The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013
- (a) on being given reasonable notice (except in case of emergency, when immediate access must be afforded) afford reasonable facilities to the surveyor for access to the site of the specified works and to any land and to existing works of the undertaker which may provide support for the waterway as will or may be affected by the specified works; and
- (b) supply the surveyor as soon as reasonably practicable with all such information as the surveyor may reasonably require with regard to such existing works of the undertaker and to the specified works or the method of their construction.
- (3) The reasonable costs of the survey are to include the costs of any dewatering or reduction of the water level of any part of the waterway (where reasonably required) which may be effected to facilitate the carrying out of the survey and the provisions of this Schedule apply with all necessary modifications to any such dewatering or reduction in the water level as though the same were specified works.
- (4) Copies of the report of the survey must be provided to both the Trust and the undertaker at no cost to the Trust.
Approval of plans, protective works etc.
6
- (1) The undertaker must before commencing construction of any specified work including any temporary works supply to the Trust proper and sufficient plans of that work and such further particulars available to it as the Trust may within 14 days of the submission of the plans reasonably require for the approval of the engineer and must not commence such construction of a specified work until plans of that work have been approved in writing by the engineer or settled by arbitration.
- (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld or delayed, and if within 28 days after such plans (including any other particulars reasonably required under sub-paragraph (1)) have been supplied to the Trust the engineer has not intimated disapproval of those plans and the grounds of disapproval the engineer is deemed to have approved the plans as submitted.
- (3) When signifying approval of the plans the engineer may specify—
- (a) any protective work (whether temporary or permanent) which in the reasonable opinion of the engineer should be carried out before the commencement of a specified work to prevent detriment; and
- (b) such other requirements as may be reasonably necessary to prevent detriment;
and such protective works must be constructed by the undertaker or by the Trust at the undertaker’s request without unnecessary delay and the undertaker must not commence the construction of a specified work until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction.
- (4) The undertaker must pay to the Trust a capitalised sum representing the reasonably increased or additional cost of maintaining and, when necessary, renewing any works, including any permanent protective works provided under sub-paragraph (3), and of carrying out any additional dredging of the waterway necessitated by the exercise of any of the powers of this Order but if the cost of maintaining the waterway, or of works of renewal of the waterway, is reduced in consequence of any such works, a capitalised sum representing such reasonable saving must be set off against any sum payable by the undertaker to the Trust under this paragraph.
- (5) In the event that the undertaker fails to complete the construction of, or part of, the specified works the Trust may, if it is reasonably required in order to avoid detriment, construct any of the specified works, or part of such works, (together with any adjoining works) in order to complete the construction of, or part of, the specified works or make such works and the undertaker must reimburse the Trust all costs, fees, charges and expenses it has reasonably incurred in carrying out such works.
Design of works
7
Without affecting its obligations under the provisions of this Schedule the undertaker must consult, collaborate and respond constructively to any approach, suggestion, proposal or initiative made by the Trust on—
- (a) the design and appearance of the specified works, including the materials to be used for their construction; and
- (b) the environmental effects of the specified works;
and must have regard to such views as may be expressed by the Trust to the extent that these accord with the requirements of the relevant planning authority in response to such consultation pursuant in particular to the requirements imposed on the Trust by section 22 (general environmental and recreational duties) of the British Waterways Act 1995[^f00023] and to the interest of the Trust in preserving and enhancing the environment of its waterways.
Notice of works
8
The undertaker must give to the engineer 28 days’ notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, the Trust may where appropriate arrange for the publication of notices bringing those works to the attention of users of the Trust’s network.
Lighting
9
The undertaker must provide and maintain at its own expense in the vicinity of the specified or protective works such temporary lighting and such signal lights for the control of navigation as the engineer may reasonably require during the construction or failure of the specified or protective works.
Construction of specified works
10
- (1) Any specified or protective works must, when commenced, be constructed—
- (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled in accordance with this Schedule and with any requirements made under paragraph 6(3) and paragraph 8;
- (b) under the supervision (if given) and to the reasonable satisfaction of the engineer;
- (c) in such manner as to cause as little detriment as is reasonably practicable;
- (d) in such manner as to cause as little inconvenience as is reasonably practicable to the Trust, its officers and agents and all other persons lawfully using the waterways, except to the extent that temporary obstruction has otherwise been agreed by the Trust.
- (2) Nothing in this Order authorises the undertaker to make or maintain any permanent works in or over the waterway so as to impede or prevent passage of any vessel which is of a kind (as to its dimensions) for which the Trust is required by section 105(1)(b) and (2) of the Transport Act 1968[^f00024] to maintain the waterway.
- (3) Following the completion of the construction of the specified works the undertaker must restore the waterway to a condition no less satisfactory than its condition immediately prior to the commencement of those works.
Prevention of pollution
11
The undertaker must not in the course of constructing a specified work or a protective work or otherwise in connection with those works do or permit anything which may result in the pollution of the waterway or the deposit of materials in it and must take such steps as the engineer may reasonably require to avoid or make good any breach of its obligations under this paragraph.
Access to work: provision of information
12
- (1) The undertaker on being given reasonable notice must—
- (a) at all times allow reasonable facilities to the engineer for access to a specified work during its construction; and
- (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.
- (2) The Trust on being given reasonable notice must—
- (a) at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by the Trust under this Schedule during their construction; and
- (b) supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them and the undertaker must reimburse the Trust’s reasonable costs in relation to the supply of such information.
Alterations to waterway
13
- (1) If during the construction of a specified work or a protective work or during a period of 12 months after the completion of those works any alterations or additions, either permanent or temporary, to the waterway are reasonably necessary in consequence of the construction of the specified work or the protective work in order to avoid detriment, the Trust must give to the undertaker reasonable notice in writing specifying the alterations or additions which it considers necessary to avoid detriment and the undertaker must at its own expense and within a time period to be agreed with the Trust carry out such alterations or additions or must pay to the Trust the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by the Trust in maintaining, working and, when necessary, renewing any such alterations or additions.
- (2) If the cost of maintaining, working or renewing the waterway is reduced in consequence of any such alterations or additions a capitalised sum representing such saving must be set off against any sum payable by the undertaker to the Trust under this paragraph.
Maintenance of works
14
If at any time after the completion of a specified work or a protective work, not being a work vested in the Trust, the Trust gives reasonable notice to the undertaker informing it that the state of maintenance of the work appears to the Trust such that the work is causing or likely to cause detriment, the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put the work in such state of maintenance as not to cause such detriment and the Trust must afford the undertaker such access as is required in order for the undertaker to carry out any such works.
Repayment of Canal & River Trust fees, etc.
15
The undertaker must repay to the Trust all fees, costs, charges and expenses reasonably incurred by the Trust —
- (a) in constructing any protective works under the provisions of paragraph 6(3)(a);
- (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction or repair of a specified work and any protective works;
- (c) in respect of the employment during the construction of the specified works or any protective works of any inspectors, watchkeepers and other persons whom it is reasonably necessary to appoint for inspecting, watching and lighting any waterway and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of the specified works or any protective works; and
- (d) in bringing the specified works or any protective works to the notice of users of the Trust’s network.
Costs of alterations, etc.
16
Any additional expenses which the Trust may reasonably incur in altering, reconstructing or maintaining the waterway under any powers existing at the date when this Order was made by reason of the existence of a specified workl, provided that 28 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, must be repaid by the undertaker to the Trust .
Making good of detriment; compensation and indemnity, etc.
17
- (1) If any detriment is caused by the construction or failure of the specified works or the protective works if carried out by the undertaker, the undertaker (if so required by the Trust ) must make good such detriment and pay to the Trust all reasonable expenses to which the Trust may be put, and compensation for any loss which the Trust may sustain, in making good or otherwise by reason of the detriment.
- (2) The undertaker is responsible for and must make good to the Trust all costs, charges, damages, expenses and losses not otherwise provided for in this Schedule which may be occasioned to or reasonably incurred by the Trust—
- (a) by reason of the construction of a specified work or a protective work or the failure of such a work; or
- (b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon the construction of a specified work or a protective work;
and subject to sub-paragraph (4) the undertaker must effectively indemnify and hold harmless the Trust from and against all claims and demands arising out of or in connection with any of the matters referred to in paragraphs (a) and (b).
- (3) The fact that any act or thing may have been done by the Trust on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision or in accordance with any directions or awards of an arbitrator does not (if it was done without negligence on the part of the Trust or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this paragraph.
- (4) The Trust must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand is to be made without the prior consent of the undertaker.
Details of capitalised sums to be provided
18
If the Trust or the undertaker cannot jointly agree the formula by which the capitalised sum is calculated it is to be settled by arbitration in accordance with article 42 (arbitration).
Arbitration
19
Any difference arising between the undertaker and the Trust under this Schedule (other than a difference as to the meaning or construction of this Schedule) is to be referred to and settled by arbitration in accordance with article 42 (arbitration).
Signed
Signed by authority of the Secretary of State for Transport
Martin Woods — Head of the Transport and Works Act Orders Unit — Department for Transport — 19th March 2013
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises Lancashire County Council (referred to in this Order as the undertaker) to construct a new dual carriageway road starting at junction 34 of the M6 motorway and ending at the eastern end of the Heysham M6 Link Phase 1 road at the A683/A589 Morecambe Road roundabout, and carry out all associated works. The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose. The Order also makes provision in connection with the maintenance of the new section of highway.
A copy of the Order plans and the book of reference mentioned in this Order and certified in accordance with article 40 of this Order (certification of plans, etc.) may be inspected free of charge during working hours at Lancashire County Council, County Hall, Preston, Lancashire, PR1 0LD.
Footnotes
[^f00001]: S.I. 2009/2264.
[^f00002]: 2008 c. 29.
[^f00003]: S.I. 2010/103.
[^f00004]: 1961 c. 33. Section 2(2) was amended by section 193 of, and paragraph 5 of Schedule 33 to, the Local Government, Planning and Land Act 1980 (c. 65). There are other amendments to the 1961 Act which are not relevant to this Order.
[^f00005]: 1965 c. 56. Section 3 was amended by section 70 of, and paragraph 3 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). Section 4 was amended by section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71). Section 5 was amended by sections 67 and 80 of, and Part 2 of Schedule 18 to, the Planning and Compensation Act 1991 (c. 34). Subsection (1) of section 11 and sections 3, 31 and 32 were amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67) and by section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). Section 12 was amended by section 56(2) of, and Part 1 to Schedule 9 to, the Courts Act 1971 (c. 23). Section 13 was amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c. 15). Section 20 was amended by section 70 of, and paragraph 14 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). Sections 9, 25 and 29 were amended by the Statute Law (Repeals) Act 1973 (c. 39). Section 31 was also amended by section 70 of, and paragraph 19 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34) and by section 14 of, and paragraph 12(2) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). There are other amendments to the 1965 Act which are not relevant to this Order.
[^f00006]: 1980 c. 66. Section 1(1) was amended by section 21(2) of the New Roads and Street Works Act 1991 (c. 22); sections 1(2), (3) and (4) were amended by section 8 of, and paragraph (1) of Schedule 4 to, the Local Government Act 1985 (c. 51); section 1(2A) was inserted, and section 1(3) was amended, by section 259 (1), (2) and (3) of the Greater London Authority Act 1999 (c. 29); sections 1(3A) and 1(5) were inserted by section 22(1) of, and paragraph 1 of Schedule 7 to, the Local Government (Wales) Act 1994 (c. 19). Section 36(2) was amended by section 4(1) of, and paragraphs 47(a) and (b) of Schedule 2 to, the Housing (Consequential Provisions) Act 1985 (c .71), by S.I. 2006/1177, by section 4 of, and paragraph 45(3) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c .11), by section 64(1) (2) and (3) of the Transport and Works Act 1992 (c. 42) and by section 57 of, and paragraph 5 of Part 1 of Schedule 6 to, the Countryside and Rights of Way Act 2000 (c. 37); section 36(3A) was inserted by section 64(4) of the Transport and Works Act 1992 and was amended by S.I. 2006/1177; section 36(6) was amended by section 8 of, and paragraph 7 of Schedule 4 to, the Local Government Act 1985 (c. 51); and section 36(7) was inserted by section 22(1) of, and paragraph 4 of Schedule 7 to, the Local Government (Wales) Act 1994 (c .19). Section 329 was amended by section 112(4) of, and Schedule 18 to, the Electricity Act 1989 (c. 29) and by section 190(3) of, and Part 1 of Schedule 27 to, the Water Act 1989 (c. 15). There are other amendments to the 1980 Act which are not relevant to this Order.
[^f00007]: 1990 c. 8. Section 206(1) was amended by section 192(8) of, and paragraphs 7 and 11 of Schedule 8 to, the Planning Act 2008 (c. 29) (date in force to be appointed see section 241(3), (4)(a), (c) of the 2008 Act). There are other amendments to the 1990 Act which are not relevant to this Order.
[^f00008]: 1991. c. 22. Section 48(3A) was inserted by section 124 of the Local Transport Act 2008 (c.26). Sections 79(4), 80(4), and 83(4) were amended by section 40 of, and Schedule 1 to, the Traffic Management Act 2004 (c. 18).
[^f00009]: 2008 c. 29.
[^f00010]: 1981 c. 67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). There are other amendments to the 1981 Act which are not relevant to this Order.
[^f00011]: 1991 c. 56.
[^f00013]: 1991 c. 57.
[^f00014]: 1981 c. 66. Sections 2 and 116 were amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11). There are other amendments to the 1981Act which are not relevant to this Order.
[^f00015]: 1981 c. 66. Sections 2(3), 6(2) and 11(6) were amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11). Section 15 was amended by sections 56 and 321(1) of, and Schedules 8 and 16 to, the Housing and Regeneration Act 2008 (c. 17). Paragraph 1 of Schedule 2 was amended by section 76 of, and Part 2 of Schedule 9 to, the Housing Act 1988 (c 50); section 161(4) of, and Schedule 19 to, the Leasehold Reform, Housing and Urban Development Act 1993 (c. 28); and sections 56 and 321(1) of, and Schedule 8 to, the Housing and Regeneration Act 2008. Paragraph 3 of Schedule 2 was amended by section 76 of, and Schedule 9 to, the Housing Act 1988 and section 56 of, and Schedule 8 to, the Housing and Regeneration Act 2008. Paragraph 2 of Schedule 3 was repealed by section 277 of, and Schedule 9 to, the Inheritance Tax Act 1984 (c. 51). There are amendments to the 1981Act which are not relevant to this Order.
[^f00016]: 2003 c. 21. There are amendments to this Act which are not relevant to this Order.
[^f00017]: 1990 c. 43. There are amendments to this Act which are not relevant to this Order.
[^f00018]: 1974 c.40, as amended at the date of the coming into force of this Order.
[^f00019]: 1978 c. 30.
[^f00021]: 1973 c. 26.
[^f00022]: S.I. 2013/675.
[^f00023]: 1995 c. i
[^f00024]: 1968 c. 73. This is amended by Schedule 2 to S.I. 2012/1659.
Editorial notes
[^key-4a3365d87625ee43e6db9cdce52f355f]: Art. 1 in force at 9.4.2013, see art. 1
[^key-be46f676c6255f5eb2c82b8ae7c7c32a]: Art. 2 in force at 9.4.2013, see art. 1
[^key-2e1ebbf4683aff293a59386a3b0bc17f]: Art. 3 in force at 9.4.2013, see art. 1
[^key-cb971e578bf1ed74145f77e02800c747]: Art. 4 in force at 9.4.2013, see art. 1
[^key-b67b8d886fe2369f8b952a1aaca1a2b5]: Art. 5 in force at 9.4.2013, see art. 1
[^key-50eacf7a133c7b8773962f1835c9e8e2]: Art. 6 in force at 9.4.2013, see art. 1
[^key-9360ccf3b897387c6606d9cd024dc8c8]: Art. 7 in force at 9.4.2013, see art. 1
[^key-4571b080c94a980929c9667a10e0de94]: Art. 8 in force at 9.4.2013, see art. 1
[^key-3da8f3196fbe13039d0340779cc898e9]: Art. 9 in force at 9.4.2013, see art. 1
[^key-fa6414932ae08dd0a0da58133317c6df]: Art. 10 in force at 9.4.2013, see art. 1
[^key-8c85a956e0ed715824385af8496e1aca]: Art. 11 in force at 9.4.2013, see art. 1
[^key-be07937d8d54ffcc0ec957e6572d7bfb]: Art. 12 in force at 9.4.2013, see art. 1
[^key-5763cdc2d4f290aa676be0ae08124676]: Art. 13 in force at 9.4.2013, see art. 1
[^key-112fb10b93f82925f78927a8dc135355]: Art. 14 in force at 9.4.2013, see art. 1
[^key-61b6c672f8e2ba3ce3faf41c76f37557]: Art. 15 in force at 9.4.2013, see art. 1
[^key-b9b41d9f778904f7266899426d630db4]: Art. 16 in force at 9.4.2013, see art. 1
[^key-d8e5b0be8d6203b594e5ee31bd711552]: Art. 17 in force at 9.4.2013, see art. 1
[^key-c09b5146eacff931037d6c4228f369d0]: Art. 18 in force at 9.4.2013, see art. 1
[^key-90742a877615e624b9c07f5871213fda]: Art. 19 in force at 9.4.2013, see art. 1
[^key-418f2e8d14b9b557cac666794c80aba5]: Art. 20 in force at 9.4.2013, see art. 1
[^key-44608dde8d1c03879d4c8b70c8d26cd0]: Art. 21 in force at 9.4.2013, see art. 1
[^key-dedff7e8c8932d3ed7f41e0fc98a80fe]: Art. 22 in force at 9.4.2013, see art. 1
[^key-bfa7d89bc6ec7638ffdf082f84320ac4]: Art. 23 in force at 9.4.2013, see art. 1
[^key-7fa5b0bc9e99ed6e3a09310db886ef5e]: Art. 24 in force at 9.4.2013, see art. 1
[^key-c1a544c61d77c9df88b36734f4dfe89e]: Art. 25 in force at 9.4.2013, see art. 1
[^key-0f55a2c85aa1d7243e31d26774671ea3]: Art. 26 in force at 9.4.2013, see art. 1
[^key-365a1a919dfc72e7b16c7d9f370984a8]: Art. 27 in force at 9.4.2013, see art. 1
[^key-3624ef7c636d892d08e0a45ed88a0775]: Art. 28 in force at 9.4.2013, see art. 1
[^key-c8ef352bc1209c3ee0ba082ea5fe2a97]: Art. 29 in force at 9.4.2013, see art. 1
[^key-91806b1fdb567e7f2976139f70755131]: Art. 30 in force at 9.4.2013, see art. 1
[^key-1ba70d1745d7b710f36e58b332e10c23]: Art. 31 in force at 9.4.2013, see art. 1
[^key-1162e292a0b5fc6ad79f9880b2ed0871]: Art. 32 in force at 9.4.2013, see art. 1
[^key-5dd255145cfda336e7c81267e8f8ceb4]: Art. 33 in force at 9.4.2013, see art. 1
[^key-df0ba3e7751bc090681bf836a72556d7]: Art. 34 in force at 9.4.2013, see art. 1
[^key-68ebfc5cbbe47e21896305040cbef08a]: Art. 35 in force at 9.4.2013, see art. 1
[^key-8a50fb6368e49ca8e7f0151c123e843f]: Art. 36 in force at 9.4.2013, see art. 1
[^key-1f96e0d944ada23a60876fd499838d7d]: Art. 37 in force at 9.4.2013, see art. 1
[^key-b295311fcf94a32c9404304ccda0dd6d]: Art. 38 in force at 9.4.2013, see art. 1
[^key-6f7760a56667f751a32ac15d14636c3d]: Art. 39 in force at 9.4.2013, see art. 1
[^key-49ebd43dfa7c292cb322b349127be8ce]: Art. 40 in force at 9.4.2013, see art. 1
[^key-bef2d6405d9bda65aee8cad36cfb5146]: Art. 41 in force at 9.4.2013, see art. 1
[^key-648dc5859701b278a95b3f07ce31244e]: Art. 42 in force at 9.4.2013, see art. 1
[^key-09d2b3b005e95c51ec8a8d5adefc76fc]: Sch. 2 para. 1 in force at 9.4.2013, see art. 1
[^key-94b906237d038786604e3a931248dc24]: Sch. 2 para. 2 in force at 9.4.2013, see art. 1
[^key-93013cc6d140933a92b162ca9ced176f]: Sch. 2 para. 3 in force at 9.4.2013, see art. 1
[^key-7cda1736f108371d906d63bf164acc90]: Sch. 2 para. 4 in force at 9.4.2013, see art. 1
[^key-336dc8a19d47612cf0b3a1d9c67384a9]: Sch. 2 para. 5 in force at 9.4.2013, see art. 1
[^key-878325502658d01dea5296f1ac5d98d2]: Sch. 2 para. 6 in force at 9.4.2013, see art. 1
[^key-833c70fc2f8dddcb297deb0e84601592]: Sch. 2 para. 7 in force at 9.4.2013, see art. 1
[^key-7633fb1cc6e24fcc2e494fd7747171e6]: Sch. 2 para. 8 in force at 9.4.2013, see art. 1
[^key-c5780e66305c41d73f1bbb9a4aefd3ad]: Sch. 2 para. 9 in force at 9.4.2013, see art. 1
[^key-37afb6566adde40a75c19a5712eb5c6e]: Sch. 2 para. 10 in force at 9.4.2013, see art. 1
[^key-a5fe44c1ffa1b34a5f5426447604b093]: Sch. 2 para. 11 in force at 9.4.2013, see art. 1
[^key-53cefc224a8df72da33013ab972ab3e4]: Sch. 2 para. 12 in force at 9.4.2013, see art. 1
[^key-4b7d15abe1bdbe63539bb4ab0551d6b5]: Sch. 2 para. 13 in force at 9.4.2013, see art. 1
[^key-679163b590383366671a12407260aec5]: Sch. 2 para. 14 in force at 9.4.2013, see art. 1
[^key-2860036346dbde5f8a9803102a37011d]: Sch. 2 para. 15 in force at 9.4.2013, see art. 1
[^key-f8ad1367db1dd66361f332efa5aba465]: Sch. 2 para. 16 in force at 9.4.2013, see art. 1
[^key-6d5cd8c16112d2c7c1d10b49e0374aee]: Sch. 2 para. 17 in force at 9.4.2013, see art. 1
[^key-c7beb79ae5b96ae01b004bb142c7dda3]: Sch. 2 para. 18 in force at 9.4.2013, see art. 1
[^key-d7c91497d789c177da3c03479dbe7b77]: Sch. 2 para. 19 in force at 9.4.2013, see art. 1
[^key-c8af315868c197478b7cff5c611a706e]: Sch. 2 para. 20 in force at 9.4.2013, see art. 1
[^key-caeb26b51411ad31f84bb6c26f275b34]: Sch. 2 para. 21 in force at 9.4.2013, see art. 1
[^key-f92957081ee349c984498a5846bc4d0e]: Sch. 2 para. 22 in force at 9.4.2013, see art. 1
[^key-8470f5b33ccb0f517cf57e4e556cfcc2]: Sch. 2 para. 23 in force at 9.4.2013, see art. 1
[^key-55f45a3b23704464de78c9e912f86578]: Sch. 5 para. 1 in force at 9.4.2013, see art. 1
[^key-8f058b7d18b290d21e2459c902dd730a]: Sch. 5 para. 2 in force at 9.4.2013, see art. 1
[^key-cc438f8fb54e31c77ceaec22bb08cf18]: Sch. 5 para. 3 in force at 9.4.2013, see art. 1
[^key-5672352272eec3cf2fa74b82930a4e84]: Sch. 5 para. 4 in force at 9.4.2013, see art. 1
[^key-706cc362aedb8fc3ad049b98e7b3e1e4]: Sch. 10 para. 1 in force at 9.4.2013, see art. 1
[^key-cc1da519b557a250c951165d6f13e342]: Sch. 10 para. 2 in force at 9.4.2013, see art. 1
[^key-74f8dfcbf3f4271db52995181006b074]: Sch. 10 para. 3 in force at 9.4.2013, see art. 1
[^key-62c0c8d89840139fb2d68634b29561b8]: Sch. 10 para. 4 in force at 9.4.2013, see art. 1
[^key-6355c16fbb1f768bc93d7c59572095f0]: Sch. 10 para. 5 in force at 9.4.2013, see art. 1
[^key-aeedaea13ec240d2afd7db6a2f39db58]: Sch. 10 para. 6 in force at 9.4.2013, see art. 1
[^key-288b9fe88627331f113b2ae021fe4cd0]: Sch. 10 para. 7 in force at 9.4.2013, see art. 1
[^key-c1963c27696c37608d89243afd2d1566]: Sch. 10 para. 8 in force at 9.4.2013, see art. 1
[^key-ca5baa71773eb2ed440cdc1e789098a4]: Sch. 10 para. 9 in force at 9.4.2013, see art. 1
[^key-a6c7b957056d1304a9a912666252dadb]: Sch. 13 para. 1 in force at 9.4.2013, see art. 1
[^key-23125d9069e58f468d955ca91274b804]: Sch. 13 para. 2 in force at 9.4.2013, see art. 1
[^key-d88666956dc79a1f9971a4b15b010838]: Sch. 13 para. 3 in force at 9.4.2013, see art. 1
[^key-d9d54bb0f87984c3670e8fe8bdf05bff]: Sch. 13 para. 4 in force at 9.4.2013, see art. 1
[^key-d783a7cef0aeffaebc5b1af5b2232874]: Sch. 13 para. 5 in force at 9.4.2013, see art. 1
[^key-d02ce8bfc26e31ee195932d671ac2443]: Sch. 13 para. 6 in force at 9.4.2013, see art. 1
[^key-564291ce92532dbb33ce5c305dc015d2]: Sch. 13 para. 7 in force at 9.4.2013, see art. 1
[^key-f2d70b0073b8348cc78d9190add6f767]: Sch. 13 para. 8 in force at 9.4.2013, see art. 1
[^key-655ff8b2076140705297931f4b8ce6c4]: Sch. 13 para. 9 in force at 9.4.2013, see art. 1
[^key-cb987ae2516b90544984307165f4f4a3]: Sch. 13 para. 10 in force at 9.4.2013, see art. 1
[^key-d3caec455a14745b2a1141454a62801b]: Sch. 13 para. 11 in force at 9.4.2013, see art. 1
[^key-798a889f1d7a2fdd841b529e362cbd81]: Sch. 13 para. 12 in force at 9.4.2013, see art. 1
[^key-40646856817c2a13a5a90e9463fedb35]: Sch. 13 para. 13 in force at 9.4.2013, see art. 1
[^key-f2f7e615433442bf40beeb170f143b0e]: Sch. 13 para. 14 in force at 9.4.2013, see art. 1
[^key-4a15078efe4fa65961ab93da1d34826c]: Sch. 13 para. 15 in force at 9.4.2013, see art. 1
[^key-f47cea517ddae1792e05e69354dd901d]: Sch. 13 para. 16 in force at 9.4.2013, see art. 1
[^key-cee3c8d708cff073cfd7c4b3e3cdbe32]: Sch. 13 para. 17 in force at 9.4.2013, see art. 1
[^key-1f9bb62792ba31c8be130a47d4548c02]: Sch. 13 para. 18 in force at 9.4.2013, see art. 1
[^key-06c949f947d8105c558e554188a8be63]: Sch. 13 para. 19 in force at 9.4.2013, see art. 1
[^key-6054fda9c8ed5d9d0907742d46557136]: Sch. 1 in force at 9.4.2013, see art. 1
[^key-58c698d16c883594371e747a42ba9b01]: Sch. 3 Pt. 1 in force at 9.4.2013, see art. 1
[^key-e54534b1318181c56eca2388dc84f76c]: Sch. 3 Pt. 2 in force at 9.4.2013, see art. 1
[^key-d688d3ce8d6b6fb447111ad9397ce06f]: Sch. 4 in force at 9.4.2013, see art. 1
[^key-402a6cec9d53b50c2e28b00074abc406]: Sch. 6 Pt. 1 in force at 9.4.2013, see art. 1
[^key-f5de15040132440c30fc589d8a7ee16a]: Sch. 6 Pt. 2 in force at 9.4.2013, see art. 1
[^key-5043027cc7bb912b06707c6646e487b1]: Sch. 6 Pt. 3 in force at 9.4.2013, see art. 1
[^key-90d9f21e93e568318852435f3b85e109]: Sch. 6 Pt. 4 in force at 9.4.2013, see art. 1
[^key-5c6f616a6c60721cfc182108d9b99459]: Sch. 7 in force at 9.4.2013, see art. 1
[^key-9f16f21759b316a058648ebf7353ac18]: Sch. 8 Pt. 1 in force at 9.4.2013, see art. 1
[^key-e1ec4e4198ecb847062b1ca4b99d3764]: Sch. 8 Pt. 2 in force at 9.4.2013, see art. 1
[^key-e15e0cb82996d90b7e9e3850d06c095f]: Sch. 9 in force at 9.4.2013, see art. 1
[^key-4351502ced04ef460002973d986bcd5a]: Sch. 11 in force at 9.4.2013, see art. 1
[^key-5474c306e05324daff9cb63e17a1e4b3]: Sch. 12 in force at 9.4.2013, see art. 1
[^key-d828580588d7dbc62af3f22cde7f7fa7]: Words in Sch. 2 para. 23 substituted (26.3.2015) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) (Amendment) Order 2015 (S.I. 2015/571), arts. 1, 5
[^key-c720d98bf5448f23afb6144e95568f4e]: Words in Sch. 1 omitted (26.3.2015) by virtue of The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) (Amendment) Order 2015 (S.I. 2015/571), arts. 1, 4(a)
[^key-e88ebf900ce515cfce911a7e3bb1a45f]: Words in Sch. 1 omitted (26.3.2015) by virtue of The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) (Amendment) Order 2015 (S.I. 2015/571), arts. 1, 4(b)
[^key-ce46583132f56352a0dd091c099f1498]: Words in art. 16(7) substituted (1.1.2017) by The Environmental Permitting (England and Wales) Regulations 2016 (S.I. 2016/1154), reg. 1(1), Sch. 29 para. 50 (with regs. 1(3), 77-79, Sch. 4)
[^key-a22ecc6eedd435c273b0e2daf96ffe39]: Words in Sch. 2 para. 5(5) substituted (30.11.2017) by The Conservation of Habitats and Species Regulations 2017 (S.I. 2017/1012), reg. 1(2), Sch. 6 para. 30
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.