The Renewable Heat Incentive Scheme Regulations 2011
Made: 27th November 2011
Coming into force in accordance with regulation 1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 1 — Introductory provisions
Citation and commencement
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Renewable heat incentive scheme
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 2 — Eligibility and matters relating to eligibility
CHAPTER 1 — Eligible installations
Eligible installations
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 2 — Eligibility criteria for technologies
Eligible installations generating heat from solid biomass
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat from solid biomass contained in municipal waste
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat using solar collectors
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat using solar collectors
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations which are CHP systems
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat using air source heat pumps
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat using geothermal sources
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Other eligibility requirements for technologies
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
MCS certification for microgeneration heating equipment
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Plants comprised of more than one plant
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Excluded plants
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 3 — Eligibility criteria in relation to metering and steam measuring
Metering of plants in simple systems
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Metering of plants in complex systems
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Shared meters
18
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Metering of CHP systems generating electricity only before 15th July 2009
19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Matters relating to all heat meters and steam measuring equipment
20
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional metering requirements for plants generating heat from biogas
21
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 3 — Accreditation and registration
Applications for accreditation
22
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exceptions to duty to accredit
23
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Changes in ownership
24
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Producers of biomethane
25
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Preliminary accreditation
26
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 4 — Ongoing obligations for participants
CHAPTER 1 — Ongoing obligations relating to the use of solid biomass to generate heat
Interpretation
27
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Participants using solid biomass contained in ... waste
28
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Participants using solid biomass in accredited RHI installations with an installation capacity of 1MWth or above
29
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Participants using solid biomass in accredited RHI installations with an installation capacity of between 45kWth and 1MWth
30
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 2 — Ongoing obligations relating to the use of biogas to generate heat and the production of biomethane for injection
Biogas produced from gasification or pyrolysis
31
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Participants generating heat from biogas
32
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Biomethane producers
33
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 3 — Ongoing obligations relating to other matters
Ongoing obligations: general
34
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Ongoing obligations in relation to metering
35
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Ongoing obligations in relation to the provision of information
36
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 5 — Periodic support payments
Payment of periodic support payments to participants
37
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Periodic support payments for accredited RHI installations in simple systems
38
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Periodic support payments accredited RHI installations for complex systems
39
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fossil fuel contamination of solid biomass and fossil fuel used for permitted ancillary purposes
40
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fossil fuel contamination adjustment to periodic support payments for producers and combusters of biogas produced from gasification and pyrolysis
41
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Periodic support payments to producers of biomethane
42
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 6 — Additional RHI capacity
Treatment of additional RHI capacity
43
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 7 — Enforcement
Power to temporarily withhold periodic support payments to investigate alleged non-compliance
44
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power to suspend periodic support payments where ongoing failure to comply
45
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power to permanently withhold or reduce a participant's periodic support payments
46
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocation of accreditation or registration
47
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Overpayment notices and offsetting
48
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 8 — Revocation of sanctions
Revocation of Part 7 sanctions
49
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 9 — Inspection
Power to inspect accredited RHI installations and equipment used to produce biomethane
50
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 10 — Reviews
Right of review
51
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 11 — Administrative Functions of the Authority and notices
Publication of guidance and tariffs
52
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reporting obligations
53
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional information
54
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Notices
55
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 1 — Information required for accreditation and registration
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 2 — Provision of information in relation to the use of biomass in certain circumstances
Information to be provided to the Authority where biomass is used for combustion or production of biomethane
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 3 — Tariffs
| Tariff name | Sources of energy or technology | Installation capacity | Tariff (pence/kWh) |
|---|---|---|---|
| Small commercial biomass | Solid biomass including solid biomass contained in municipal solid waste and CHP | Less than 200kWth | Tier 1: 7.9 Tier 2: 2.0 |
| Medium commercial Biomass | As above | 200kWth and above up to but not including 1MWth | Tier 1: 4.9 Tier 2: 2.0 |
| Large commercial biomass | As above | 1MWth and above | 1.0 |
| Small commercial heat pumps | Ground source heat pump, water source heat pump, deep geothermal | Less than 100kWth | 4.5 |
| Large commercial heat pumps | As above | 100kWth and above | 3.2 |
| All Solar collectors | Solar collectors | Below 200kWth | 8.5 |
| Biomethane and biogas combustion | Biomethane injection and biogas combustion | All biomethane injection and biogas combustion below 200kWth | 6.8 |
Signed
Gregory Barker — Minister of State — 2011-11-27
Explanatory note
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Footnotes
[^f00001]: 2008 c.32. Section 100 is amended by S.I. 2011/2195, which was made on 5.9.11 and came into force on 6.9.11.
[^f00002]: 1986 c.44; section 7 was amended by the Utilities Act 2000 (c.27), section 3(2), section 76, section 108, Schedule 6, Part I, paragraphs 1 and 4 and Schedule 8 and the Energy Act 2004 (c.20), section 149, subsections (1) and (5), section 197(9) and Schedule 23, Part I.
[^f00003]: Details of which are available at www.microgenerationcertification.org.
[^f00004]: ISBN 0580294153. Copies can be obtained from the British Standards Institution at www.bsigroup.com.
[^f00005]: OJ L 135, 30.4.2004, p. 1, amended by Commission Directive 2009/137/EC (OJ L 294, 11.11.2009, p. 7).
[^f00006]: 2003 c.33.
[^f00007]: Section 5(6) to (10) was inserted by section 149(1) and (3) of the Energy Act 2004 (c.20).
[^f00008]: S.I. 2009/785, amended by S.I. 2010/1107 and S.I. 2011/984.
[^f00009]: S.S.I. 2009/140, amended by S.S.I. 2010/147 and S.S.I 2011/225.
[^f00010]: A copy is available on www.chpqa.decc.gov.uk.
[^f00011]: 2003 c.33. Section 24 was amended by section 209(1)(a) and (b) of the Local Government and Public Involvement in Heath Act 2007 (c.28).
[^f00012]: ISBN 0580194825. Copies can be obtained from the British Standards Institution: www.bsi-global.com/en/.
[^f00013]: 1990 c.43. Section 75(2) was substituted by section 120(1) of and paragraph 88(1) and (2) of Schedule 22 to the Environment Act 1995 (c.25) and a Schedule 2B (Categories of Waste) was inserted by paragraph 95 of that Schedule.
[^f00014]: Section 30(3) was amended by the Local Government (Wales) Act 1994 (c.19), section 66(8), paragraph 17(3) of Schedule 9 and Schedule 18 and subsection (3)(c) was substituted by section 180(1) of and paragraph 167(3) of Schedule 13 to the Local Government etc (Scotland) Act 1994 (c.39).
[^f00015]: Paragraph (f) of section 30(2) was substituted by paragraph 17(2) of Schedule 9 to the Local Government (Wales) Act 1994 (c.19) and paragraph (g) was amended by section 180(1) of and paragraph 167(3) of Schedule 13 to the Local Government etc (Scotland) Act 1994 (c.39).
[^f00016]: S.I. 2010/675, amended by S.I. 2011/988.
[^f00017]: S.S.I. 2000/323, as amended in particular by S.S.I. 2002/493; S.S.I. 2003/146; S.S.I. 2003/170; S.S.I. 2005/101; S.S.I. 2005/340; S.S.I. 2007/2325 and S.S.I. 2011/226.
Editorial notes
[^key-a328146d1b52d980296b0d512af27431]: Regulations revoked (22.5.2018) by The Renewable Heat Incentive Scheme Regulations 2018 (S.I. 2018/611), regs. 1(1), 92(1) (with reg. 92(3)-(14))
PART 10A — Restriction of entry to the scheme
Circumstances in which entry to the scheme is restricted
51A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation
51B
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Calculation of initial tariffs on or after the relevant date
37A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Calculation of A
37B
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Calculation of B
37C
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Calculation of C
37D
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Expenditure forecast statement and tariff change notice
37E
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Periodic support payments for accredited RHI installations in simple systems
Periodic support payments accredited RHI installations for complex systems
Fossil fuel contamination of solid biomass and fossil fuel used for permitted ancillary purposes
Fossil fuel contamination adjustment to periodic support payments for producers and combusters of biogas produced from gasification and pyrolysis
Periodic support payments to producers of biomethane
SCHEDULE 4 — Total expenditure
| Assessment date | Total expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A |
|---|---|---|
| 30th April 2013 | £ 97.2 million | £ 48.6 million |
| 31st July 2013 | £ 120.2 million | £ 60.1 million |
| 31st October 2013 | £ 143.3 million | £ 71.6 million |
| 31st January 2014 | £ 166.3 million | £ 83.2 million |
| 30th April 2014 | £ 192.8 million | £ 96.4 million |
| 31st July 2014 | £ 184.1 million | £ 92.1 million |
| 31st October 2014 | £ 207.2 million | £ 103.6 million |
| 31st January 2015 | £ 230.3 million | £ 115.1 million |
| 30th April 2015 | £ 260.9 million | £ 130.4 million |
| 31st July 2015 | £ 306.2 million | £ 153.1 million |
| 31st October 2015 | £ 351.5 million | £ 175.7 million |
| 31st January 2016 | £ 396.8 million | £ 198.4 million |
| 30th April 2016 | £ 442.1 million | £ 221.1 million |
| 31st July 2016 | £ 487.4 million | £ 243.7 million |
| 31st October 2016 | £ 532.7 million | £ 266.4 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 578.0 million | £ 289.0 million |
| 31st October 2017 | £728.55 million | £364.28 million |
| 31st January 2018 | £753.27 million | £376.64 million |
| 30th April 2018 | £778.22 million | £389.11 million |
| Any date after 30th July 2018 | £802.65 million | £401.32 million |
SCHEDULENonBreakingSpace5 — Expenditure in relation to individual technologies
PART 1 — Small biomass plants
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 30th April 2013 | £ 14.8 million | £ 22.2 million | - |
| 31st July 2013 | £ 16.7 million | £ 25.1 million | £ 2.9 million |
| 31st October 2013 | £ 18.7 million | £ 28.0 million | £ 2.9 million |
| 31st January 2014 | £ 20.6 million | £ 30.9 million | £ 2.9 million |
| 30th April 2014 | £ 22.6 million | £ 34.0 million | £ 3.1 million |
| 31st July 2014 | £ 48.8 million | £ 58.6 million | £ 8.7 million |
| 31st October 2014 | £ 56.0 million | £ 67.2 million | £ 8.7 million |
| 31st January 2015 | £ 63.2 million | £ 75.9 million | £ 8.7 million |
| 30th April 2015 | £ 71.1 million | £ 85.3 million | £ 9.5 million |
| 31st July 2015 | £ 80.3 million | £ 96.4 million | £ 11.0 million |
| 31st October 2015 | £ 89.5 million | £ 107.4 million | £ 11.0 million |
| 31st January 2016 | £ 98.7 million | £ 118.5 million | £ 11.0 million |
| 30th April 2016 | £ 107.9 million | £ 129.5 million | £ 11.0 million |
| 31st July 2016 | £ 117.1 million | £ 140.5 million | £ 11.0 million |
| 31st October 2016 | £ 126.3 million | £ 151.5 million | £ 11.0 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 135.4 million | £ 162.5 million | £ 11.0 million |
| 31st October 2017 | £160.40 million | £160.97 million | £1.72 million |
| 31st January 2018 | £162.12 million | £162.70 million | £1.72 million |
| 30th April 2018 | £163.85 million | £164.43 million | £1.73 million |
| Any date after 30th July 2018 | £165.42 million | £166.00 million | £1.58 million |
PART 2 — Medium biomass plants
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 30th April 2013 | £ 13.4 million | £ 20.1 million | - |
| 31st July 2013 | £ 15.5 million | £ 23.2 million | £ 3.1 million |
| 31st October 2013 | £ 17.6 million | £ 26.3 million | £ 3.1 million |
| 31st January 2014 | £ 19.6 million | £ 29.4 million | £ 3.1 million |
| 30th April 2014 | £ 21.8 million | £ 32.7 million | £ 3.3 million |
| 31st July 2014 | £ 43.7 million | £ 52.5 million | £ 6.3 million |
| 31st October 2014 | £ 49.0 million | £ 58.8 million | £ 6.3 million |
| 31st January 2015 | £ 54.2 million | £ 65.1 million | £ 6.3 million |
| 30th April 2015 | £ 59.9 million | £ 71.8 million | £ 6.7 million |
| 31st July 2015 | £ 66.2 million | £ 79.4 million | £ 7.6 million |
| 31st October 2015 | £ 72.5 million | £ 87.0 million | £ 7.6 million |
| 31st January 2016 | £ 78.8 million | £ 94.5 million | £ 7.6 million |
| 30th April 2016 | £ 85.1 million | £ 102.1 million | £ 7.6 million |
| 31st July 2016 | £ 91.4 million | £ 109.7 million | £ 7.6 million |
| 31st October 2016 | £ 97.8 million | £ 117.3 million | £ 7.6 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 104.1 million | £ 124.9 million | £ 7.6 million |
| 31st October 2017 | £182.24 million | £187.29 million | £3.30 million |
| 31st January 2018 | £185.57 million | £190.61 million | £3.32 million |
| 30th April 2018 | £188.91 million | £193.96 million | £3.34 million |
| Any date after 30th July 2018 | £192.10 million | £197.14 million | £3.19 million |
PART 3 — Large biomass plants
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 30th April 2013 | £ 23.1 million | £ 34.7 million | - |
| 31st July 2013 | £ 27.6 million | £ 41.3 million | £ 6.6 million |
| 31st October 2013 | £ 32.0 million | £ 48.0 million | £ 6.7 million |
| 31st January 2014 | £ 36.4 million | £ 54.6 million | £ 6.6 million |
| 30th April 2014 | £ 41.2 million | £ 61.8 million | £ 7.2 million |
| 31st July 2014 | £ 10.9 million | £ 16.3 million | £ 2.2 million |
| 31st October 2014 | £ 12.4 million | £ 18.5 million | £ 2.2 million |
| 31st January 2015 | £ 13.9 million | £ 20.8 million | £ 2.2 million |
| 30th April 2015 | £ 15.8 million | £ 23.8 million | £ 3.0 million |
| 31st July 2015 | £ 18.8 million | £ 28.2 million | £ 4.5 million |
| 31st October 2015 | £ 21.8 million | £ 32.7 million | £ 4.5 million |
| 31st January 2016 | £ 24.8 million | £ 37.2 million | £ 4.5 million |
| 30th April 2016 | £ 27.8 million | £ 41.7 million | £ 4.5 million |
| 31st July 2016 | £ 30.8 million | £ 46.2 million | £ 4.5 million |
| 31st October 2016 | £ 33.8 million | £ 50.7 million | £ 4.5 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 36.8 million | £ 55.2 million | £ 4.5 million |
| 31st October 2017 | £31.18 million | £38.86 million | £2.65 million |
| 31st January 2018 | £33.87 million | £41.54 million | £2.69 million |
| 30th April 2018 | £36.59 million | £44.26 million | £2.72 million |
| Any date after 30th July 2018 | £39.30 million | £46.97 million | £2.71 million |
PART 4 — Heat pumps (except air source heat pumps)
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 30th April 2013 | £ 28.9 million | £ 43.4 million | - |
| 31st July 2013 | £ 36.3 million | £ 54.4 million | £ 11 million |
| 31st October 2013 | £ 43.6 million | £ 65.5 million | £ 11.1 million |
| 31st January 2014 | £ 51 million | £ 76.5 million | £ 11 million |
| 30th April 2014 | £ 59.7 million | £ 89.5 million | £ 13 million |
PART 5 — Plants using solar collectors
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 30th April 2013 | £ 4.9 million | £ 4.9 million | - |
| 31st July 2013 | £ 6.0 million | £ 6.0 million | £ 1.1 million |
| 31st October 2013 | £ 7.2 million | £ 7.2 million | £ 1.2 million |
| 31st January 2014 | £ 8.3 million | £ 8.3 million | £ 1.1 million |
| 30th April 2014 | £ 9.6 million | £ 9.6 million | £ 1.3 million |
| 31st July 2014 | £ 3.9 million | £ 3.9 million | £ 0.8 million |
| 31st October 2014 | £ 4.7 million | £ 4.7 million | £ 0.8 million |
| 31st January 2015 | £ 5.5 million | £ 5.5 million | £ 0.8 million |
| 30th April 2015 | £ 6.5 million | £ 6.5 million | £ 0.9 million |
| 31st July 2015 | £ 7.5 million | £ 7.5 million | £ 1.1 million |
| 31st October 2015 | £ 8.6 million | £ 8.6 million | £ 1.1 million |
| 31st January 2016 | £ 9.8 million | £ 9.8 million | £ 1.1 million |
| 30th April 2016 | £ 10.9 million | £ 10.9 million | £ 1.1 million |
| 31st July 2016 | £ 12.0 million | £ 12.0 million | £ 1.1 million |
| 31st October 2016 | £ 13.1 million | £ 13.1 million | £ 1.1 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 14.1 million | £ 14.1 million | £ 1.1 million |
| 31st October 2017 | £0.25 million | £0.28 million | £0.02 million |
| 31st January 2018 | £0.27 million | £0.30 million | £0.02 million |
| 30th April 2018 | £0.29 million | £0.32 million | £0.02 million |
| Any date after 30th July 2018 | £0.32 million | £0.34 million | £0.02 million |
PART 6 — Producers of biomethane for injection and plants which generate heat from biogas
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 30th April 2013 | £ 12 million | £ 18 million | - |
| 31st July 2013 | £ 18.1 million | £ 27.2 million | £ 9.2 million |
| 31st October 2013 | £ 24.2 million | £ 36.3 million | £ 9.1 million |
| 31st January 2014 | £ 30.3 million | £ 45.5 million | £ 9.2 million |
| 30th April 2014 | £ 37 million | £ 55.5 million | £ 10 million |
PART 7 — New biomass CHP systems
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 31st July 2014 | £ 17.9 million | £ 26.9 million | - |
| 31st October 2014 | £ 18.8 million | £ 28.2 million | £ 1.4 million |
| 31st January 2015 | £ 19.7 million | £ 29.6 million | £ 1.4 million |
| 30th April 2015 | £ 22.8 million | £ 34.2 million | £ 4.7 million |
| 31st July 2015 | £ 30.3 million | £ 45.5 million | £ 11.2 million |
| 31st October 2015 | £ 37.8 million | £ 56.7 million | £ 11.2 million |
| 31st January 2016 | £ 45.3 million | £ 68.0 million | £ 11.2 million |
| 30th April 2016 | £ 52.8 million | £ 79.2 million | £ 11.2 million |
| 31st July 2016 | £ 60.3 million | £ 90.4 million | £ 11.2 million |
| 31st October 2016 | £ 67.7 million | £ 101.6 million | £ 11.2 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 75.2 million | £ 112.8 million | £ 11.2 million |
| 31st October 2017 | £70.20 million | £72.59 million | £1.41 million |
| 31st January 2018 | £71.62 million | £74.00 million | £1.42 million |
| 30th April 2018 | £73.05 million | £75.43 million | £1.43 million |
| Any date after 30th July 2018 | £74.41 million | £76.80 million | £1.37 million |
RHI emission certificates
5A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat from solid biomass contained in municipal waste
Eligible installations generating heat using ground source heat pumps
Eligible installations which are CHP systems
Eligible installations generating heat using biogas
Other eligibility requirements for technologies
MCS certification for microgeneration heating equipment
Plants comprised of more than one plant
Excluded plants
Metering in respect of new applications for accreditation
17A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Shared meters
Metering of CHP systems generating electricity only before 15th July 2009
Matters relating to all heat meters and steam measuring equipment
Additional metering requirements for plants generating heat from biogas
Changes in location of accredited RHI installations
24A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Producers of biomethane
Preliminary accreditation
Ongoing obligations: emissions from biomass
34A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Ongoing obligations in relation to metering
Ongoing obligations in relation to the provision of information
Periodic support payments for new accredited RHI installations
39A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fossil fuel contamination of solid biomass and fossil fuel used for permitted ancillary purposes
Fossil fuel contamination adjustment to periodic support payments for producers and combusters of biogas produced from gasification and pyrolysis
Periodic support payments to producers of biomethane
Calculation of heat loss in certain circumstances
42A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE A1 — Content of RHI emission certificates
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations which are CHP systems
Eligible installations which are new solid biomass CHP systems
9A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Eligible installations generating heat using geothermal sources
Eligible installations generating heat using biogas
Other eligibility requirements for technologies
Certification for installation of Microgeneration heating equipment
Plants comprised of more than one plant
Excluded plants
Metering in respect of new applications for accreditation in respect of ground source or air source heat pumps
17B
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Shared meters
Metering of CHP systems generating electricity only before 15th July 2009
Matters relating to all heat meters and steam measuring equipment
Additional metering requirements for plants generating heat from biogas
Treatment of grants from public funds
Preliminary registration of biomethane producers
26A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Determination of increase in expenditure forecasts for 1st September 2014 expenditure forecast statement
37F
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Periodic support payments for accredited RHI installations in simple systems
Periodic support payments accredited RHI installations for complex systems
Periodic support payments for new accredited RHI installations
Periodic support payments for CHP systems using biomass or biogas in combination with other sources of energy
39B
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHP systems accredited in relation to the Renewables Obligation
39C
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fossil fuel contamination of solid biomass and fossil fuel used for permitted ancillary purposes
Fossil fuel contamination adjustment to periodic support payments for producers and combusters of biogas produced from gasification and pyrolysis
Periodic support payments to producers of biomethane
Calculation of heat loss in certain circumstances
Additional RHI capacity
Additional capacity for biomethane production
43A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULENonBreakingSpace3A — New tariffs for plants generating heat from solid biomass with a capacity of 1 MWth or above, ground source heat pumps and solar collectors
| Tariff name | Source of energy or technology | Installation capacity | Tariff (pence/kWh) |
|---|---|---|---|
| New large biomass | Solid biomass including solid biomass contained in waste, including CHP systems generating heat and power from solid biomass | 1MWth and above | 2.0 |
| New ground source heat pumps | Ground source heat pumps | All capacities | Tier 1: 8.7Tier 2: 2.6 |
| New solar collectors | Solar collectors | Less than 200kWth | 10.0 |
SCHEDULENonBreakingSpace3B — New tariffs for new solid biomass CHP systems, deep geothermal energy, biogas combustion with a capacity of 200kWth and above and air source heat pumps
| Tariff name | Source of energy or technology | Installation capacity | Tariff (pence/kWh) |
|---|---|---|---|
| New solid biomass CHP systems | Solid biomass (excluding solid biomass contained in waste) used in CHP systems which comply with the requirements in regulation 9A | All capacities | 4.1 |
| New deep geothermal | Deep geothermal energy, including CHP systems generating heat and power from such energy | All capacities | 5 |
| Medium biogas | Biogas combustion | 200kWth and above up to but not including 600kWth | 5.9 |
| Large biogas | Biogas combustion | 600kWth and above | 2.2 |
| Air source heat pumps | Air source heat pumps | All capacities | 2.5 |
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
| --- | --- | --- | --- |
| 30th April 2013 | £ 4.9 million | £ 4.9 million | - |
| 31st July 2013 | £ 6 million | £ 6 million | £ 1.1 million |
| 31st October 2013 | £ 7.2 million | £ 7.2 million | £ 1.2 million |
| 31st January 2014 | £ 8.3 million | £ 8.3 million | £ 1.1 million |
| 30th April 2014 | £ 9.6 million | £ 9.6 million | £ 1.3 million |
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
| --- | --- | --- | --- |
| 31st July 2014 | £ 7.4 million | £ 11.1 million | £ 2.3 million |
| 31st October 2014 | £ 8.9 million | £ 13.3 million | £ 2.3 million |
| 31st January 2015 | £ 10.4 million | £ 15.6 million | £ 2.3 million |
| 30th April 2015 | £ 12.6 million | £ 18.9 million | £ 3.3 million |
| 31st July 2015 | £ 16.2 million | £ 24.2 million | £ 5.4 million |
| 31st October 2015 | £ 19.7 million | £ 29.6 million | £ 5.4 million |
| 31st January 2016 | £ 23.3 million | £ 35.0 million | £ 5.4 million |
| 30th April 2016 | £ 26.9 million | £ 40.4 million | £ 5.4 million |
| 31st July 2016 | £ 30.5 million | £ 45.8 million | £ 5.4 million |
| 31st October 2016 | £ 34.1 million | £ 51.2 million | £ 5.4 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 37.7 million | £ 56.6 million | £ 5.4 million |
| 31st October 2017 | £13.21 million | £14.67 million | £0.57 million |
| 31st January 2018 | £13.79 million | £15.25 million | £0.58 million |
| 30th April 2018 | £14.38 million | £15.83 million | £0.59 million |
| Any date after 30th July 2018 | £14.96 million | £16.41 million | £0.58 million |
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
| --- | --- | --- | --- |
| 31st July 2014 | £ 3.9 million | £ 3.9 million | £ 0.8 million |
| 31st October 2014 | £ 4.7 million | £ 4.7 million | £ 0.8 million |
| 31st January 2015 | £ 5.5 million | £ 5.5 million | £ 0.8 million |
| 30th April 2015 | £ 6.5 million | £ 6.5 million | £ 0.9 million |
| 31st July 2015 | £ 7.5 million | £ 7.5 million | £ 1.1 million |
| 31st October 2015 | £ 8.6 million | £ 8.6 million | £ 1.1 million |
| 31st January 2016 | £ 9.8 million | £ 9.8 million | £ 1.1 million |
| 30th April 2016 | £ 10.9 million | £ 10.9 million | £ 1.1 million |
| 31st July 2016 | £ 12.0 million | £ 12.0 million | £ 1.1 million |
| 31st October 2016 | £ 13.1 million | £ 13.1 million | £ 1.1 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 14.1 million | £ 14.1 million | £ 1.1 million |
| 31st October 2017 | £66.15 million | £78.50 million | £4.42 million |
| 31st January 2018 | £70.63 million | £82.97 million | £4.47 million |
| 30th April 2018 | £75.15 million | £87.50 million | £4.52 million |
| Any date after 30th July 2018 | £79.65 million | £92.00 million | £4.50 million |
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
| --- | --- | --- | --- |
| 31st July 2014 | £ 41.5 million | £ 49.8 million | £ 5.1 million |
| 31st October 2014 | £ 45.9 million | £ 55.1 million | £ 5.3 million |
| 31st January 2015 | £ 50.3 million | £ 60.4 million | £ 5.3 million |
| 30th April 2015 | £ 57.5 million | £ 69.0 million | £ 8.6 million |
| 31st July 2015 | £ 70.2 million | £ 84.2 million | £ 15.2 million |
| 31st October 2015 | £ 82.8 million | £ 99.4 million | £ 15.2 million |
| 31st January 2016 | £ 95.5 million | £ 114.6 million | £ 15.2 million |
| 30th April 2016 | £ 108.2 million | £ 129.8 million | £ 15.2 million |
| 31st July 2016 | £ 120.8 million | £ 145.0 million | £ 15.2 million |
| 31st October 2016 | £ 133.5 million | £ 160.2 million | £ 15.2 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 146.2 million | £ 175.4 million | £ 15.2 million |
| 31st October 2017 | £267.37 million | £293.82 million | £10.69 million |
| 31st January 2018 | £278.17 million | £304.62 million | £10.80 million |
| 30th April 2018 | £289.07 million | £315.52 million | £10.90 million |
| Any date after 30th July 2018 | £299.80 million | £326.25 million | £10.73 million |
PART 8 — Deep geothermal plants
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 31st July 2014 | £ 3.9 million | £ 3.9 million | - |
| 31st October 2014 | £ 4.7 million | £ 4.7 million | £ 0.8 million |
| 31st January 2015 | £ 5.5 million | £ 5.5 million | £ 0.8 million |
| 30th April 2015 | £ 6.5 million | £ 6.5 million | £ 0.9 million |
| 31st July 2015 | £ 7.5 million | £ 7.5 million | £ 1.1 million |
| 31st October 2015 | £ 8.6 million | £ 8.6 million | £ 1.1 million |
| 31st January 2016 | £ 9.8 million | £ 9.8 million | £ 1.1 million |
| 30th April 2016 | £ 10.9 million | £ 10.9 million | £ 1.1 million |
| 31st July 2016 | £ 12.0 million | £ 12.0 million | £ 1.1 million |
| 31st October 2016 | £ 13.1 million | £ 13.1 million | £ 1.1 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 14.1 million | £ 14.1 million | £ 1.1 million |
| 31st October 2017 | £0.25 million | £0.85 million | £0.19 million |
| 31st January 2018 | £0.44 million | £1.04 million | £0.19 million |
| 30th April 2018 | £0.63 million | £1.24 million | £0.19 million |
| Any date after 30th July 2018 | £0.83 million | £1.43 million | £0.19 million |
PART 9 — Air source heat pumps
| Assessment date | Expenditure anticipated for subsequent year | Expenditure threshold when calculating C for the purposes of regulation 37A | Anticipated increase in expenditure since previous assessment date |
|---|---|---|---|
| 31st July 2014 | £ 12.2 million | £ 18.3 million | - |
| 31st October 2014 | £ 14.0 million | £ 21.0 million | £ 2.7 million |
| 31st January 2015 | £ 15.8 million | £ 23.7 million | £ 2.7 million |
| 30th April 2015 | £ 17.9 million | £ 26.8 million | £ 3.2 million |
| 31st July 2015 | £ 20.7 million | £ 31.0 million | £ 4.2 million |
| 31st October 2015 | £ 23.4 million | £ 35.1 million | £ 4.2 million |
| 31st January 2016 | £ 26.2 million | £ 39.3 million | £ 4.2 million |
| 30th April 2016 | £ 29.0 million | £ 43.5 million | £ 4.2 million |
| 31st July 2016 | £ 31.8 million | £ 47.7 million | £ 4.2 million |
| 31st October 2016 | £ 34.6 million | £ 51.9 million | £ 4.2 million |
| Any date after 30th January 2017 but before 31st October 2017 | £ 37.4 million | £ 56.1 million | £ 4.2 million |
| 31st October 2017 | £0.69 million | £1.04 million | £0.11 million |
| 31st January 2018 | £0.81 million | £1.15 million | £0.11 million |
| 30th April 2018 | £0.92 million | £1.26 million | £0.11 million |
| Any date after 30th July 2018 | £1.04 million | £1.38 million | £0.11 million |
CHAPTERNonBreakingSpace4 — Sustainable solid biomass etc
Interpretation
36A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Ongoing obligation to use sustainable solid biomass or biogas or to produce sustainable biomethane
36B
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Information to be provided to the Authority in relation to the use of sustainable solid biomass etc
36C
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Sustainability audit reports
36D
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Schemes for listing approved sustainable fuels
36E
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULENonBreakingSpace2A — Greenhouse gas criteria
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 2B — Land criteria
PARTNonBreakingSpace1 — Interpretation
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PARTNonBreakingSpace2 — Land criteria for solid biomass which is wood or wholly derived from wood, excluding energy crops
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PARTNonBreakingSpace3 — Land criteria for other solid biomass including energy crops
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power to withhold periodic support payments: further provisions
Provision of information to the Authority etc
52A
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reporting obligations
Additional information
Notices
SCHEDULENonBreakingSpace3C — New biomethane tariffs
| Tariff name | Tariff (pence/kWh injected) |
|---|---|
| New biomethane | Tier 1: 7.5 |
| Tier 2: 4.4 | |
| Tier 3: 3.4 |
Periodic support payments for new solid biomass CHP systems
39D
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fossil fuel contamination of solid biomass and fossil fuel used for permitted ancillary purposes
Fossil fuel contamination adjustment to periodic support payments for producers and combusters of biogas produced from gasification and pyrolysis
Periodic support payments to producers of biomethane
Calculation of heat loss in certain circumstances
Calculation of initial tariffs for certain installations and biomethane producers with tariff start dates before 1st January 2018
37AA
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Calculation of A for tariff start dates before the fifth relevant date
Calculation of A for tariff start dates on or after 1st January 2018
37BA
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Calculation of B
Calculation of C
Expenditure forecast statement and tariff change notice
Determination of increase in expenditure forecasts for 1st September 2014 expenditure forecast statement
Periodic support payments for accredited RHI installations in simple systems
Periodic support payments accredited RHI installations for complex systems
Periodic support payments for new accredited RHI installations
Periodic support payments for CHP systems using biomass or biogas in combination with other sources of energy
CHP systems accredited in relation to the Renewables Obligation
Periodic support payments for new solid biomass CHP systems
Fossil fuel contamination of solid biomass and fossil fuel used for permitted ancillary purposes
Fossil fuel contamination adjustment to periodic support payments for producers and combusters of biogas produced from gasification and pyrolysis
Periodic support payments to producers of biomethane
Calculation of heat loss in certain circumstances
SCHEDULENonBreakingSpace3D — New tariffs
| Tariff name | Source of energy and technology | Installation capacity | Tariff (pence/kWh) |
|---|---|---|---|
| Small biomass plants | Solid biomass including solid biomass contained in waste which is not a new solid biomass CHP system | Less than 200kWth | Tier 1: 2.96Tier 2: 2.08 |
| Medium biomass plants | As above | 200kWth and above up to but not including 1MWth | Tier 1: 2.96Tier 2: 2.08 |
| Large biomass plants | As above | 1MWth and above | Tier 1: 2.96Tier 2: 2.08 |
| New solid biomass CHP systems | Solid biomass (excluding solid biomass contained in waste) used in CHP systems which comply with the requirements in regulation 9A | All capacities | 4.29 |
| Deep geothermal plants | Deep geothermal energy including CHP systems generating heat and power from such energy | All capacities | 5.22 |
| Small biogas plants | Biogas combustion | Less than 200kWth | 2.88 |
| Medium biogas plants | Biogas combustion | 200kWth and above up to but not including 600kWth | 2.26 |
| Large biogas plants | Biogas combustion | 600kWth and above | 0.86 |
| Plants which use solar collectors | Solar collectors | All capacities | 10.44 |
| Ground source heat pumps | Ground source heat pumps | All capacities | Tier 1: 9.09Tier 2: 2.71 |
| Air source heat pumps | Air source heat pumps | All capacities | 2.61 |
| Producers of biomethane for injection | Biomethane injection | All biomethane injection | Tier 1: 3.20Tier 2: 1.89Tier 3: 1.45 |
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.