The Pollution Prevention and Control (Industrial Emissions) Regulations (Northern Ireland) 2013

Type Ni-Statutory-Rule
Publication 2013-06-05
Last updated 2025-04-01
State In force
Jurisdiction Northern Ireland
Department Government Printer for Northern Ireland
PDF Download
articles Not indexed
Reform history JSON API

Made: 5th June 2013

Coming into operation in accordance with regulation 1

In accordance with Article 4(4) of that Order, the Department of the Environment has consulted district councils and such bodies or persons appearing to it to be representative of the interests of district councils as it considers appropriate, such bodies or persons appearing to it to be representative of the interests of industry, agriculture and business as it considers appropriate and such other bodies or persons as it considers appropriate.

PART 1 — GENERAL

Citation and commencement

1

These Regulations may be cited as the Pollution Prevention and Control (Industrial Emissions) Regulations (Northern Ireland) 2013 and shall, subject to Schedules 3 and 17, come into operation on 20th June 2013.

Interpretation: general

2
  • (1) In these Regulations—
  • “the 2003 Landfill Regulations” means the Landfill Regulations (Northern Ireland) 2003[^f00002];
  • “baseline report” means, in relation to any particular site, all relevant information on the state of soil and groundwater contamination by relevant hazardous substances and shall include in particular all relevant—information on the existing use of the site;information on past uses of the site; andsoil and groundwater measurements based on—previously existing information; andnew information,if using that information provides an accurate description of the state of the site at the time of the report;
  • “change in operation” means, in relation to an installation or mobile plant, a change in the nature or functioning or an extension of the installation or mobile plant which may have consequences for the environment;
  • “chief inspector” means the inspector constituted to be the chief inspector under regulation 8(3);
  • “coating” means any preparation, including all the organic solvents or preparations containing organic solvents necessary for its proper application, which is used to provide a film with decorative, protective or other functional effect on a surface;
  • “cogeneration” means the simultaneous generation in one process of thermal energy and electrical or mechanical energy;
  • “combustion plant” means any technical apparatus in which fuels are oxidised in order to use the heat thus generated;
  • ...
  • “controlled waste” has the same meaning as in the Waste and Contaminated Land (Northern Ireland) Order 1997;
  • “cost-benefit analysis” means a cost-benefit analysis carried out in accordance with Part 2 of Annex IX of the Energy Efficiency Directive;
  • “the Department” means the Department of the Environment;
  • “the Directive” means Directive 2008/98/EC of the European Parliament and of the Council on waste as last amended by Directive (EU) 2018/851;
  • “directly associated activity” means—in relation to an activity carried out in a stationary technical unit and falling within any description in sections 1.1 to 6.11 of Part 1 of Schedule 1, any directly associated activity which has a technical connection with the activity carried out in the stationary technical unit and which could have an effect on pollution; andin relation to a SED activity, any directly associated activity which has a technical connection with the SED activity carried out on the same site and which could have an effect on any discharge of volatile organic compounds into the environment;
  • “draft determination” means the proposed decision made by the enforcing authority in relation to an application for, a permit or a permit variation, for a Part A installation or Part A mobile plant. The proposed decision must be advertised and interested parties may make representations which are then considered by the enforcing authority before it makes its final determination, in line with public participation principles.
  • “emission” means—in relation to Part A installations, the direct or indirect release of substances, vibrations, heat or noise from individual or diffuse sources in the installation into the air, water or land;in relation to Part B installations, the direct release of substances or heat from individual or diffuse sources in the installation into the air;in relation to Part C installations, the direct release of substances or heat from individual or diffuse sources in the installation into the air;in relation to Part A mobile plant, the direct or indirect release of substances, vibrations, heat or noise from the mobile plant into the air, water or land;in relation to Part B mobile plant, the direct release of substances or heat from the mobile plant into the air;in relation to Part C mobile plant, the direct release of substances or heat from the mobile plant into the air;
  • “emission limit value” means the mass, expressed in terms of specific parameters, concentration or level of an emission, which may not be exceeded during one or more periods of time;
  • “Energy Efficiency Directive” means Directive 2012/27/EU of the European Parliament and of the Council on energy efficiency amending Directives 2009/125/EC and 2010/30/EU and repealing Directives 2004/8/EC and 2006/32/EC[^f00003];
  • “enforcement notice” has the meaning given by regulation 27(1);
  • “enforcing authority” means, in relation to the exercise of functions under these Regulations, the authority, being either the chief inspector or district council, by whom, under regulation 7, those functions are exercisable;
  • “environmental inspection” means all actions, including site visits, monitoring of emissions and checks of internal reports and follow-up documents, verification of self-monitoring, checking of the techniques used and adequacy of the environmental management of the installation or mobile plant, undertaken by or on behalf of the competent authority to check and promote compliance of operations with their permit conditions and, where necessary, to monitor their environmental impact;
  • “environmental quality standard” means the set of requirements which must be fulfilled at a given time by a given environment or particular part thereof, as set out in EU law;
  • “existing medium combustion plant” means a combustion plant put into operation before 20th December 2018 or for which a permit was granted before 19th December 2017 provided that the plant is put into operation no later than 20th December 2018;
  • fibre-based composite material” means packaging material which is made of paperboard or paper fibres, with a layer of plastic, and which may also have layers of other materials, to form a single unit that cannot be separated by hand;
  • “food waste” means controlled waste that was at any time food intended for human consumption (even if of no nutritional value), and includes biodegradable waste produced as a consequence of the processing or preparation of food, but does not include drink;
  • “fuel” means any solid, liquid or gaseous combustible material;
  • “gas turbine” means any rotating machine which converts thermal energy into mechanical work, consisting mainly of a compressor, a thermal device in which fuel is oxidised in order to heat the working fluid, and a turbine;
  • “groundwater” means groundwater as defined in point 2 of Article 2 of Directive 2000/60/EC[^f00003] of the European Parliament and of the Council establishing a framework for community action in the field of water policy;
  • “hazardous substances” means substances or mixtures as defined in Article 3 of Regulation (EC) No 1272/2008[^f00004] of the European Parliament and of the Council on classification, labelling and packaging of substances and mixtures;
  • “hazardous waste” means hazardous waste as defined in point 2 of Article 3 of the Directive ;
  • “high-efficiency cogeneration” means cogeneration meeting the criteria laid down in Annex II of the Energy Efficiency Directive;
  • “IED” means Directive 2010/75/EU[^f00006] of the European Parliament and of the Council of 24 November 2010 on industrial emissions (integrated pollution prevention and control) (Recast);
  • “inspector” means a person appointed under regulation 8(1) or (5);
  • “installation” means a stationary technical unit within which one or more activities listed in Part 1 of Schedule 1 are carried out, and any other directly associated activities on the same site which have a technical connection with the activities listed in that Part and which could have an effect on emissions and pollution;
  • “landfill” means a landfill to which the 2003 Landfill Regulations apply;
  • materials facility” means––a facility or part of a facility where waste material is received in order to-–separate it into specified output material; orconsolidate it into bulk quantities (whether as a first point of consolidation for such waste or following the first consolidation of bulk quantities transferred from other suppliers);for the purpose of selling it, or transferring it to other facilities or persons to enable that material to be prepared for re-use or recycling;any reference to a “materials facility” excludes a facility or part of a facility––at which all the waste material received during a reporting period is attributable exclusively to a single supplier, unless the waste material so received is separated into specified output material at that facility;that is provided pursuant to arrangements made under section 25(1)(b) of the Waste and Contaminated Land (Northern Ireland) Order 1997;that undertakes the processing or sorting of waste electrical and electronic equipment, waste batteries or accumulators;
  • Materials Facilities Code” means the Code of Practice on Sampling and Reporting at Materials Facilities issued by the Department on 31st January 2025;
  • “MCPD” means the “Medium Combustion Plant Directive” which is Directive 2015/2193/EU of the European Parliament and of the Council of the 25 November 2015 on the limitation of emissions of certain pollutants into the air from medium combustion plants[^f00004];
  • “medium combustion plant” means a combustion plant with a rated thermal input equal to or greater than 1 megawatt and less than 50 megawatts irrespective of the type of fuel they use and includes any combination of combustion plants referred to in article 2(2) or article 4 of the MCPD, provided that—it does not fall within Article 2(3) or (4) of the MCPD;it is not installed on an offshore platform situated on, above or below those parts of the territorial sea adjacent to Northern Ireland;
  • “mixture” means a mixture or solution composed of two or more substances;
  • “mobile medium combustion plant” means a medium combustion plant which is designed to move or be moved whether on roads or other land;
  • “mobile plant” means plant which is designed to move or to be moved whether on roads or otherwise and which is used to carry out one or more activities listed in sections 1.1 to 6.11 of Part 1 of Schedule 1;
  • “net rated thermal input” means the rate at which fuel can be burned at the maximum continuous rating of the appliance multiplied by the net calorific value of the fuel and expressed as megawatts;
  • “new medium combustion plant” means a medium combustion plant which is not an existing medium combustion plant;
  • “off-site condition” has the meaning given by regulation 13(7);
  • “organic compound” means any compound containing at least the element carbon and one or more of hydrogen, halogens, oxygen, sulphur, phosphorus, silicon or nitrogen, with the exception of carbon oxides, inorganic carbonates and bicarbonates;
  • “organic solvent” means any volatile organic compound which is used for any of the following—alone or in combination with other agents, and without undergoing a chemical change, to dissolve raw materials, products or waste materials;as a cleaning agent to dissolve contaminants;as a dissolver;as a dispersion medium;as a viscosity adjuster;as a surface tension adjuster;as a plasticiser; oras a preservative;
  • “operator”, subject to paragraph (2), means any natural or legal person who operates or controls in whole or in part the installation or mobile plant;
  • “Part A installation”, “Part B installation” and “Part C installation” shall be interpreted in accordance with Part 3 of Schedule 1;
  • “Part A mobile plant”, “Part B mobile plant” and “Part C mobile plant” shall be interpreted in accordance with Part 3 of Schedule 1;
  • “permit” means a written authorisation granted under regulation 10 to operate all or part of an installation or mobile plant;
  • “Planning Appeals Commission” means the Planning Appeals Commission established under Article 110 of the Planning (Northern Ireland) Order 1991[^f00007];
  • “pollution” means the direct or indirect introduction, as a result of human activity, of substances, vibrations, heat or noise into air, water or land which may be harmful to human health or the quality of the environment, result in damage to material property or impair or interfere with amenities and other legitimate uses of the environment;
  • “poultry” means poultry as defined in point 1 of Article 2 of Council Directive 2009/158/EC of 30 November 2009 on animal health conditions governing intra-Community trade in, and imports from third countries of, poultry and hatching eggs as last amended by Commission Implementing Decision 2011/879/EU;
  • “the public” means one or more natural or legal persons and, in accordance with national law or practice, their associations, organisations or groups;
  • “the public concerned” means the public affected or likely to be affected by, or having an interest in, the taking of a decision on the granting or the updating of a permit or of permit conditions; for the purposes of this definition, non-governmental organisations promoting environmental protection and meeting any requirements under national law shall be deemed to have an interest;
  • “rated thermal input” means the rate at which fuel can be burned at the maximum continuous rating of the appliance multiplied by the gross calorific value of the fuel and expressed as megawatts;
  • “recovery” means any operation the principal result of which is the waste serving a useful purpose by replacing other materials which would otherwise have been used to fulfil a particular function, or waste being prepared to fulfil that function, in the plant or in the wider economy. Annex II to the Directive , sets out a non-exhaustive list of recovery operations;
  • “reduction scheme” means a reduction scheme which complies with Part 5 of Annex VII of the IED;
  • “revocation notice” has the meaning given by regulation 24(1);
  • “SED activity” means any activity falling within section 7 of Part 1 of Schedule 1 and any other activity listed in Schedule 1 to which Chapter V of the IED applies;
  • “SED installation” means—a stationary technical unit where one or more SED activities are carried out; andany other location on the same site where any other directly associated activities are carried out;
  • “separately collected food waste” means food waste which is presented for collection, and collected in a manner that ensures that food waste is kept separate from other waste;
  • “site report” means a report describing the condition of the site of the installation or mobile plant containing the information specified in Schedule 4.
  • “small SED installation” means a SED installation which falls within the lower threshold band of items 1, 3, 4, 5, 8, 10, 13, 16 or 17 of Part 2 of Annex VII of the IED or, for the other activities of Part 2 of Annex VII, which have a solvent consumption of less than 10 tonnes/year;
  • “soil” means the top layer of the Earth’s crust, composed of mineral particles, organic matter, water, air and living organisms, situated between the bedrock and the surface;
  • “specified generator” has the meaning given in paragraph 2 of Schedule 9B.
  • “specified waste management activity” means any one of the following activities—the disposal of waste in a landfill, whether or not the disposal falls within section 5.2 of Part 1 of Schedule 1;the disposal or recovery of hazardous waste falling within section 5.3 of that Part of that Schedule;the disposal or recovery of non-hazardous waste falling within section 5.4 of that Part of that Schedule;the temporary storage of waste falling within section 5.5 of that Part of that Schedule;the underground storage of waste falling within section 5.5 of that Part of that Schedule;
  • specified output material” means a batch of material (whether or not waste) that is—produced from a separating process for waste material; andmade up of one or more of the following kinds of material—glass;metal;paper;card;plastic;fibre-based composite material;
  • “stack” means a structure containing one or more flues providing a passage for waste gases in order to discharge them into the air;
  • “substance” means any chemical element and its compounds, with the exception of the following substances—radioactive substances as defined in Article 1 of Council Directive 96/29/Euratom[^f00009] of 13 May 1996 laying down basic safety standards for the protection of the health of workers and the general public against the dangers arising from ionising radiation;genetically modified micro-organisms as defined in Article 2(b) of Directive 2009/41/EC[^f00010] of the European Parliament and of the Council of 6 May 2009 on the contained use of genetically modified micro-organisms;genetically modified organisms as defined in Article 2(2) of Directive 2001/18/EC[^f00011] of the European Parliament and of the Council of 12 March 2001 on the deliberate release into the environment of genetically modified organisms;
  • “substantial change” means a change in the nature or functioning, or an extension, of an installation or mobile plant which, in the opinion of the enforcing authority, may have negative effects on human health or the environment and shall include—in relation to a small SED installation which does not fall wholly within the scope of Annex I of the IED, a change of the nominal capacity leading to an increase of emissions of volatile organic compounds of more than 25 per cent;in relation to all other SED installations which do not fall within the scope of Annex I of the IED, a change of the nominal capacity leading to an increase of emissions of volatile organic compounds of more than 10 per cent;any change in operation of an installation or mobile plant which in itself meets any of the thresholds specified for a Part A activity under Part 1 of Schedule 1.
  • “suspension notice” has the meaning given by regulation 28(1);
  • “variation notice” has the meaning given by regulation 19(5);
  • “volatile organic compound” or “VOC” means any organic compound as well as the fraction of creosote, having at 293.15 K a vapour pressure of 0.01 kPa or more, or having a corresponding volatility under the particular conditions of use;
  • “waste” means waste as defined in Article 3(1) of the Directive ;
  • “waste incineration plant” means any stationary or mobile technical unit and equipment dedicated to the thermal treatment of waste, with or without recovery of the combustion heat generated, through the incineration by oxidation of waste as well as other thermal treatment processes, such as pyrolysis, gasification or plasma process, if the substances resulting from the treatment are subsequently incinerated;
  • “waste co-incineration plant” means any stationary or mobile technical unit whose main purpose is the generation of energy or production of material products and which uses waste as a regular or additional fuel or in which waste is thermally treated for the purpose of disposal through the incineration by oxidation of waste as well as other thermal treatment processes, such as pyrolysis, gasification or plasma process, if the substances resulting from the treatment are subsequently incinerated;
  • “waste incineration installation” means an installation or mobile plant (or part thereof) to which Chapter IV of the IED applies;
  • waste material” means waste that—is household waste, or originates from a source other than household waste but is similar to household waste in terms of its nature or composition;has been separately collected (whether as a single kind of material or two or more kinds of material mixed together) for the primary purpose of preparing it for re-use or recycling; andconsists (whether wholly or in part) of any of the following kinds of material—glass;metal;paper;card;plastic;fibre-based composite material.
  • (2) For the purposes of these Regulations—
  • (a) where an installation or mobile plant has not been put into operation, the person who will have control over the operation of the installation or mobile plant when it is put into operation shall be treated as the operator of the installation or mobile plant;
  • (b) where an installation or mobile plant has ceased to be in operation, the person who holds the permit which applies to the installation or mobile plant shall be treated as the operator of the installation or mobile plant.
  • (3) In these Regulations—
  • (a) a reference to a release into water includes a release into a sewer (within the meaning of Article 2(2) of the Water and Sewerage Services (Northern Ireland) Order 2006[^f00012]);
  • (b) a reference to a Council Directive is a reference to that Directive together with any amendment made before the date on which these Regulations are made.
  • (4) Schedule 1 shall have effect and Part 1 of Schedule 1 shall be interpreted in accordance with the provisions as to interpretation in Parts 1 and 2 of that Schedule.

Interpretation: “best available techniques” or “BAT”

3
  • (1) For the purpose of these Regulations, “best available techniques” or “BAT” means the most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing in principle the basis for emission limit values designed to prevent and, where that is not practicable, generally to reduce emissions and the impact on the environment as a whole, and for the purpose of this definition—
  • (a) “available techniques” means those techniques which have been developed on a scale which allows implementation in the relevant industrial sector, under economically and technically viable conditions, taking into consideration the cost and advantages, whether or not the techniques are used or produced inside the United Kingdom, as long as they are reasonably accessible to the operator;
  • (b) “best” means, in relation to techniques, the most effective in achieving a high general level of protection of the environment as a whole;
  • (c) “techniques” includes both the technology used and the way in which the installation or mobile plant is designed, built, maintained, operated and decommissioned.
  • (2) “BAT reference document” means a document, resulting from the exchange of information organised pursuant to Article 13 of the IED, drawn up for defined activities and describing, in particular, applied techniques, present emissions and consumption levels, techniques considered for the determination of BAT as well as BAT conclusions and any emerging techniques, giving special consideration to the criteria listed in Schedule 2.
  • (3) “BAT conclusions” means a document containing the parts of a BAT reference document laying down the conclusions on BAT, their description, information to assess their applicability, the emission levels associated with BAT, associated monitoring, associated consumption levels and, where appropriate, relevant site remediation measures.
  • (4) “emission levels associated with BAT” means the range of emission levels obtained under normal operating conditions using a best available technique or a combination of BAT, as described in BAT conclusions, expressed as an average over a given period of time, under specified reference conditions.
  • (5) “emerging technique” means a novel technique for an industrial activity that, if commercially developed, could provide either a higher general level of protection of the environment or at least the same level of protection of the environment and higher cost savings than existing BAT.
  • (6) Schedule 2 shall have effect in relation to the determination of BAT.

Fit and proper person

4
  • (1) This regulation applies for the purpose of the discharge of any function under these Regulations which requires the chief inspector to determine whether a person is or is not a fit and proper person to carry out a specified waste management activity.
  • (2) Whether a person is or is not a fit and proper person to carry out a specified waste management activity shall be determined by reference to the fulfilment of the conditions of the permit which apply or will apply to the carrying out of that activity.
  • (3) Subject to paragraph (4), a person shall be treated as not being a fit and proper person if it appears to the chief inspector that—
  • (a) that person or another relevant person has been convicted of a relevant offence;
  • (b) that person has not made, or will not before commencement of the specified waste management activity make, adequate financial provision (either by way of financial security or its equivalent) to ensure that—
  • (i) the obligations (including after-care provisions) arising from the permit in relation to that activity are discharged; and
  • (ii) any closure procedures required by the permit in relation to that activity are followed;
  • (c) that person and all staff engaged in carrying out that activity will not be provided with adequate professional technical development and training; or
  • (d) the management of that activity will not be in the hands of a technically competent person.
  • (4) The chief inspector may, if he considers it proper to do so in any particular case, treat a person as a fit and proper person notwithstanding that paragraph (3)(a) applies in that person’s case.
  • (5) For the purposes of this regulation—
  • (a) “relevant offence” means an offence prescribed for the purpose of Article 3(3)(a) of the Waste and Contaminated Land (Northern Ireland) Order 1997[^f00013]; and
  • (b) the qualifications and experience required of a person for the purposes of Article 3(3)(b) of the Waste and Contaminated Land (Northern Ireland) Order 1997 which are prescribed under Article 3(5) of that Order shall be treated as the qualifications and experience required of a person for the purposes of paragraph (3)(d).
  • (6) In paragraph 3(a), “another relevant person” means, in relation to the holder or proposed holder of a permit—
  • (a) any person who has been convicted of a relevant offence committed—
  • (i) by him in the course of his employment by the holder or proposed holder of the permit; or
  • (ii) in the course of the carrying on of any business by a partnership one of the members of which was the holder or proposed holder of the permit;
  • (b) a body corporate which has been convicted of a relevant offence committed when the holder or proposed holder of the permit was a director, manager, secretary or other similar officer of that body corporate; or
  • (c) where the holder or proposed holder of the permit is a body corporate, a person who is a director, manager, secretary or other similar officer of that body corporate and who—
  • (i) has been convicted of a relevant offence; or
  • (ii) was a director, manager, secretary or other similar officer of another body corporate at a time when a relevant offence of which that other body corporate has been convicted, was committed.

Application to the Crown

5
  • (1) Subject to the provisions of this regulation, these Regulations and the 2003 Landfill Regulations bind the Crown to the full extent authorised or permitted by the constitutional laws of Northern Ireland.
  • (2) No contravention by the Crown of any provision of these Regulations or the 2003 Landfill Regulations shall make the Crown criminally liable under regulation 36 of these Regulations or under regulation 17 of the 2003 Landfill Regulations and no proceedings may be taken against the Crown under regulation 37 of these Regulations but the High Court may, on the application of the enforcing authority charged with enforcing that provision, declare unlawful any act or omission of the Crown which constitutes such a contravention.
  • (3) Notwithstanding anything in paragraph (2), the provisions of these Regulations and the 2003 Landfill Regulations shall apply to persons in the public service of the Crown as they apply to other persons.
  • (4) If the Secretary of State certifies that it appears to him, as respects any Crown premises and any specified powers of entry exercisable under regulation 30, that it is requisite or expedient that, in the interests of national security, the powers of entry should not be exercisable in relation to the premises, those powers shall not be exercisable in relation to those premises; and in this paragraph “specified” means specified in the certificate and “Crown premises” means premises held or used by or on behalf of the Crown.
  • (5) Any reference to the Crown in this regulation includes the Crown in right of Her Majesty’s Government in the United Kingdom.

Applications

6
  • (1) An enforcing authority may require any application or type of application made to it under any provision of these Regulations to be made on a form made available by the enforcing authority.
  • (2) A form made available by an enforcing authority under paragraph (1) shall specify the information required by the enforcing authority to determine the application, which shall include any information required to be contained in the application by the provision of these Regulations under which the application is made.
  • (3) Any application made under these Regulations may, with the agreement of the enforcing authority, be sent to the enforcing authority electronically.
  • (4) Where an application which is required to be accompanied by a fee, map or plan is sent electronically, the fee, map or plan may be sent to the enforcing authority separately from the application but the application shall not be treated as having been received by the enforcing authority until the fee, map or plan has also been received.
  • (5) An application made under these Regulations may be withdrawn at any time before it is determined.

Discharge and scope of functions

7
  • (1) This regulation determines the authority by whom the functions conferred or imposed by these Regulations on an enforcing authority are exercisable and the purposes for which they are exercisable.
  • (2) Those functions, in their application to a Part A installation or Part A mobile plant, shall be functions of the chief inspector and shall be exercisable for the purpose of—
  • (a) achieving a high level of protection of the environment taken as a whole by, in particular, preventing or, where that is not practicable, reducing emissions into the air, water and land; and
  • (b) where appropriate, ensuring that cost-benefit analyses are carried out in accordance with Article 14(5) of the Energy Efficiency Directive and Schedule 13A.
  • (3) Those functions, in their application to a Part B installation or Part B mobile plant, shall be functions of the chief inspector and, subject to paragraph (5), shall be exercisable for the purpose of—
  • (a) preventing or, where that is not practicable, reducing emissions into the air; and
  • (b) where appropriate, ensuring that cost-benefit analyses are carried out in accordance with Article 14(5) of the Energy Efficiency Directive and Schedule 13A.
  • (4) Those functions, in their application to a Part C installation, shall be functions of the district council in whose district the installation is (or will be) situated and, subject to paragraph (5), shall be exercisable for the purpose of—
  • (a) preventing or, where that is not practicable, reducing emissions into the air; and
  • (b) where appropriate, ensuring that cost-benefit analyses are carried out in accordance with Article 14(5) of the Energy Efficiency Directive and Schedule 13A.
  • (5) The functions conferred or imposed by these Regulations in relation to a SED installation shall be exercisable for the purpose of preventing or reducing emissions of volatile organic compounds into air, soil and water as well as preventing the inclusion or reducing the amount of solvents contained in any product and, where appropriate, ensuring that cost-benefit analyses are carried out in accordance with Article 14(5) of the Energy Efficiency Directive and Schedule 13A.
  • (6) Those functions, in their application to a Part C mobile plant, shall be functions of—
  • (a) where the operator of the mobile plant has their principal place of business in Northern Ireland, the district council in whose district that place of business is;
  • (b) where the operator of the mobile plant has their principal place of business outside of Northern Ireland and the mobile plant is not covered by a permit, the district council in whose district the plant is first operated or, where the plant has not been operated in Northern Ireland, the district council in whose district it is intended by the operator that the plant should first be operated;
  • (c) where the operator has their principal place of business outside of Northern Ireland and the mobile plant is covered by a permit, the district council which granted the permit,

and shall be exercisable for the purpose of preventing or, where that is not practicable, reducing emissions into the air and, where appropriate, ensuring that cost-benefit analyses are carried out in accordance with Article 14(5) of the Energy Efficiency Directive and Schedule 13A.

  • (7) The Department may, as respects functions under these Regulations exercisable by a district council specified in a direction, direct that those functions shall be exercised instead by the chief inspector while the direction remains in force or during such period as may be specified in the direction.
  • (8) A transfer of functions under paragraph (7) to the chief inspector relating to Part C installations or Part C mobile plant does not make them exercisable by the chief inspector for any other purpose than that mentioned in paragraphs (4), (5) and (6).
  • (9) The Department may, as respects functions under these Regulations exercisable by the chief inspector in respect of Part B installations specified in a direction, direct that those functions shall be exercised instead by a district council while the direction remains in force or during such period as may be specified in the direction.
  • (10) A direction under paragraph (7) may transfer functions exercisable by a district council in relation to all or certain types of installations or mobile plant (a “general direction”) or in relation to a specific installation or mobile plant specified in the direction (a “specific direction”) but a direction under paragraph (9) may only be a specific direction.
  • (11) A direction under paragraph (7) or (9) may include such saving and transitional provisions as the Department considers necessary or expedient.
  • (12) The Department, on giving or withdrawing a general direction under paragraph (7), shall—
  • (a) serve notice of it on the chief inspector and on the district councils affected by the direction; and
  • (b) cause notice of it to be published as soon as practicable in the Belfast Gazette and in at least two newspapers circulating in the district of each district council affected by the direction,

and any such notice shall specify the date on which the direction is to take (or took) effect and (where appropriate) its duration.

  • (13) The Department, on giving or withdrawing a specific direction under paragraph (7) or (9), shall—
  • (a) serve notice on the chief inspector, the district council and the operator or the person appearing to the Department to be the operator of the installation or mobile plant affected; and
  • (b) cause notice of it to be published in the Belfast Gazette and in at least two newspapers circulating in the district council’s district,

and any such notice shall specify the date on which the direction is to take (or took) effect and (where appropriate) its duration.

  • (14) The requirements of paragraph (12)(b) or paragraph (13)(b) shall not apply in any case where, in the opinion of the Secretary of State, the publication of the notice in accordance with that sub-paragraph would be contrary to the interests of national security.
  • (15) It shall be the duty of the chief inspector to follow developments in BAT, and the publication of any new or updated BAT conclusions and he shall make that information available to the public concerned.
  • (16) The chief inspector shall have regard to any guidance ... which assists in encouraging the development and application of emerging techniques.
  • (17) Schedules 8 to 13A shall have effect.

Appointment of chief inspector and other inspectors

8
  • (1) The Department may appoint as inspectors (under whatever title the Department may determine) such persons having such suitable qualifications as the Department thinks necessary for carrying these Regulations into effect, and may terminate any appointment made under this paragraph.
  • (2) The Department may make to, or in respect of, any person so appointed such payments by way of remuneration, allowances or otherwise as the Department may determine.
  • (3) The Department shall constitute one of the inspectors appointed under paragraph (1) to be the chief inspector.
  • (4) The functions conferred or imposed by or under these Regulations on the chief inspector as the enforcing authority may, to any extent, be delegated by him to any other inspector appointed under paragraph (1).
  • (5) A district council may appoint as inspectors (under whatever title the council may determine) such persons having suitable qualifications as the council thinks necessary for carrying these Regulations into effect in the council’s district, and may terminate any appointment made under this paragraph.
  • (6) An inspector shall not be liable in any civil or criminal proceedings for anything done in the performance of their functions under Part 3 if the court is satisfied that the act was done in good faith and that there were reasonable grounds for doing it.

PART 2 — PERMITS

Permits: requirement for a permit

9
  • (1) No person shall operate an installation or mobile plant after the prescribed date except under and to the extent authorised by a permit granted by the enforcing authority.
  • (2) In paragraph (1), the “prescribed date” means the appropriate date set out in or determined in accordance with Schedule 3.

Permits: general provisions

10
  • (1) An application for a permit to operate an installation or mobile plant shall be made to the enforcing authority in accordance with Part 1 of Schedule 4 and, where appropriate, Schedule 13A and shall be accompanied by any fee prescribed in respect of the application under regulation 25.
  • (2) Subject to paragraphs (3) to (4A) , where an application is duly made to the enforcing authority, the enforcing authority shall either grant the permit, subject to any conditions which may be imposed pursuant to regulations 11, 12, 13, 14 ,14A or 15 of , or Schedule 13A to, these Regulations, and regulation 8 of the 2003 Landfill Regulations, or refuse the permit.
  • (3) A permit shall not be granted if the enforcing authority considers that the applicant will not be the person who will have control over the operation of the installation or mobile plant concerned after the grant of the permit, or will not ensure that the installation or mobile plant is operated so as to comply with any conditions which would be included in the permit.
  • (4) In the case of an application for a permit that will authorise the carrying out of a specified waste management activity at an installation or by means of mobile plant, the permit shall not be granted unless—
  • (a) the chief inspector is satisfied that the applicant is a fit and proper person to carry out that activity; and
  • (b) in the case of an installation where the use of the application site for the carrying out of the activity requires planning permission granted under the Planning (Northern Ireland) Order 1991—
  • (i) such planning permission is in force in relation to the use of the land; or
  • (ii) a certificate under Article 83A of that Order has been issued in respect of that use of the land.
  • (4A) In the case of an application for a permit to operate an installation or mobile plant carrying out only an activity falling within head (b) of Part C of section 1.1 of Schedule 1—
  • (a) any permit granted pursuant to the application shall only contain conditions required for complying with paragraphs 13 to 18 of Schedule 13A; and
  • (b) regulations 11, 12, 14 and 16 shall not apply.
  • (5) A permit may authorise the operation of—
  • (a) more than one Part A installation or Part A mobile plant on the same site operated by the same operator;
  • (b) more than one Part B installation on the same site operated by the same operator;
  • (c) more than one Part B mobile plant operated by the same operator;
  • (d) more than one Part C installation on the same site operated by the same operator; or
  • (e) more than one Part C mobile plant operated by the same operator,

but may not otherwise authorise the operation of more than one installation or mobile plant.

  • (6) A permit authorising the operation of a Part A mobile plant may only authorise the operation of that plant on a site specified in the permit and only one site may be specified in each such permit (accordingly, the operation of the plant on a different site shall require a distinct permit).
  • (7) A permit authorising the operation of an installation or Part A mobile plant shall include a map or plan showing the site of the installation or mobile plant covered by the permit and, in the case of an installation, the location of the installation on that site.
  • (8) A permit shall be transferred only in accordance with regulation 20 or 21 and shall cease to have effect only in accordance with regulation 21, 22, 23, 24 or paragraph (9).
  • (9) Where—
  • (a) the conditions of a permit have been varied under regulation 19 or affected by a partial transfer, surrender or revocation under regulations 20 to 24; or
  • (b) there is more than one permit applying to installations on the same site operated by the same operator or to mobile plant operated by the same operator,

the enforcing authority may replace the permit or permits with a consolidated permit applying to the same installations or mobile plant and subject to the same conditions as the permit or permits being replaced.

  • (10) Parts 1 and 2 of Schedule 4 shall have effect subject to Part 3 of that Schedule.

Conditions of permits: general principles

11
  • (1) When determining the conditions of a permit, the enforcing authority shall take account of the general principles set out in paragraph (2) and, in the case of a permit authorising the operation of a Part A installation or Part A mobile plant, the additional general principles set out in paragraph (3).
  • (2) The general principles referred to in paragraph (1) are that installations and mobile plant must be operated in such a way that—
  • (a) all the appropriate preventative measures are taken against pollution, in particular through the application of BAT; and
  • (b) no significant pollution is caused.
  • (3) The additional general principles referred to in paragraph (1) in relation to a permit authorising the operation of a Part A installation or a Part A mobile plant are that the installation or mobile plant must be operated in such a way that—
  • (a) BAT conclusions shall be the reference for setting permit conditions;
  • (b) waste production is avoided in accordance with the Directive; and, where waste is produced, it is in order of priority and in accordance with the Directive, prepared for re-use, recycled, recovered, or where that is technically and economically impossible, it is disposed of while avoiding or reducing any adverse impact on the environment;
  • (c) energy is used efficiently;
  • (d) the necessary measures are taken to prevent accidents and limit their consequences; and
  • (e) upon the definitive cessation of activities, the necessary assessments and measures are taken to avoid any pollution risk and to return the site of the installation or mobile plant to a satisfactory state.
  • (4) The Department may establish rules under which the chief inspector may set stricter permit conditions than those achievable by the use of BAT as described in the BAT conclusions (in addition to the circumstances described in regulation 12(4)).
  • (5) Where the chief inspector sets permit conditions on the basis of a BAT, not described in any of the relevant BAT conclusions, the chief inspector shall ensure that—
  • (a) that technique is determined by giving special consideration to the criteria listed in Schedule 2; and
  • (b) the requirements of regulations 12(3) and 13(2) to (4) are complied with.
  • (6) Where the relevant BAT conclusions do not contain emission levels associated with the BAT, the chief inspector shall ensure that the technique referred to in paragraph (5) ensures a level of environmental protection equivalent to the BAT described in the BAT conclusions.
  • (7) Where an activity or a type of production process carried out within an installation is not covered by any BAT conclusions, or where those conclusions do not address all the potential environmental effects of the activity or process, the chief inspector shall, after prior consultations with the operator, set the permit conditions on the basis of the BAT that he has determined for the activities or processes concerned, by giving special consideration to the criteria listed in Schedule 2.
  • (8) The monitoring requirements referred to in regulation 13(6)(e) and (f) shall, where applicable, be based on the conclusions on monitoring as described in the BAT conclusions.

Conditions of permits: specific conditions for all installations and mobile plant

12
  • (1) Subject to paragraphs (11) and (12) and regulations 14A, 15 and 16, there shall be included in all permits such conditions as the enforcing authority considers appropriate to ensure compliance with paragraphs (2) to (7).
  • (2) Subject to paragraph (6), a permit shall include emission limit values for pollutants, in particular those listed in Schedule 5, likely to be emitted from the installation or mobile plant in significant quantities, having regard to their nature and, in the case of emissions from a Part A installation or a Part A mobile plant, their potential to transfer pollution from one environmental medium to another.
  • (3) The emission limit values required by paragraph (2)—
  • (a) may, where appropriate, apply to groups of pollutants rather than to individual pollutants; and
  • (b) shall normally apply at the point at which the emissions leave the installation or mobile plant, any dilution being disregarded when determining those values.
  • (4) Where an environmental quality standard requires stricter emission limit values than those that would be required from the application of BAT, the enforcing authority shall require that those stricter emission limit values are imposed.
  • (5) The emission limit values required by paragraph (2) may, where appropriate, be supplemented or replaced by equivalent parameters or technical measures ensuring an equivalent level of environmental protection.
  • (6) Where emissions of a pollutant from an installation are the subject of conditions imposed pursuant to regulation 10(2) and (3) of the Greenhouse Gas Emissions Trading Scheme Regulations 2005[^f00014], the permit shall not include an emission limit value, equivalent parameter or technical measure for those emissions unless the enforcing authority considers that the value, parameter or measure is necessary to ensure that no significant local pollution is caused.
  • (7) For activities listed in Annex I to Directive 2003/87/EC[^f00015] as last amended by Directive (EU) 2018/410 of the European Parliament and of the Council , the competent authority may choose not to impose requirements relating to energy efficiency in respect of combustion units or other units emitting carbon dioxide on the site.
  • (8) Paragraphs (6) and (7) shall not apply where the relevant installation is an excluded installation for the purposes of regulation 11 of the Greenhouse Gas Emissions Trading Scheme Regulations 2005.
  • (9) Subject to paragraph (10), there is implied in every permit a condition that, in operating the installation or mobile plant, the operator shall use BAT for preventing or, where that is not practicable, reducing emissions from the installation or mobile plant.
  • (10) The obligation implied by virtue of paragraph (9) shall not apply in relation to any aspect of the operation of the installation or mobile plant in question which is regulated by a condition imposed under any other paragraph of this regulation.
  • (11) A permit may, without prejudice to the generality of the previous provisions of this regulation, include conditions—
  • (a) imposing limits on the amount or composition of any substance produced or utilised during the operation of the installation or mobile plant in any period;
  • (b) which are supplemental or incidental to other conditions contained in the permit.
  • (12) The Department may give directions to enforcing authorities—
  • (a) as to the specific conditions which are, or are not, to be included in all permits, in permits of a specified description or in any particular permit;
  • (b) as to the objectives which are to be achieved by conditions included in such permits,

and the enforcing authorities shall include in such permits such conditions as are specified or required to comply with such directions.

  • (13) The enforcing authority may rely on arrangements referred to in, and sanctioned by, guidance issued by the Department under regulation 41 to secure a particular result, as an alternative to including a condition in the permit pursuant to this regulation or regulation 8 (conditions to be included in landfill permits) of the 2003 Landfill Regulations.

Conditions of permits: specific conditions for Part A installations and Part A mobile plant

13
  • (1) The chief inspector shall include in all permits authorising any Part A installation or Part A mobile plant such other conditions as appear to the chief inspector to be appropriate, when taken together with the condition implied by regulation 12(8), for the purpose of ensuring a high level of protection for the environment as a whole, taking into account, in particular, the general principles set out in regulation 11.
  • (2) Without prejudice to regulation 12(4), the emission limit values referred to in regulation 12(2) and the equivalent parameters and technical measures referred to in regulation 12(5) shall be based on BAT, without prescribing the use of any technique or specific technology. When setting the emission limit values the chief inspector—
  • (a) shall ensure that, under normal operating conditions, emissions do not exceed the emission levels associated with BAT as laid down in the BAT conclusions through either—
  • (i) setting emission limit values that do not exceed the emission levels associated with BAT. Those emission limit values shall be expressed for the same or shorter periods of time and under the same reference conditions as those emission levels associated with BAT; or
  • (ii) setting different emission limit values than those referred to under sub-paragraph (a) in terms of values, periods of time and reference conditions, and at least annually, assessing the results of emission monitoring in order to ensure that emissions under normal operating conditions have not exceeded the emission levels associated with BAT; and
  • (b) may take into account the effect of a waste water treatment plant when determining the emission limit values applying in relation to indirect releases into water from a Part A installation or Part A mobile plant provided that an equivalent level of protection of the environment as a whole is maintained and that taking such treatment into account does not lead to higher levels of pollution.
  • (3) By way of derogation from paragraph (2), but without prejudice to regulation 12(4), the chief inspector may, in specific cases, set less strict emission limit values. In such cases—
  • (a) an assessment must show that the achievement of emission levels associated with BAT as described in BAT conclusions would lead to disproportionately higher costs compared to the environmental benefits due to—
  • (i) the geographical location or the local environmental conditions of the installation concerned; or
  • (ii) the technical characteristics of the installation concerned;
  • (b) the chief inspector shall document in an annex to the permit conditions the reasons for the application of sub-paragraph (a) including the result of the assessment and the justification for the conditions imposed;
  • (c) the emission limit values set in accordance with sub-paragraph (a) shall, however, not exceed the emission limit values set out in Annexes V and VI to the IED, where applicable; and
  • (d) the chief inspector shall re-assess the application of sub-paragraph (a) as part of each review of the permit conditions pursuant to regulation 17.
  • (4) The chief inspector may grant temporary derogations from the requirements of regulation 11(2)(a) and paragraph (2) of this regulation for the testing and use of emerging techniques for a total period of time not exceeding nine months, provided that after the period specified, either the technique is stopped or the activity achieves at least the emission levels associated with BAT.
  • (5) The chief inspector shall include conditions—
  • (a) requiring the operator to inform the enforcing authority, immediately, of any incident or accident which causes or may cause significant pollution and to immediately take all appropriate measures to limit the environmental consequences and to prevent further possible incidents or accidents; and
  • (b) in the event of a breach of any permit condition, requiring the operator to—
  • (i) inform the regulator;
  • (ii) take the measures necessary to ensure that compliance is restored within the shortest possible time; and
  • (c) in the event of a breach of a permit condition which poses an immediate danger to human health or threatens to cause an immediate significant adverse effect on the environment, immediately suspend the operation of the installation or mobile plant or the relevant part of it until compliance with the permit conditions has been restored.
  • (6) The chief inspector shall also include conditions—
  • (a) aimed at minimising long distance and transboundary pollution;
  • (b) ensuring appropriate protection of the soil and groundwater and appropriate management of waste generated by the installation or mobile plant, including appropriate requirements for the regular maintenance and surveillance of measures taken to prevent emissions to soil and groundwater and appropriate requirements concerning the periodic monitoring of soil and groundwater in relation to relevant hazardous substances likely to be found at the site and having regard to the possibility of soil and groundwater contamination at the site of the installation. Periodic monitoring shall be carried out at least once every five years for groundwater and ten years for soil, unless such monitoring is based on a systematic appraisal of the risk of contamination;
  • (c) relating to the periods when the installation or mobile plant is not operating normally and there is a risk that the environment may be adversely affected during such periods, including, in particular, conditions relating to the start up of operations, leaks, malfunctions and momentary stoppages;
  • (d) setting out the steps to be taken prior to the operation of the installation or mobile plant and after the definitive cessation of operations;
  • (e) setting out suitable emission monitoring requirements, specifying the measurement methodology, frequency and the evaluation procedure, ensuring that the operator supplies the chief inspector with the data required to check compliance with the permit and where emission limit values are set in accordance with paragraph (2)(a)(ii), requiring that the results of emission monitoring are available for the same periods of time and reference conditions as for the emission levels associated with BAT; and
  • (f) requiring the operator to supply the chief inspector regularly and at least annually with the results of the monitoring of emissions, the basis of those results and other specified data that enables the chief inspector to verify compliance with the permit conditions and, where emission limit values are set in accordance with paragraph (2)(a)(ii), requiring that a written summary of the results is supplied which allows a comparison with the emission levels associated with BAT.
  • (7) A permit authorising the operation of a Part A installation or Part A mobile plant may include a condition (an “off-site condition”) requiring the operator to carry out works or do other things in relation to land not forming part of the site of the installation or mobile plant notwithstanding that he is not entitled to carry out the works or do the things, and any person whose consent would be required shall grant, or join in granting, the operator such rights in relation to that land as will enable the operator to comply with any requirements imposed on him by the permit.
  • (8) Schedule 6 shall have effect in relation to compensation where rights are granted pursuant to paragraph (7).
  • (9) A permit which authorises any activity relating to waste oils shall contain conditions ensuring that, so far as technically feasible and economically viable—
  • (a) waste oils having different characteristics are not mixed; and
  • (b) waste oils are not mixed with other kinds of waste or substances, if such mixing would impede their treatment.
  • (10) In paragraph (9), “waste oils” and “treatment” have the same meanings as in the Directive .
  • (11) A permit granted or varied on or after 1st April 2015 for an activity described in Chapter 5 of Part 1 of Schedule 1, or in Section 6.8 of Chapter 6 of that Part, shall contain any conditions as appear to the chief inspector to be appropriate to ensure that no separately collected food waste is mixed with any other waste or any material, to the extent that mixing would hamper future recycling.
  • (12) A permit granted or varied before 1st April 2015 for an activity described in Chapter 5 of Part 1 of Schedule 1, or in Section 6.8 of Chapter 6 of that Part, and which continues in existence after that date, shall be deemed to contain the condition that no separately collected food waste is mixed with any other waste or any material, to the extent that mixing would hamper future recycling.

Conditions of permits: specific conditions for Part B and C installations and mobile plant

14
  • (1) The enforcing authority shall include in all permits authorising any Part B or Part C installation or Part B or Part C mobile plant, such other conditions as appear to the enforcing authority to be appropriate, when taken together with the condition implied by regulation 12(8), for the purpose of preventing or, where that is not practicable, reducing emissions into the air, taking into account, in particular, the general principles set out in regulation 11(2).
  • (2) Subject to regulation 12(4), in the case of Part B or Part C installations and Part B or Part C mobile plant, the emission limit values required by regulation 12(2) shall be based on BAT for the description of installation or mobile plant concerned but shall take account of the technical characteristics of the particular installation or mobile plant being permitted and, in the case of an installation, its geographical location and the local environmental conditions.
  • (3) Where a Part B or Part C mobile plant authorised by a permit is used to carry out an activity on the site of an installation which is authorised by a separate permit then, if different requirements are imposed in the permits in respect of the carrying out of the activity, the requirements in the permit authorising the operation of the installation shall prevail in the event of any inconsistency.

Conditions of permits: Department’s notice in relation to emissions into water

15
  • (1) In the case of a Part A installation or Part A mobile plant the Department may, at any time, give notice to the chief inspector specifying the emission limit values or conditions (not containing emission limit values) which it considers are appropriate in relation to preventing or reducing emissions into water.
  • (2) Where a notice under paragraph (1) specifies emission limit values, the emission limit values required by regulation 12(2), in relation to emissions into water from the installation or mobile plant concerned, shall be those specified in that notice or such stricter emission limit values as may be determined by the chief inspector in accordance with the application of BAT or required by regulation 12(4).
  • (3) Where a notice under paragraph (1) specifies conditions in relation to emissions into water from an installation or mobile plant, the permit authorising the operation of that installation or mobile plant shall include those conditions or any more onerous conditions dealing with the same matters as the chief inspector considers are appropriate.

General binding rules

16
  • (1) The Department may make rules (“general binding rules”) containing requirements applying to certain types of installation or mobile plant.
  • (2) The Department shall only make general binding rules under this regulation applying to Part A installations or Part A mobile plant, if it is satisfied that the operation of such installations or mobile plant under the rules will result in the same high level of environmental protection and integrated prevention and control of pollution, as would result from the operation of the installations or mobile plant under the conditions that would be included in the permits for those installations or mobile plant, pursuant to regulations 12 and 13 if the rules did not apply.
  • (3) In the case of a Part A installation or Part A mobile plant, general binding rules shall be based on BAT, without prescribing the use of any technique or specific technology, in order to ensure compliance with Articles 14 and 15 of the IED.
  • (4) The Department shall ensure that general binding rules applying to Part A installations or Part A mobile plant are updated to take into account any developments in BAT and in order to ensure compliance with Article 21 of the IED.
  • (5) Where the Department makes general binding rules an enforcing authority may, at the request of the operator, include, in a permit authorising the operation of an installation or mobile plant covered by the rules, a condition (a “general binding rules condition”) providing that the aspects of the operation of the installation or mobile plant covered by the requirements in the rules shall be subject to those requirements instead of to conditions included in the permit pursuant to regulations 12 to 14.
  • (6) Where a permit includes a general binding rules condition the requirements in the general binding rules shall be treated as if they were conditions of the permit for the purpose of regulations 26, 27 and 36(1)(b).
  • (7) The Department may vary general binding rules by means of a notice of variation specifying the variations and the date on which the variations are to take effect, which shall not be less than 3 months after the date on which notice of the variation is given in the Belfast Gazette pursuant to paragraph (11)(c).
  • (8) The Department may revoke general binding rules by means of a notice of revocation.
  • (9) Where aspects of the operation of an installation or mobile plant are covered by the requirements in general binding rules which are revoked, the enforcing authority shall vary the permit authorising the operation of the installation or mobile plant under regulation 19, to delete the general binding rules condition and to insert the conditions that will be required by regulations 11 to 14 when the requirements in the general binding rules no longer apply.
  • (10) Where the Department revokes general binding rules, the requirements in the general binding rules shall continue to be treated under paragraph (6) as if they were conditions of a permit until the variations of the permit required by paragraph (9) take effect.
  • (11) Where the Department makes, varies or revokes general binding rules it shall—
  • (a) serve a copy of the rules, notice of variation or notice of revocation on the chief inspector and all district councils;
  • (b) publish the rules, notice of variation or notice of revocation in such manner as it considers appropriate for the purpose of bringing the rules or notice to the attention of operators likely to be affected by them and, in the case of Part A installations or Part A mobile plant, the rules shall contain a reference to the IED; and
  • (c) give notice of the making, variation or revocation of the rules in the Belfast Gazette.

Review of conditions of permits

17
  • (1) Enforcing authorities shall periodically review the conditions of permits and may do so at any time.
  • (2) Without prejudice to paragraph (1), a review of a permit under this regulation shall be carried out where—
  • (a) the pollution caused by the installation or mobile plant covered by the permit is of such significance that the existing emission limit values of the permit need to be revised or new emission limit values need to be included in the permit;
  • (b) substantial changes in BAT make it possible to reduce emissions from the installation or mobile plant significantly without imposing excessive costs;
  • (c) the operational safety of the activities carried out in the installation or mobile plant requires other techniques to be used; or
  • (d) it is necessary to comply with a new or revised environmental quality standard.
  • (3) In relation to Part A installations and Part A mobile plant, at the request of the chief inspector, the operator shall submit all the information necessary for the purpose of reconsidering the permit conditions, including, in particular, results of emission monitoring and other data, that enables a comparison of the operation of the installation or mobile plant with the BAT described in the applicable BAT conclusions and with the emission levels associated with BAT.
  • (4) When reconsidering permit conditions for Part A installations or Part A mobile plant, the chief inspector shall—
  • (a) use any information resulting from monitoring or inspections;
  • (b) within four years of publication of decisions on BAT conclusions relating to the main activity of an installation or mobile plant, ensure that all the permit conditions for the installation or mobile plant concerned are considered and, if necessary, updated to ensure compliance with the IED; and
  • (c) take into account all the new or updated BAT conclusions, applicable to the installation or mobile plant, since the permit was granted or last reconsidered.

Proposed change in the operation of an installation or mobile plant

18
  • (1) Subject to paragraph (4), where an operator of an installation or mobile plant which is permitted under these Regulations proposes to make a change in the operation of that installation or mobile plant the operator shall, at least 14 days before making the change, notify the enforcing authority.
  • (2) A notification under paragraph (1) shall be in writing and shall contain a description of the proposed change in the operation of the installation or mobile plant.
  • (3) An enforcing authority shall, by notice in writing served on the operator, acknowledge receipt of any notification received under paragraph (1).
  • (4) Paragraph (1) shall not apply where the operator applies under regulation 19(2) for the variation of the conditions of his permit before making the proposed change and the application contains a description of the change.

Variation of conditions of permits

19
  • (1) The enforcing authority may at any time vary the conditions of a permit and shall do so if it appears to the enforcing authority at that time, whether as a result of a review under regulation 17, a notification under regulation 15 or regulation 18 or otherwise, that regulations 11, 12, 13 , 14 and 14A of these Regulations or regulation 8 of the 2003 Landfill Regulations require conditions to be included which are different from the subsisting conditions.
  • (2) An operator of an installation or mobile plant which is permitted under these Regulations may apply to the enforcing authority for the variation of the conditions of his permit.
  • (3) An application under paragraph (2) shall be made in accordance with Part 1 of Schedule 7 and, where appropriate, Schedule 13A and shall be accompanied by any fee prescribed in respect of the application in accordance with regulation 25; and Schedule 7 shall have effect with respect to such applications.
  • (4) Where an application is duly made to the enforcing authority under paragraph (2), the enforcing authority shall determine, in accordance with regulations 11, 12, 13, 14 ,14A and 17 of , or Schedule 13A to, these Regulations or regulation 8 of the 2003 Landfill Regulations, whether to vary the conditions of the permit.
  • (5) Where the enforcing authority decides to vary the conditions of the permit, whether on an application under paragraph (2) or otherwise, it shall serve a notice in writing on the operator (a “variation notice”) specifying the variations of the conditions of the permit and the date or dates on which the variations are to take effect and, unless the notice is withdrawn, the variations specified in the notice shall take effect on the date or dates so specified.
  • (5A) Where the enforcing authority decides to vary the conditions of a permit for an installation or mobile plant carrying out only an activity falling within head (b) of Part C of section 1.1 of Part 1 of Schedule 1—
  • (a) the variation notice shall only contain conditions required for complying with paragraphs 13 to 18 of Schedule 13A; and
  • (b) regulations 11, 12, 14 and 16 shall not apply.
  • (6) A variation notice served under paragraph (5) shall, unless served for the purpose of determining an application under paragraph (2), require the operator to pay, within such period as may be specified in the notice, any fee prescribed in respect of the variation notice in accordance with regulation 25.
  • (7) Where the enforcing authority decides on an application under paragraph (2) not to vary the conditions of the permit, it shall give notice of its decision to the operator in writing.
  • (8) Parts 1, 2 and 3 of Schedule 7 shall have effect subject to Part 4 of that Schedule.
  • (9) This regulation and Schedule 7 apply to the variation of any provision other than a condition which is contained in a permit as they apply to the variation of a condition.

Transfer of permits

20
  • (1) Where the operator of an installation or mobile plant wishes to transfer their permit, in whole or in part, to another person (“the proposed transferee”) the operator and the proposed transferee shall jointly make an application to the enforcing authority to effect the transfer.
  • (2) An application under paragraph (1) shall be accompanied by the permit and any fee prescribed in respect of the transfer under regulation 25 and shall contain—
  • (a) the operator’s and the proposed transferee’s telephone number and address and, if different, any address to which correspondence relating to the application should be sent; and
  • (b) in the case of an application to effect the transfer of a permit or part of a permit that authorises the carrying out of a specified waste management activity, any information which the applicants wish the chief inspector to take into account when considering whether the transferee is a fit and proper person to carry out that activity.
  • (3) Where the operator wishes to retain part of their permit (a “partial transfer”), an application under paragraph (1) shall—
  • (a) identify the installation or mobile plant to which the transfer applies (the “transferred unit”); and
  • (b) where the transfer applies to the operation of an installation or Part A mobile plant, contain a map or plan identifying the part of the site used for the operation of that installation or mobile plant (the “identified part of the site”).
  • (4) Subject to paragraph (5), the enforcing authority shall effect the transfer unless it considers that the proposed transferee will not be the person who will have control over the operation of the installation or mobile plant covered by the transfer after the transfer is effected or will not ensure compliance with the conditions of the transferred permit.
  • (5) In the case of an application to effect the transfer of a permit or part of a permit which authorises the carrying out of a specified waste management activity, the chief inspector shall only effect the transfer if the chief inspector is satisfied that the proposed transferee is a fit and proper person to carry out that activity.
  • (6) The enforcing authority shall effect a transfer under this regulation by—
  • (a) in the case of a partial transfer—
  • (i) issuing a new permit, to the proposed transferee for that part of the installation or mobile plant to which the transfer relates; and
  • (ii) returning the original permit to the operator, endorsed to record the transfer in respect of the transfer and any variation of the permit conditions; or
  • (b) in the case of a transfer of the whole permit, causing the permit to be endorsed with the name and other particulars of the proposed transferee as the operator of the installation or mobile plant concerned,

and the transfer shall take effect from such date as may be agreed with the applicants and specified in the endorsement and, in the case of a partial transfer, the new permit.

  • (7) In the case of a partial transfer effected under this regulation, the conditions included in the new permit and original permit after the transfer shall be the same as the conditions included in the original permit immediately before the transfer in so far as they are relevant to any installation, site and mobile plant covered by the new permit or the original permit, but subject to such variations as, in the opinion of the enforcing authority, are necessary to take account of the transfer.
  • (8) If within the period of two months beginning with the date on which the enforcing authority receives an application under paragraph (1), or within such longer period as the enforcing authority and the applicants may agree in writing, the enforcing authority has neither effected the transfer nor given notice in writing to the applicants that it has rejected the application, the application shall, if the applicants notify the enforcing authority in writing that they treat the failure as such, be deemed to have been refused at the end of that period or that longer period.
  • (9) The enforcing authority may, by notice in writing, require the operator or the proposed transferee to furnish such further information specified in the notice, within the period so specified, as the enforcing authority may require for the purpose of determining an application under this regulation.
  • (10) Where a notice is served on an operator or proposed transferee under paragraph (9)—
  • (a) for the purpose of calculating the period of two months specified in paragraph (8), no account shall be taken of the period beginning with the date on which notice is served and ending on the date on which the information specified in the notice is furnished; and
  • (b) if the specified information is not furnished within the period specified, the application shall, if the enforcing authority gives notice in writing to the operator and proposed transferee that it treats the failure as such, be deemed to have been withdrawn at the end of that period.

Death of a permit holder

21
  • (1) This regulation applies if—
  • (a) a permit is held by an individual (A); and
  • (b) A dies.
  • (2) On the death of A, the permit—
  • (a) shall be property forming part of A’s personal estate; and
  • (b) shall continue to have effect subject to—
  • (i) the same conditions that applied at the time of A’s death; and
  • (ii) the condition mentioned in paragraph (3).
  • (3) The permit shall be read as if it contained the following condition—
  • “As soon as is practicable after administration of the estate of A, the personal representative shall notify the regulator that the permit has vested in them.”
  • (4) The permit shall cease to have effect 6 months after the date on which A dies, unless it is transferred in accordance with regulation 20, by the personal representative, before the end of that period.

Surrender of a permit for a Part A installation or Part A mobile plant

22
  • (1) Subject to paragraph (2), this regulation applies where an operator of a Part A installation or Part A mobile plant ceases or intends to cease operating the installation (in whole or in part) or the mobile plant.
  • (2) This regulation does not apply in relation to that part of any installation or mobile plant where an activity falling within paragraphs (b), (d), (g) or (h) of Part A of section 5.1 of Part 1 of Schedule 1 is carried out.
  • (3) Where this regulation applies, an operator may—
  • (a) if they have ceased or intend to cease operating all of the installations and mobile plant covered by the permit, apply to the chief inspector to surrender the whole permit; or
  • (b) in any other case, apply to the chief inspector to surrender the permit in so far as it authorises the operation of the installation or mobile plant (“the surrender unit”) which they have ceased or intend to cease operating (a “partial surrender”).
  • (4) An application under paragraph (3) shall be accompanied by any fee prescribed in respect of the application under regulation 25, and shall contain the following information—
  • (a) the operator’s telephone number and address and, if different, any address to which correspondence relating to the application should be sent;
  • (b) in the case of a partial surrender, a description of the surrender unit and a map or plan identifying the part of the site used for the operation of the surrender unit;
  • (c) a site report describing the condition of the site, or the identified part of the site, identifying, in particular, any changes in the condition of the site as described in the site report, and where applicable, the baseline report, and including an assessment of any contamination caused to the soil or groundwater by relevant hazardous substances; and
  • (d) a description of the steps that have been taken to avoid pollution risks from the site, including any steps that have been taken to—
  • (i) return the site to a satisfactory state, and
  • (ii) remove, control, contain or reduce any relevant hazardous substance in soil and groundwater.
  • (5) If the chief inspector is satisfied, in relation to the site, or in the case of a partial surrender, the part of the site used for the operation of the surrender unit, that all appropriate measures to—
  • (a) avoid any pollution risk resulting from the operation of the Part A installation or Part A mobile plant;
  • (b) return the site to a satisfactory state, taking into account the technical feasibility of the measures; and
  • (c) remove, control, contain or reduce any relevant hazardous substance in soil or groundwater so that the site, taking into account its current or approved future use, ceases to pose a significant risk to human health or the environment,

have been taken by the operator, the chief inspector shall accept the surrender and give the operator notice in writing of the determination and the permit shall cease to have effect or, in the case of partial surrender, shall cease to have effect to the extent surrendered, on the date specified in the notice of determination.

  • (6) If, in the case of a partial surrender, the chief inspector is of the opinion that it is necessary to vary the conditions included in the permit to take account of the surrender, the chief inspector shall specify the necessary variations in the notice of determination given under paragraph (4) and the variations specified in the notice shall take effect on the date specified in the notice.
  • (7) If the chief inspector is not satisfied as specified in paragraph (5) he shall give to the operator notice in writing of his determination stating that the application has been refused.
  • (8) The chief inspector shall give notice in writing of his determination of an application under this regulation within the period of three months beginning with the date on which the chief inspector receives the application or within such longer period as the chief inspector and the operator may agree in writing.
  • (9) If the chief inspector fails to give notice in writing of his determination accepting the surrender or refusing the application within the period allowed by or under paragraph (8) the application shall, if the operator notifies the chief inspector in writing that he treats the failure as such, be deemed to have been refused at the end of that period.
  • (10) The chief inspector may, by notice in writing to the operator, require the operator to furnish such further information specified in the notice, within the period so specified, as the chief inspector may require for the purpose of determining an application under this regulation.
  • (11) Where a notice is served on an operator under paragraph (10)—
  • (a) for the purpose of calculating the period of three months specified in paragraph (8), no account shall be taken of the period beginning with the date on which notice is served and ending on the date on which the information specified in the notice is furnished; and
  • (b) if the specified information is not furnished within the period specified, the application shall, if the chief inspector gives notice in writing to the operator that the failure is treated as such, be deemed to have been withdrawn at the end of that period.
  • (12) For the purpose of deciding whether a pollution risk results from the operation of a Part A installation or Part A mobile plant—
  • (a) where the operation of the installation or plant involved the carrying out of a specified waste management activity, only risks resulting from the carrying out of that activity after the date on which the permit applying to the installation or mobile plant was granted shall be treated as resulting from the operation of the installation or mobile plant; and
  • (b) where the operation of the installation or mobile plant involved the carrying out of other activities, only risks resulting from the carrying out of those other activities after the date on which the permit applying to the installation or mobile plant was granted shall be treated as resulting from the operation of the installation or mobile plant.
  • (13) The relevant date for a specified waste management activity for the purpose of paragraph (12)(a) is—
  • (a) where the activity was carried out on the site of the installation or mobile plant under a disposal licence which, by virtue of Article 10(1) of the Pollution Control and Local Government (Northern Ireland) Order 1978[^f00016], ceased to have effect in relation to the carrying out of that activity on that site on the granting of the permit applying to the installation or mobile plant, the date on which that disposal licence was granted; and
  • (b) in any other case, the date on which the permit applying to the installation or mobile plant was granted.
  • (14) In paragraph (13)(a) “disposal licence” has the same meaning as in Article 5(1) of the Pollution Control and Local Government (Northern Ireland) Order 1978.
  • (15) In paragraphs (4)(c) and (12) “permit” means a permit granted under these Regulations or under the Pollution Prevention and Control (Northern Ireland) Regulations 2003[^f00017].

Surrender of a permit for a Part B or Part C installation or Part B or Part C mobile plant

23
  • (1) This regulation applies—
  • (a) where an operator of a Part B or Part C installation or Part B or Part C mobile plant ceases or intends to cease operating the installation (in whole or in part) or the mobile plant; and
  • (b) in relation to that part of any installation or mobile plant where an activity falling within paragraphs (b), (d), (g) and (h) of Part A of section 5.1 of Part 1 of Schedule 1 is carried out.
  • (2) Where this regulation applies, the operator may—
  • (a) if they have ceased or intend to cease operating all of the installations and mobile plant covered by the permit, notify the enforcing authority of the surrender of the whole permit; or
  • (b) in any other case, notify the enforcing authority of the surrender of the permit in so far as it authorises the operation of the installation or mobile plant (“the surrender unit”) which the operator has ceased or intends to cease operating (a “partial surrender”).
  • (3) A notification under paragraph (2) shall contain the following information—
  • (a) the operator’s telephone number and address and, if different, any address to which correspondence relating to the notification should be sent;
  • (b) in the case of a partial surrender of a permit, a description of the surrender unit and a map or plan identifying the part of the site used for the operation of the surrender unit;
  • (c) in the case of a partial surrender of a permit applying to mobile plant, a list of the mobile plant to which it applies; and
  • (d) the date on which the surrender is to take effect, which shall be at least 28 days after the date on which the notice is served on the enforcing authority.
  • (4) The enforcing authority may, by notice in writing, require the operator to supply such further information specified in the notice within the period so specified.
  • (5) Subject to paragraphs (6) and (7), where a surrender is notified under this regulation the permit shall cease to have effect on the date specified in the notification or, in the case of partial surrender, shall cease to have effect on that date to the extent surrendered.
  • (6) If, in the case of a partial surrender, the enforcing authority is of the opinion that it is necessary to vary the conditions of the permit to take account of the surrender, the enforcing authority shall—
  • (a) notify the operator of its opinion in writing; and
  • (b) serve a variation notice under regulation 19 on the operator specifying the variations of the conditions necessitated by the surrender,

and the permit shall cease to have effect to the extent surrendered on the date on which the variations specified in the variation notice take effect if that date is after the date specified in the notification of the surrender.

  • (7) If the enforcing authority has required the operator to supply further information by notice in writing, the enforcing authority shall serve notice on the operator acknowledging receipt of the requested information, and stating the date on which the permit will cease to have effect, which shall not be more than 28 days after the date on which the information was received.

Revocation of permits

24
  • (1) The enforcing authority may at any time revoke a permit, in whole or in part, by serving a notice in writing (“a revocation notice”) on the operator.
  • (2) Without prejudice to the generality of paragraph (1), the enforcing authority may serve a notice under this regulation in relation to a permit where—
  • (a) the permit authorises the carrying out of a specified waste management activity and it appears to the chief inspector that the operator of the installation or mobile plant concerned has ceased to be a fit and proper person to carry out that activity by reason of their having been convicted of a relevant offence within the meaning of regulation 4(5) or by reason of the management of that activity having ceased to be in the hands of a technically competent person; or
  • (b) the holder of the permit has ceased to be the operator of the installation or mobile plant covered by the permit.
  • (3) A revocation notice may—
  • (a) revoke a permit entirely;
  • (b) revoke a permit only in so far as it authorises the operation of some of the installations or mobile plant to which it applies; or
  • (c) revoke a permit only in so far as it authorises the carrying out of some of the activities which may be carried out in an installation or by means of mobile plant to which it applies.
  • (4) A revocation notice shall specify—
  • (a) in the case of a revocation specified in paragraph (3)(b) or (c) (a “partial revocation”), the extent to which the permit is being revoked; and
  • (b) in all cases, the date on which the revocation shall take effect, which shall be at least 28 days after the date on which the notice is served.
  • (5) If, in the case of a revocation specified in paragraph (3)(b) or (c) applying to a Part A installation or Part A mobile plant, the chief inspector considers that it is appropriate to require the operator to take steps, once the installation or mobile plant is no longer in operation, to—
  • (a) avoid any pollution risk resulting from the operation of the installation or mobile plant on the site or, in the case of a partial revocation, that part of the site used for the operation of that installation or mobile plant;
  • (b) return the site, or that part of the site, to a satisfactory state; or

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.