system operator and management of the network, and to activities necessary for the preparation of the ten-year network development plan developed pursuant to Article 51.

2.

The Supervisory Body shall be composed of members representing the vertically integrated undertaking, members representing third-party shareholders and, where the relevant national law so provides, members representing other interested parties such as employees of the transmission system operator.

3.

The first subparagraph of Article 48(2) and Article 48(3) to (7) shall apply to at least half of the members of the Supervisory Body minus one.

Point (b) of the second subparagraph of Article 48(2) shall apply to all the members of the Supervisory Body.

Article 50

Compliance programme and compliance officer
1.

Member States shall ensure that transmission system operators establish and implement a compliance programme which sets out the measures taken in order to ensure that discriminatory conduct is excluded, and ensure that the compliance with that programme is adequately monitored. The compliance programme shall set out the specific obligations of employees to meet those objectives. It shall be subject to approval by the regulatory authority. Without prejudice to the powers of the regulatory authority, compliance with the programme shall be independently monitored by a compliance officer.

2.

The compliance officer shall be appointed by the Supervisory Body, subject to approval by the regulatory authority. The regulatory authority may refuse the approval of the compliance officer only for reasons of lack of independence or professional capacity. The compliance officer may be a natural or legal person. Article 48(2) to (8) shall apply to the compliance officer.

3.

The compliance officer shall be in charge of:

  • (a) monitoring the implementation of the compliance programme;
  • (b) elaborating an annual report, setting out the measures taken in order to implement the compliance programme and submitting it to the regulatory authority;
  • (c) reporting to the Supervisory Body and issuing recommendations on the compliance programme and its implementation;
  • (d) notifying the regulatory authority on any substantial breaches with regard to the implementation of the compliance programme; and
  • (e) reporting to the regulatory authority on any commercial and financial relations between the vertically integrated undertaking and the transmission system operator.
4.

The compliance officer shall submit the proposed decisions on the investment plan or on individual investments in the network to the regulatory authority. This shall occur at the latest when the management and/or the competent administrative body of the transmission system operator submits them to the Supervisory Body.

5.

Where the vertically integrated undertaking, in the general assembly or through the vote of the members of the Supervisory Body it has appointed, has prevented the adoption of a decision with the effect of preventing or delaying investments, which under the ten-year network development plan was to be executed in the following three years, the compliance officer shall report this to the regulatory authority, which then shall act in accordance with Article 51.

6.

The conditions governing the mandate or the employment conditions of the compliance officer, including the duration of its mandate, shall be subject to approval by the regulatory authority. Those conditions shall ensure the independence of the compliance officer, including by providing all the resources necessary for fulfilling the compliance officer's duties. During his or her mandate, the compliance officer shall have no other professional position, responsibility or interest, directly or indirectly, in or with any part of the vertically integrated undertaking or with its controlling shareholders.

7.

The compliance officer shall report regularly, either orally or in writing, to the regulatory authority and shall have the right to report regularly, either orally or in writing, to the Supervisory Body of the transmission system operator.

8.

The compliance officer may attend all meetings of the management or administrative bodies of the transmission system operator, and those of the Supervisory Body and the general assembly. The compliance officer shall attend all meetings that address the following matters:

  • (a) conditions for access to the network, as laid down in Regulation (EU) 2019/943, in particular regarding tariffs, third-party access services, capacity allocation and congestion management, transparency, ancillary services and secondary markets;
  • (b) projects undertaken in order to operate, maintain and develop the transmission system, including interconnection and connection investments;
  • (c) energy purchases or sales necessary for the operation of the transmission system.
9.

The compliance officer shall monitor the compliance of the transmission system operator with Article 41.

10.

The compliance officer shall have access to all relevant data and to the offices of the transmission system operator and to all the information necessary for the fulfilment of his task.

11.

The compliance officer shall have access to the offices of the transmission system operator without prior announcement.

12.

After prior approval by the regulatory authority, the Supervisory Body may dismiss the compliance officer. It shall dismiss the compliance officer for reasons of lack of independence or professional capacity upon request of the regulatory authority.

Article 51

Network development and powers to make investment decisions
1.

At least every two years, transmission system operators shall submit to the regulatory authority a ten-year network development plan based on existing and forecast supply and demand after having consulted all the relevant stakeholders. That network development plan shall contain efficient measures in order to guarantee the adequacy of the system and the security of supply. The transmission system operator shall publish the ten-year network development plan on its website.

2.

The ten-year network development plan shall in particular:

  • (a) indicate to market participants the main transmission infrastructure that needs to be built or upgraded over the next ten years;
  • (b) contain all the investments already decided and identify new investments which have to be executed in the next three years; and
  • (c) provide for a time frame for all investment projects.
3.

When elaborating the ten-year network development plan, the transmission system operator shall fully take into account the potential for the use of demand response, energy storage facilities or other resources as alternatives to system expansion, as well as expected consumption, trade with other countries and investment plans for Union-wide and regional networks.

4.

The regulatory authority shall consult all actual or potential system users on the ten-year network development plan in an open and transparent manner. Persons or undertakings claiming to be potential system users may be required to substantiate such claims. The regulatory authority shall publish the result of the consultation process, in particular possible needs for investments.

5.

The regulatory authority shall examine whether the ten-year network development plan covers all investment needs identified during the consultation process, and whether it is consistent with the non-binding Union-wide ten-year network development plan (‘Union-wide network development plan’) referred to in point (b) of Article 30(1) of Regulation (EU) 2019/943. If any doubt arises as to the consistency with the Union-wide network development plan, the regulatory authority shall consult ACER. The regulatory authority may require the transmission system operator to amend its ten-year network development plan.

The competent national authorities shall examine the consistency of the ten-year network development plan with the national energy and climate plan submitted in accordance with Regulation (EU) 2018/1999.

6.

The regulatory authority shall monitor and evaluate the implementation of the ten-year network development plan.

7.

In circumstances where the transmission system operator, other than for overriding reasons beyond its control, does not execute an investment, which, under the ten-year network development plan, was to be executed in the following three years, Member States shall ensure that the regulatory authority is required to take at least one of the following measures to ensure that the investment in question is made if such investment is still relevant on the basis of the most recent ten-year network development plan:

  • (a) to require the transmission system operator to execute the investments in question;
  • (b) to organise a tender procedure open to any investors for the investment in question; or
  • (c) to oblige the transmission system operator to accept a capital increase to finance the necessary investments and allow independent investors to participate in the capital.
8.

Where the regulatory authority has made use of its powers under point (b) of paragraph 7, it may oblige the transmission system operator to agree to one or more of the following:

  • (a) financing by any third party;
  • (b) construction by any third party;
  • (c) building the new assets concerned itself;
  • (d) operating the new asset concerned itself.

The transmission system operator shall provide the investors with all information needed to realise the investment, shall connect new assets to the transmission network and shall generally make its best efforts to facilitate the implementation of the investment project.

The relevant financial arrangements shall be subject to approval by the regulatory authority.

9.

Where the regulatory authority has made use of its powers under paragraph 7, the relevant tariff regulations shall cover the costs of the investments in question.

Section 4 Designation and certification of transmission system operators

Article 52

Designation and certification of transmission system operators
1.

Before an undertaking is approved and designated as transmission system operator, it shall be certified in accordance with the procedures laid down in paragraphs 4, 5 and 6 of this Article and in Article 51 of Regulation (EU) 2019/943.

2.

Undertakings which have been certified by the regulatory authority as having complied with the requirements of Article 43 pursuant to the certification procedure below, shall be approved and designated as transmission system operators by Member States. The designation of transmission system operators shall be notified to the Commission and published in the Official Journal of the European Union.

3.

Transmission system operators shall notify to the regulatory authority any planned transaction which may require a reassessment of their compliance with the requirements of Article 43.

4.

Regulatory authorities shall monitor the continuing compliance of transmission system operators with the requirements of Article 43. They shall open a certification procedure to ensure such compliance:

  • (a) upon notification by the transmission system operator pursuant to paragraph 3;
  • (b) on their own initiative where they have knowledge that a planned change in rights or influence over transmission system owners or transmission system operators may lead to an infringement of Article 43, or where they have reason to believe that such an infringement may have occurred; or
  • (c) upon a reasoned request from the Commission.
5.

The regulatory authorities shall adopt a decision on the certification of a transmission system operator within four months of the date of the notification by the transmission system operator or from the date of the Commission request. After expiry of that period, the certification shall be deemed to be granted. The explicit or tacit decision of the regulatory authority shall become effective only after conclusion of the procedure set out in paragraph 6.

6.

The explicit or tacit decision on the certification of a transmission system operator shall be notified without delay to the Commission by the regulatory authority, together with all the relevant information with respect to that decision. The Commission shall act in accordance with the procedure laid down in Article 51 of Regulation (EU) 2019/943.

7.

The regulatory authorities and the Commission may request from transmission system operators and undertakings performing any of the functions of generation or supply any information relevant for the fulfilment of their tasks under this Article.

8.

Regulatory authorities and the Commission shall preserve the confidentiality of commercially sensitive information.

Article 53

Certification in relation to third countries
1.

Where certification is requested by a transmission system owner or a transmission system operator which is controlled by a person or persons from a third country or third countries, the regulatory authority shall notify the Commission.

The regulatory authority shall also notify to the Commission without delay any circumstances that would result in a person or persons from a third country or third countries acquiring control of a transmission system or a transmission system operator.

2.

The transmission system operator shall notify to the regulatory authority any circumstances that would result in a person or persons from a third country or third countries acquiring control of the transmission system or the transmission system operator.

3.

The regulatory authority shall adopt a draft decision on the certification of a transmission system operator within four months of the date of notification by the transmission system operator. It shall refuse the certification if it has not been demonstrated:

  • (a) that the entity concerned complies with the requirements of Article 43; and
  • (b) to the regulatory authority or to another competent national authority designated by the Member State that granting certification will not put at risk the security of energy supply of the Member State and the Union. In considering that question the regulatory authority or other competent national authority shall take into account:
  • (i) the rights and obligations of the Union with respect to that third country arising under international law, including any agreement concluded with one or more third countries to which the Union is a party and which addresses the issues of security of energy supply;
  • (ii) the rights and obligations of the Member State with respect to that third country arising under agreements concluded with it, insofar as they comply with Union law; and
  • (iii) other specific facts and circumstances of the case and the third country concerned.
4.

The regulatory authority shall notify the decision to the Commission without delay, together with all the relevant information with respect to that decision.

5.

Member States shall provide for the regulatory authority or the designated competent authority referred to in point (b) of paragraph 3, before the regulatory authority adopts a decision on the certification, to request an opinion from the Commission on whether:

  • (a) the entity concerned complies with the requirements of Article 43; and
  • (b) granting certification will not put at risk the security of energy supply to the Union.
6.

The Commission shall examine the request referred to in paragraph 5 as soon as it is received. Within two months of receiving the request, it shall deliver its opinion to the regulatory authority or, if the request was made by the designated competent authority, to that authority.

In preparing the opinion, the Commission may request the views of ACER, the Member State concerned, and interested parties. In the event that the Commission makes such a request, the two-month period shall be extended by two months.

In the absence of an opinion by the Commission within the period referred to in the first and second subparagraphs, the Commission shall be deemed not to raise objections to the decision of the regulatory authority.

7.

When assessing whether the control by a person or persons from a third country or third countries will put at risk the security of energy supply to the Union, the Commission shall take into account:

  • (a) the specific facts of the case and the third country or third countries concerned; and
  • (b) the rights and obligations of the Union with respect to that third country or third countries arising under international law, including an agreement concluded with one or more third countries to which the Union is a party and which addresses the issues of security of supply.
8.

The regulatory authority shall, within two months of the expiry of the period referred to in paragraph 6, adopt its final decision on the certification. In adopting its final decision the regulatory authority shall take utmost account of the Commission's opinion. In any event Member States shall have the right to refuse certification where granting certification puts at risk the Member State's security of energy supply or the security of energy supply of another Member State. Where the Member State has designated another competent national authority to make the assessment referred to in point (b) of paragraph 3, it may require the regulatory authority to adopt its final decision in accordance with the assessment of that competent national authority. The regulatory authority's final decision and the Commission's opinion shall be published together. Where the final decision diverges from the Commission's opinion, the Member State concerned shall provide and publish, together with that decision, the reasoning underlying such decision.

9.

Nothing in this Article shall affect the right of Member States to exercise, in accordance with Union law, national legal controls to protect legitimate public security interests.

10.

This Article, with exception of point (a) of paragraph 3 thereof, shall also apply to Member States which are subject to a derogation under Article 66.

Article 54

Ownership of energy storage facilities by transmission system operators
1.

Transmission system operators shall not own, develop, manage or operate energy storage facilities.

2.

By way of derogation from paragraph 1, Member States may allow transmission system operators to own, develop, manage or operate energy storage facilities, where they are fully integrated network components and the regulatory authority has granted its approval, or where all of the following conditions are fulfilled:

  • (a) other parties, following an open, transparent and non-discriminatory tendering procedure that is subject to review and approval by the regulatory authority, have not been awarded a right to own, develop, manage or operate such facilities, or could not deliver those services at a reasonable cost and in a timely manner;
  • (b) such facilities or non-frequency ancillary services are necessary for the transmission system operators to fulfil their obligations under this Directive for the efficient, reliable and secure operation of the transmission system and they are not used to buy or sell electricity in the electricity markets; and
  • (c) the regulatory authority has assessed the necessity of such a derogation, has carried out an ex ante review of the applicability of a tendering procedure, including the conditions of the tendering procedure, and has granted its approval.

The regulatory authority may draw up guidelines or procurement clauses to help transmission system operators ensure a fair tendering procedure.

3.

The decision to grant a derogation shall be notified to the Commission and ACER together with relevant information about the request and the reasons for granting the derogation.

4.

The regulatory authorities shall perform, at regular intervals or at least every five years, a public consultation on the existing energy storage facilities in order to assess the potential availability and interest of other parties in investing in such facilities. Where the public consultation, as assessed by the regulatory authority, indicates that other parties are able to own, develop, operate or manage such facilities in a cost-effective manner, the regulatory authority shall ensure that transmission system operators' activities in this regard are phased-out within 18 months. As part of the conditions of that procedure, regulatory authorities may allow the transmission system operators to receive reasonable compensation, in particular to recover the residual value of their investment in the energy storage facilities.

5.

Paragraph 4 shall not apply to fully integrated network components or for the usual depreciation period of new battery storage facilities with a final investment decision until 2024, provided that such battery storage facilities are:

  • (a) connected to the grid at the latest two years thereafter;
  • (b) integrated into the transmission system;
  • (c) used only for the reactive instantaneous restoration of network security in the case of network contingencies where such restoration measure starts immediately and ends when regular re-dispatch can solve the issue; and
  • (d) not used to buy or sell electricity in the electricity markets, including balancing.

Section 5 Unbundling and transparency of accounts

Article 55

Right of access to accounts
1.

Member States or any competent authority that they designate, including the regulatory authorities referred to in Article 57, shall, insofar as necessary to carry out their functions, have right of access to the accounts of electricity undertakings as set out in Article 56.

2.

Member States and any designated competent authority, including the regulatory authorities, shall preserve the confidentiality of commercially sensitive information. Member States may provide for the disclosure of such information where such disclosure is necessary in order for the competent authorities to carry out their functions.

Article 56

Unbundling of accounts
1.

Member States shall take the necessary steps to ensure that the accounts of electricity undertakings are kept in accordance with paragraphs 2 and 3.

2.

Electricity undertakings, whatever their system of ownership or legal form, shall draw up, submit to audit and publish their annual accounts in accordance with the rules of national law concerning the annual accounts of limited liability companies adopted pursuant to Directive 2013/34/EU.

Undertakings which are not legally obliged to publish their annual accounts shall keep a copy of these at the disposal of the public in their head office.

3.

Electricity undertakings shall, in their internal accounting, keep separate accounts for each of their transmission and distribution activities as they would be required to do if the activities in question were carried out by separate undertakings, with a view to avoiding discrimination, cross-subsidisation and distortion of competition. They shall also keep accounts, which may be consolidated, for other electricity activities not relating to transmission or distribution. Revenue from ownership of the transmission or distribution system shall be specified in the accounts. Where appropriate, they shall keep consolidated accounts for other, non-electricity activities. The internal accounts shall include a balance sheet and a profit and loss account for each activity.

4.

The audit referred to in paragraph 2 shall, in particular, verify that the obligation to avoid discrimination and cross-subsidisation referred to in paragraph 3 is respected.

CHAPTER VII REGULATORY AUTHORITIES

Article 57

Designation and independence of regulatory authorities
1.

Each Member State shall designate a single regulatory authority at national level.

2.

Paragraph 1 shall be without prejudice to the designation of other regulatory authorities at regional level within Member States, provided that there is one senior representative for representation and contact purposes at Union level within ACER's Board of Regulators in accordance with Article 21(1) of Regulation (EU) 2019/942.

3.

By way of derogation from paragraph 1, a Member State may designate regulatory authorities for small systems in a geographically separate region whose consumption, in 2008, accounted for less than 3 % of the total consumption of the Member State of which it is part. That derogation shall be without prejudice to the appointment of one senior representative for representation and contact purposes at Union level within ACER's Board of Regulators in accordance with Article 21(1) of Regulation (EU) 2019/942.

4.

Member States shall guarantee the independence of the regulatory authority and shall ensure that it exercises its powers impartially and transparently. For that purpose, Member States shall ensure that, when carrying out the regulatory tasks conferred upon it by this Directive and related legislation, the regulatory authority:

  • (a) is legally distinct and functionally independent from other public or private entities;
  • (b) ensures that its staff and the persons responsible for its management:
  • (i) act independently from any market interest; and
  • (ii) do not seek or take direct instructions from any government or other public or private entity when carrying out the regulatory tasks. That requirement is without prejudice to close cooperation, as appropriate, with other relevant national authorities or to general policy guidelines issued by the government not related to the regulatory powers and duties under Article 59.
5.

In order to protect the independence of the regulatory authority, Member States shall in particular ensure that:

  • (a) the regulatory authority can take autonomous decisions, independently from any political body;
  • (b) the regulatory authority has all the necessary human and financial resources it needs to carry out its duties and exercise its powers in an effective and efficient manner;
  • (c) the regulatory authority has a separate annual budget allocation and autonomy in the implementation of the allocated budget;
  • (d) the members of the board of the regulatory authority or, in the absence of a board, the regulatory authority's top management are appointed for a fixed term of five up to seven years, renewable once;
  • (e) the members of the board of the regulatory authority or, in the absence of a board, the regulatory authority's top management are appointed based on objective, transparent and published criteria, in an independent and impartial procedure, which ensures that the candidates have the necessary skills and experience for the relevant position in the regulatory authority;
  • (f) conflict of interest provisions are in place and confidentiality obligations extend beyond the end of the mandate of the members of the board of the regulatory authority or, in the absence of a board, the end of the mandate of the regulatory authority's top management;
  • (g) the members of the board of the regulatory authority or, in the absence of a board, the regulatory authority's top management can be dismissed only based on transparent criteria in place.

In regard to point (d) of the first subparagraph, Member States shall ensure an appropriate rotation scheme for the board or the top management. The members of the board or, in the absence of a board, members of the top management may be relieved from office during their term only if they no longer fulfil the conditions set out in this Article or have been guilty of misconduct under national law.

6.

Member States may provide for the ex post control of the regulatory authorities' annual accounts by an independent auditor.

7.

By 5 July 2022 and every four years thereafter, the Commission shall submit a report to the European Parliament and the Council on the compliance of national authorities with the principle of independence set out in this Article.

Article 58

General objectives of the regulatory authority

In carrying out the regulatory tasks specified in this Directive, the regulatory authority shall take all reasonable measures in pursuit of the following objectives within the framework of its duties and powers as laid down in Article 59, in close consultation with other relevant national authorities, including competition authorities, as well as authorities, including regulatory authorities, from neighbouring Member States and neighbouring third countries, as appropriate, and without prejudice to their competence:

  • (a) promoting, in close cooperation with regulatory authorities of other Member States, the Commission and ACER, a competitive, flexible, secure and environmentally sustainable internal market for electricity within the Union, and effective market opening for all customers and suppliers in the Union, and ensuring appropriate conditions for the effective and reliable operation of electricity networks, taking into account long-term objectives;
  • (b) developing competitive and properly functioning regional cross-border markets within the Union with a view to achieving the objectives referred to in point (a);
  • (c) eliminating restrictions on trade in electricity between Member States, including developing appropriate cross-border transmission capacities to meet demand and enhancing the integration of national markets which may facilitate electricity flows across the Union;
  • (d) helping to achieve, in the most cost-effective way, the development of secure, reliable and efficient non-discriminatory systems that are consumer-oriented, and promoting system adequacy and, in accordance with general energy policy objectives, energy efficiency, as well as the integration of large and small-scale production of electricity from renewable sources and distributed generation in both transmission and distribution networks, and facilitating their operation in relation to other energy networks of gas or heat;
  • (e) facilitating access to the network for new generation capacity and energy storage facilities, in particular removing barriers that could prevent access for new market entrants and of electricity from renewable sources;
  • (f) ensuring that system operators and system users are granted appropriate incentives, in both the short and the long term, to increase efficiencies, especially energy efficiency, in system performance and to foster market integration;
  • (g) ensuring that customers benefit through the efficient functioning of their national market, promoting effective competition and helping to ensure a high level of consumer protection, in close cooperation with relevant consumer protection authorities;
  • (h) helping to achieve high standards of universal service and of public service in electricity supply, contributing to the protection of vulnerable customers and contributing to the compatibility of necessary data exchange processes for customer switching.

Article 59

Duties and powers of the regulatory authorities
1.

The regulatory authority shall have the following duties:

  • (a) fixing or approving, in accordance with transparent criteria, transmission or distribution tariffs or their methodologies, or both;
  • (aa) carrying out the obligations laid out in Article 3, Article 5(7) and Articles 14 to 17 of Regulation (EU) 2022/869 of the European Parliament and the Council ([^E0013]).
  • (b) ensuring the compliance of transmission system operators and distribution system operators and, where relevant, system owners, as well as the compliance of any electricity undertakings and other market participants, with their obligations under this Directive, Regulation (EU) 2019/943, the network codes and the guidelines adopted pursuant to Articles 59, 60 and 61 of Regulation (EU) 2019/943, and other relevant Union law, including as regards cross-border issues, as well as with ACER's decisions;
  • (c) in close coordination with the other regulatory authorities, ensuring the compliance of the single allocation platform established in accordance with Commission Regulation (EU) 2016/1719 ([^E0014]), the ENTSO for Electricity and the EU DSO entity with their obligations under this Directive, Regulation (EU) 2019/943, the network codes and guidelines adopted pursuant to Articles 59, 60 and 61 of Regulation (EU) 2019/943, and other relevant Union law, including as regards cross-border issues, as well as with ACER’s decisions, and jointly identifying non-compliance of the single allocation platform, the ENTSO for Electricity and the EU DSO entity with their respective obligations; where the regulatory authorities have not been able to reach an agreement within a period of four months after the start of consultations for the purpose of jointly identifying non-compliance, the matter shall be referred to the ACER for a decision, pursuant to Article 6(10) of Regulation (EU) 2019/942;
  • (d) approving products and procurement process for non-frequency ancillary services;
  • (e) implementing the network codes and guidelines adopted pursuant to Articles 59, 60 and 61 of Regulation (EU) 2019/943 through national measures or, where so required, coordinated regional or Union-wide measures;
  • (f) cooperating in regard to cross-border issues with the regulatory authority or authorities of the Member States concerned and with ACER, in particular through participation in the work of ACER's Board of Regulators pursuant to Article 21 of Regulation (EU) 2019/942;
  • (g) complying with, and implementing, any relevant legally binding decisions of the Commission and of ACER;
  • (h) ensuring that transmission system operators make available interconnector capacities to the utmost extent pursuant to Article 16 of Regulation (EU) 2019/943;
  • (i) reporting annually on its activity and the fulfilment of its duties to the relevant authorities of the Member States, the Commission and ACER, including on the steps taken and the results obtained as regards each of the tasks listed in this Article;
  • (j) ensuring that there is no cross-subsidisation between transmission, distribution and supply activities or other electricity or non-electricity activities;
  • (k) monitoring investment plans of the transmission system operators and providing in its annual report an assessment of the investment plans of the transmission system operators as regards their consistency with the Union-wide network development plan; such assessment may include recommendations to amend those investment plans;
  • (l) monitoring and assessing the performance of transmission system operators and distribution system operators in relation to the development of a smart grid that promotes energy efficiency and the integration of energy from renewable sources, based on a limited set of indicators, and publish a national report every two years, including recommendations;
  • (m) setting or approving standards and requirements for quality of service and quality of supply or contributing thereto together with other competent authorities and monitoring compliance with and reviewing the past performance of network security and reliability rules;
  • (n) monitoring the level of transparency, including of wholesale prices, and ensuring compliance of electricity undertakings with transparency obligations;
  • (o) monitoring the level and effectiveness of market opening and competition at wholesale and retail levels, including on electricity exchanges, prices for household customers including prepayment systems, the impact of dynamic electricity price contracts and of the use of smart metering systems, switching rates, disconnection rates, charges for maintenance services, the execution of maintenance services, the relationship between household and wholesale prices, the evolution of grid tariffs and levies, and complaints by household customers, as well as any distortion or restriction of competition, including by providing any relevant information, and bringing any relevant cases to the relevant competition authorities;
  • (p) monitoring the occurrence of restrictive contractual practices, including exclusivity clauses which may prevent customers from contracting simultaneously with more than one supplier or restrict their choice to do so, and, where appropriate, informing the national competition authorities of such practices;
  • (q) monitoring the time taken by transmission system operators and distribution system operators to make connections and repairs;
  • (r) helping to ensure, together with other relevant authorities, that the consumer protection measures are effective and enforced;
  • (s) publishing recommendations, at least annually, in relation to compliance of supply prices with Article 5, and providing those recommendations to the competition authorities, where appropriate;
  • (t) ensuring non-discriminatory access to customer consumption data, the provision, for optional use, of an easily understandable harmonised format at national level for consumption data, and prompt access for all customers to such data pursuant to Articles 23 and 24;
  • (u) monitoring the implementation of rules relating to the roles and responsibilities of transmission system operators, distribution system operators, suppliers, customers and other market participants pursuant to Regulation (EU) 2019/943;
  • (v) monitoring investment in generation and storage capacities in relation to security of supply;
  • (w) monitoring technical cooperation between Union and third-country transmission system operators;
  • (x) contributing to the compatibility of data exchange processes for the most important market processes at regional level;
  • (y) monitoring the availability of comparison tools that meet the requirements set out in Article 14;
  • (z) monitoring the removal of unjustified obstacles to and restrictions on the development of consumption of self-generated electricity, energy sharing, renewable energy communities and citizen energy communities, including obstacles and restrictions preventing the connection of flexible distributed energy generation within a reasonable time in accordance with Article 58, point (d).
2.

Where a Member State has so provided, the monitoring duties set out in paragraph 1 may be carried out by other authorities than the regulatory authority. In such a case, the information resulting from such monitoring shall be made available to the regulatory authority as soon as possible.

While preserving their independence, without prejudice to their own specific competence and consistent with the principles of better regulation, the regulatory authority shall, as appropriate, consult transmission system operators and, as appropriate, closely cooperate with other relevant national authorities when carrying out the duties set out in paragraph 1.

Any approvals given by a regulatory authority or ACER under this Directive are without prejudice to any duly justified future use of its powers by the regulatory authority under this Article or to any penalties imposed by other relevant authorities or the Commission.

3.

Member States shall ensure that regulatory authorities are granted the powers enabling them to carry out the duties referred to in this Article in an efficient and expeditious manner. For this purpose, the regulatory authority shall have at least the following powers:

  • (a) to issue binding decisions on electricity undertakings;
  • (b) to carry out investigations into the functioning of the electricity markets, and to decide upon and impose any necessary and proportionate measures to promote effective competition and ensure the proper functioning of the market. Where appropriate, the regulatory authority shall also have the power to cooperate with the national competition authority and the financial market regulators or the Commission in conducting an investigation relating to competition law;
  • (c) to require any information from electricity undertakings relevant for the fulfilment of its tasks, including the justification for any refusal to grant third-party access, and any information on measures necessary to reinforce the network;
  • (d) to impose effective, proportionate and dissuasive penalties on electricity undertakings not complying with their obligations under this Directive, Regulation (EU) 2019/943 or any relevant legally binding decisions of the regulatory authority or of ACER, or to propose that a competent court impose such penalties, including the power to impose or propose the imposition of penalties of up to 10 % of the annual turnover of the transmission system operator on the transmission system operator or of up to 10 % of the annual turnover of the vertically integrated undertaking on the vertically integrated undertaking, as the case may be, for non-compliance with their respective obligations pursuant to this Directive; and
  • (e) appropriate rights of investigation and relevant powers of instruction for dispute settlement under Article 60(2) and (3).
4.

The regulatory authority located in the Member State in which the single allocation platform, the ENTSO for Electricity or the EU DSO entity has its seat shall have the power to impose effective, proportionate and dissuasive penalties on those entities where they do not comply with their obligations under this Directive, Regulation (EU) 2019/943 or any relevant legally binding decisions of the regulatory authority or of ACER, or to propose that a competent court impose such penalties.

5.

In addition to the duties conferred upon it under paragraphs 1 and 3 of this Article, when an independent system operator has been designated under Article 44, the regulatory authority shall:

  • (a) monitor the transmission system owner's and the independent system operator's compliance with their obligations under this Article, and issue penalties for non-compliance in accordance with point (d) of paragraph 3;
  • (b) monitor the relations and communications between the independent system operator and the transmission system owner so as to ensure compliance of the independent system operator with its obligations, and in particular approve contracts and act as a dispute settlement authority between the independent system operator and the transmission system owner with respect to any complaint submitted by either party pursuant to Article 60(2);
  • (c) without prejudice to the procedure under point (c) of Article 44(2), for the first ten-year network development plan, approve the investments planning and the multi-annual network development plan submitted at least every two years by the independent system operator;
  • (d) ensure that network access tariffs collected by the independent system operator include remuneration for the network owner or network owners, which provides for adequate remuneration of the network assets and of any new investments made therein, provided they are economically and efficiently incurred;
  • (e) have the powers to carry out inspections, including unannounced inspections, at the premises of transmission system owner and independent system operator; and
  • (f) monitor the use of congestion charges collected by the independent system operator in accordance with Article 19(2) of Regulation (EU) 2019/943.
6.

In addition to the duties and powers conferred on it under paragraphs 1 and 3 of this Article, when a transmission system operator has been designated in accordance with Section 3 of Chapter VI, the regulatory authority shall be granted at least the following duties and powers:

  • (a) to impose penalties in accordance with point (d) of paragraph 3 for discriminatory behaviour in favour of the vertically integrated undertaking;
  • (b) to monitor communications between the transmission system operator and the vertically integrated undertaking so as to ensure compliance of the transmission system operator with its obligations;
  • (c) to act as dispute settlement authority between the vertically integrated undertaking and the transmission system operator with respect to any complaint submitted pursuant to Article 60(2);
  • (d) to monitor commercial and financial relations including loans between the vertically integrated undertaking and the transmission system operator;
  • (e) to approve all commercial and financial agreements between the vertically integrated undertaking and the transmission system operator on the condition that they comply with market conditions;
  • (f) to request a justification from the vertically integrated undertaking when notified by the compliance officer in accordance with Article 50(4), such justification including, in particular, evidence demonstrating that no discriminatory behaviour to the advantage of the vertically integrated undertaking has occurred;
  • (g) to carry out inspections, including unannounced ones, on the premises of the vertically integrated undertaking and the transmission system operator; and
  • (h) to assign all or specific tasks of the transmission system operator to an independent system operator appointed in accordance with Article 44 in the case of a persistent breach by the transmission system operator of its obligations under this Directive, in particular in the case of repeated discriminatory behaviour to the benefit of the vertically integrated undertaking.
7.

The regulatory authorities, except where ACER is competent to fix and approve the terms and conditions or methodologies for the implementation of network codes and guidelines under Chapter VII of Regulation (EU) 2019/943 pursuant to Article 5(2) of Regulation (EU) 2019/942 because of their coordinated nature, shall be responsible for fixing or approving sufficiently in advance of their entry into force at least the national methodologies used to calculate or establish the terms and conditions for:

  • (a) connection and access to national networks, including transmission and distribution tariffs or their methodologies, those tariffs or methodologies shall allow the necessary investments in the networks to be carried out in a manner allowing those investments to ensure the viability of the networks;
  • (b) the provision of ancillary services which shall be performed in the most economic manner possible and provide appropriate incentives for network users to balance their input and off-takes, such ancillary services shall be provided in a fair and non-discriminatory manner and be based on objective criteria; and
  • (c) access to cross-border infrastructures, including the procedures for the allocation of capacity and congestion management.
8.

The methodologies or the terms and conditions referred to in paragraph 7 shall be published.

9.

With a view to increasing transparency in the market and providing all interested parties with all necessary information and decisions or proposals for decisions concerning transmission and distribution tariffs as referred in Article 60(3), regulatory authorities shall make publicly available the detailed methodology and underlying costs used for the calculation of the relevant network tariffs, while preserving the confidentiality of commercially sensitive information.

10.

The regulatory authorities shall monitor congestion management of national electricity systems including interconnectors, and the implementation of congestion management rules. To that end, transmission system operators or market operators shall submit their congestion management rules, including capacity allocation, to the regulatory authorities. Regulatory authorities may request amendments to those rules.

Article 60

Decisions and complaints
1.

Regulatory authorities shall have the authority to require transmission system operators and distribution system operators, if necessary, to modify the terms and conditions, including tariffs or methodologies referred to Article 59 of this Directive, to ensure that they are proportionate and applied in a non-discriminatory manner, in accordance with Article 18 of Regulation (EU) 2019/943. In the event of delay in the fixing of transmission and distribution tariffs, regulatory authorities shall have the power to fix or approve provisional transmission and distribution tariffs or methodologies and to decide on the appropriate compensatory measures if the final transmission and distribution tariffs or methodologies deviate from those provisional tariffs or methodologies.

2.

Any party having a complaint against a transmission or distribution system operator in relation to that operator's obligations under this Directive may refer the complaint to the regulatory authority which, acting as dispute settlement authority, shall issue a decision within two months of receipt of the complaint. That period may be extended by two months where additional information is sought by the regulatory authority. That extended period may be further extended with the agreement of the complainant. The regulatory authority's decision shall have binding effect unless and until overruled on appeal.

3.

Any party who is affected and who has a right to complain concerning a decision on methodologies taken pursuant to Article 59 or, where the regulatory authority has a duty to consult, concerning the proposed tariffs or methodologies, may, within two months, or within a shorter period as provided for by Member States, after publication of the decision or proposal for a decision, submit a complaint for review. Such a complaint shall not have suspensive effect.

4.

Member States shall create appropriate and efficient mechanisms for regulation, control and transparency so as to avoid any abuse of a dominant position, in particular to the detriment of consumers, and any predatory behaviour. Those mechanisms shall take account of the provisions of the TFEU, and in particular Article 102 thereof.

5.

Member States shall ensure that the appropriate measures are taken, including administrative action or criminal proceedings in conformity with their national law, against the natural or legal persons responsible where confidentiality rules imposed by this Directive have not been respected.

6.

Complaints referred to in paragraphs 2 and 3 shall be without prejudice to the exercise of rights of appeal under Union or national law.

7.

Decisions taken by regulatory authorities shall be fully reasoned and justified to allow for judicial review. The decisions shall be available to the public while preserving the confidentiality of commercially sensitive information.

8.

Member States shall ensure that suitable mechanisms exist at national level under which a party affected by a decision of a regulatory authority has a right of appeal to a body independent of the parties involved and of any government.

Article 61

Regional cooperation between regulatory authorities on cross-border issues
1.

Regulatory authorities shall closely consult and cooperate with each other, in particular within ACER, and shall provide each other and ACER with any information necessary for the fulfilment of their tasks under this Directive. With respect to the information exchanged, the receiving authority shall ensure the same level of confidentiality as that required of the originating authority.

2.

Regulatory authorities shall cooperate at least at a regional level to:

  • (a) foster the creation of operational arrangements in order to enable an optimal management of the network, promote joint electricity exchanges and the allocation of cross-border capacity, and to enable an adequate level of interconnection capacity, including through new interconnection, within the region and between regions to allow for development of effective competition and improvement of security of supply, without discriminating between suppliers in different Member States;
  • (b) coordinate the joint oversight of entities performing functions at regional level;
  • (c) coordinate, in cooperation with other involved authorities, the joint oversight of national, regional and European resource adequacy assessments;
  • (d) coordinate the development of all network codes and guidelines for the relevant transmission system operators and other market actors; and
  • (e) coordinate the development of the rules governing the management of congestion.
3.

Regulatory authorities shall have the right to enter into cooperative arrangements with each other to foster regulatory cooperation.

4.

The actions referred to in paragraph 2 shall be carried out, as appropriate, in close consultation with other relevant national authorities and without prejudice to their specific competence.

5.

The Commission is empowered to adopt delegated acts in accordance with Article 67 in order to supplement this Directive by establishing guidelines on the extent of the duties of regulatory authorities to cooperate with each other and with ACER.

Article 62

Duties and powers of regulatory authorities with respect to regional coordination centres
1.

The regional regulatory authorities of the system operation region in which a regional coordination centre is established shall, in close coordination with each other:

  • (a) approve the proposal for the establishment of regional coordination centres in accordance with Article 35(1) of Regulation (EU) 2019/943;
  • (b) approve the costs related to the activities of the regional coordination centres, which are to be borne by the transmission system operators and to be taken into account in the calculation of tariffs, provided that they are reasonable and appropriate;
  • (c) approve the cooperative decision-making process;
  • (d) ensure that the regional coordination centres are equipped with all the necessary human, technical, physical and financial resources for fulfilling their obligations under this Directive and carrying out their tasks independently and impartially;
  • (e) propose jointly with other regulatory authorities of a system operation region possible additional tasks and additional powers to be assigned to the regional coordination centres by the Member States of the system operation region;
  • (f) ensure compliance with the obligations under this Directive and other relevant Union law, in particular as regards cross-border issues, and jointly identify non-compliance of the regional coordination centres with their respective obligations; where the regulatory authorities have not been able to reach an agreement within a period of four months after the start of consultations for the purpose of jointly identifying non-compliance, the matter shall be referred to ACER for a decision, pursuant to Article 6(10) of Regulation (EU) 2019/942;
  • (g) monitor the performance of system coordination and report annually to ACER in this respect in accordance with Article 46 of Regulation (EU) 2019/943.
2.

Member States shall ensure that regulatory authorities are granted the powers enabling them to carry out the duties referred to in paragraph 1 in an efficient and expeditious manner. For this purpose, the regulatory authorities shall have at least the following powers:

  • (a) to request information from the regional coordination centres;
  • (b) to carry out inspections, including unannounced inspections, at the premises of the regional coordination centres;
  • (c) to issue joint binding decisions on the regional coordination centres.
3.

The regulatory authority located in the Member State in which a regional coordination centre has its seat shall have the power to impose effective, proportionate and dissuasive penalties on the regional coordination centre where it does not comply with its obligations under this Directive, Regulation (EU) 2019/943 or any relevant legally binding decisions of the regulatory authority or of ACER, or shall have the power to propose that a competent court impose such penalties.

Article 63

Compliance with the network codes and guidelines
1.

Any regulatory authority and the Commission may request the opinion of ACER on the compliance of a decision taken by a regulatory authority with the network codes and guidelines referred to in this Directive or in Chapter VII of Regulation (EU) 2019/943.

2.

ACER shall provide its opinion to the regulatory authority which has requested it or to the Commission, respectively, and to the regulatory authority which has taken the decision in question within three months of the date of receipt of the request.

3.

Where the regulatory authority which has taken the decision does not comply with ACER's opinion within four months of the date of receipt of that opinion, ACER shall inform the Commission accordingly.

4.

Any regulatory authority may inform the Commission where it considers that a decision relevant for cross-border trade taken by another regulatory authority does not comply with the network codes and guidelines referred to in this Directive or in Chapter VII of Regulation (EU) 2019/943 within two months of the date of that decision.

5.

Where the Commission, within two months of having been informed by ACER in accordance with paragraph 3, or by a regulatory authority in accordance with paragraph 4, or, on its own initiative, within three months of the date of the decision, finds that the decision of a regulatory authority raises serious doubts as to its compatibility with the network codes and guidelines referred to in this Directive or in Chapter VII of Regulation (EU) 2019/943, the Commission may decide to examine the case further. In such a case, it shall invite the regulatory authority and the parties to the proceedings before the regulatory authority to submit observations.

6.

Where the Commission takes a decision to examine the case further, it shall, within four months of the date of such decision, issue a final decision:

  • (a) not to raise objections against the decision of the regulatory authority; or
  • (b) to require the regulatory authority concerned to withdraw its decision on the basis that network codes and guidelines have not been complied with.
7.

Where the Commission has not taken a decision to examine the case further or a final decision within the time-limits set in paragraphs 5 and 6 respectively, it shall be deemed not to have raised objections to the decision of the regulatory authority.

8.

The regulatory authority shall comply with the Commission decision requiring it to withdraw its decision within two months and shall inform the Commission accordingly.

9.

The Commission is empowered to adopt delegated acts in accordance with Article 67 supplementing this Directive by establishing guidelines setting out the details of the procedure to be followed for the application of this Article.

Article 64

Record keeping
1.

Member States shall require suppliers to keep at the disposal of the national authorities, including the regulatory authority, the national competition authorities and the Commission, for the fulfilment of their tasks, for at least five years, the relevant data relating to all transactions in electricity supply contracts and electricity derivatives with wholesale customers and transmission system operators.

2.

The data shall include details on the characteristics of the relevant transactions such as duration, delivery and settlement rules, the quantity, the dates and times of execution and the transaction prices and means of identifying the wholesale customer concerned, as well as specified details of all unsettled electricity supply contracts and electricity derivatives.

3.

The regulatory authority may decide to make available to market participants elements of that information provided that commercially sensitive information on individual market players or individual transactions is not released. This paragraph shall not apply to information about financial instruments which fall within the scope of Directive 2014/65/EU.

4.

This Article shall not create additional obligations towards the authorities referred to in paragraph 1 for entities falling within the scope of Directive 2014/65/EU.

5.

In the event that the authorities referred to in paragraph 1 need access to data kept by entities falling within the scope of Directive 2014/65/EU, the authorities responsible under that Directive shall provide them with the required data.

CHAPTER VIII FINAL PROVISIONS

Article 65

Level playing field
1.

Measures that the Member States may take pursuant to this Directive in order to ensure a level playing field shall be compatible with the TFEU, in particular Article 36 thereof, and with Union law.

2.

The measures referred to in paragraph 1 shall be proportionate, non-discriminatory and transparent. Those measures may be put into effect only following the notification to and approval by the Commission.

Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.

This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence. EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.