The Contracts for Difference (Electricity Supplier Obligations) Regulations 2014

Type Statutory-Instrument
Publication 2014-07-31
Last updated 2025-07-22
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

[^key-9add1d18d5a3f440a18d4ff617b74c91]: Words in reg. 23(7)(a)(i) omitted (1.4.2022) by virtue of The Electricity Supplier Payments (Amendment) Regulations 2022 (S.I. 2022/401), regs. 1(2), 2(c)

[^key-3e8d19ce13762ca5885aa93a064d7766]: Reg. 23(7)(a)(ii)-(iv) inserted (1.4.2022) by The Electricity Supplier Payments (Amendment) Regulations 2022 (S.I. 2022/401), regs. 1(2), 2(d)

[^key-2b3ddbdd65660d2b74d5fe5729be8036]: Reg. 4(1) formula substituted (1.4.2023) by The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(3)(a)(i)

[^key-a3f55c88649ee25662effc4b52630670]: Words in reg. 4(1) omitted (1.4.2023) by virtue of The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(3)(a)(ii)

[^key-3269f0b9c452177c12d7976555f914ba]: Words in reg. 4(1) omitted (1.4.2023) by virtue of The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(3)(a)(iii)

[^key-398cc1b5f58cb2083cbdb6a28991812a]: Reg. 4(1A) omitted (1.4.2023) by virtue of The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(3)(b)

[^key-17de0ca9ffe1322239c5bb31c25d97cb]: Reg. 4(1B) omitted (1.4.2023) by virtue of The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(3)(c)

[^key-9d1970492f8eff8b48f78f220d5e86c9]: Words in reg. 5 substituted (1.4.2023) by The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(4)

[^key-daaaa28394eb0e3ae9e56ab734b5abfd]: Words in reg. 2(1) inserted (1.4.2023) by The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(2)(a)

[^key-c7ceae7aa8a9318838e399c81f6dd6b3]: Words in reg. 2(1) omitted (1.4.2023) by virtue of The Electricity Supplier Obligations (Green Excluded Electricity) (Amendment) Regulations 2023 (S.I. 2023/389), regs. 1(2), 2(2)(b)

[^key-08506479eba001f63877b57ce56df000]: Words in reg. 2(1) inserted (1.10.2024) by The Energy Act 2023 (Consequential Amendments) Regulations 2024 (S.I. 2024/706), regs. 1(1), 28(a); S.I. 2024/957, reg. 2(a)

[^key-5affc3edc882a43210b9b10237344bbc]: Words in reg. 2(1) substituted (1.10.2024) by The Energy Act 2023 (Consequential Amendments) Regulations 2024 (S.I. 2024/706), regs. 1(1), 28(b); S.I. 2024/957, reg. 2(a)

[^key-31b40f4a4b3358034e270a838aed4a40]: Words in reg. 2(1) inserted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 3

[^key-7398783d92dab0d598614700793227e9]: Words in reg. 4(1) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 4(a)(i)

[^key-49f2bb946b4c5a1c2004c431469c6ea9]: Words in reg. 4(1) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 4(a)(ii)

[^key-3a74d7367b6681bfbc745c9b8066933b]: Words in reg. 4(2) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 4(b)(i)

[^key-6f5e0cf3c09524ebd474a757554ec74b]: Words in reg. 4(2) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 4(b)(ii)

[^key-1aa3e178a7f22687cd25f1542ea0d1ef]: Reg. 7(2) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 5(a)

[^key-6379db8fef59365ef14a23ce4e8c948e]: Words in reg. 7(3)(a) omitted (12.11.2024) by virtue of The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 5(b)

[^key-a957e78539ab781d49b1c2674a0b5fe5]: Words in reg. 7(5) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 5(c)(i)

[^key-a12a79b4fba90fab5fa210ad40531a66]: Words in reg. 7(5) substituted (12.11.2024) by The Contracts for Difference (Electricity Supplier Obligations) (Amendment) Regulations 2024 (S.I. 2024/1159), regs. 1(2), 5(c)(ii)

[^key-cc37776f949137d1f9967cbbde1852ed]: Words in reg. 2(1) inserted (22.7.2025) by The Contracts for Difference (Miscellaneous Amendments) (No. 3) Regulations 2025 (S.I. 2025/903), regs. 1(2), 13

[^key-396414c03b34bdf10e6b2db2e3eed9ec]: Words in reg. 4(1) inserted (22.7.2025) by The Contracts for Difference (Miscellaneous Amendments) (No. 3) Regulations 2025 (S.I. 2025/903), regs. 1(2), 14(a)

[^key-26ee6e6c5c96ea916c7ba6e88496c2b1]: Words in reg. 4(2) inserted (22.7.2025) by The Contracts for Difference (Miscellaneous Amendments) (No. 3) Regulations 2025 (S.I. 2025/903), regs. 1(2), 14(b)(i)

[^key-faf06a7397f3d57467a39e9596da5253]: Words in reg. 4(2) inserted (22.7.2025) by The Contracts for Difference (Miscellaneous Amendments) (No. 3) Regulations 2025 (S.I. 2025/903), regs. 1(2), 14(b)(ii)

[^key-e7ec0559f6a4e5397a58ca4bdd150e10]: Words in reg. 7(5) inserted (22.7.2025) by The Contracts for Difference (Miscellaneous Amendments) (No. 3) Regulations 2025 (S.I. 2025/903), regs. 1(2), 15

Netting of payments by the CFD counterparty

30A
  • (1) This regulation applies where—
  • (a) the CFD counterparty must make a payment of an amount to an electricity supplier under these Regulations by a certain date (the “counterparty payment”); and
  • (b) that supplier must make a payment of an amount to the CFD counterparty by the same date (the “supplier payment”).
  • (2) Where the counterparty payment is more than the supplier payment, payment of the counterparty payment less the supplier payment discharges—
  • (a) the CFD counterparty’s obligation to make the counterparty payment, and
  • (b) the supplier’s obligation to make the supplier payment.
  • (3) Where the counterparty payment is less than the supplier payment, payment of the supplier payment less the counterparty payment discharges—
  • (a) that supplier’s obligation to make the supplier payment, and
  • (b) the CFD counterparty’s obligation to make the counterparty payment.
  • (4) Where this regulation applies and the counterparty payment is equal to the supplier payment—
  • (a) the CFD counterparty’s obligation to make the counterparty payment is discharged, and
  • (b) the supplier’s obligation to make the supplier payment is discharged.

Discharge of obligations by payment

Use of payments

Apportioning sums to CFDs

Application of apportionment to CFDs

Interest

29A

Regulation 30A has effect as if—

  • (a) each reference in paragraph (1) to “the CFD counterparty” is to “a CFD counterparty”,
  • (b) the reference in paragraph (2)(a) to “the CFD counterparty” is to “that CFD counterparty”,
  • (c) the reference in paragraph (3)(b) to “the CFD counterparty” is to “that CFD counterparty”,
  • (d) the reference in paragraph (4)(a) to “the CFD counterparty” is to “that CFD counterparty”.
14A
  • (1) This regulation applies where the CFD counterparty is of the opinion that there is a high degree of likelihood that it will collect significantly more from suppliers under regulations 8(1) and 11(1) in respect of a quarterly obligation period than the amount it requires to be able to make all payments it is required to make during the reserve period which commences during that quarterly obligation period, taking into account any SoS funds that the Secretary of State has specified will be available in respect of that reserve period and that the Secretary of State has specified should be taken into account when adjusting the total reserve amount.
  • (2) Subject to paragraph (3), where this regulation applies the CFD counterparty may determine again the total reserve amount in respect of that quarterly obligation period in accordance with regulation 10(1)(a) and (5) (and for the purposes of this regulation the amount after it has been determined again is the “reduced total reserve amount”).
  • (3) The CFD counterparty may not make a determination under paragraph (2) in respect of a total reserve amount after the date which is 5 working days before the date electricity suppliers must make a reserve payment in respect of that total reserve amount under regulation 11(1).
  • (4) Where the CFD counterparty makes a determination under paragraph (2) in respect of a quarterly obligation period, it must—
  • (a) publish a notice setting out its determination of the reduced total reserve amount for that period;
  • (b) recalculate the amount (the “reduced reserve payment”) each supplier must pay under regulation 11(1) in respect of that period in accordance with regulation 11(3), and
  • (c) issue a notice to each electricity supplier who was issued a notice under regulation 10(4) in respect of that period setting out the amount that supplier must pay under regulation 11(1) in respect of that period.
  • (5) A notice under paragraph (4)(c) may only be issued before a reconciliation notice has been issued under regulation 15(3) in respect of the same obligation period.
  • (6) Where the CFD counterparty issues a notice to a supplier under paragraph (4)(c) and that supplier has already made a reserve payment in respect of the quarterly obligation period to which it relates which exceeds the reduced reserve payment due from that supplier, the CFD counterparty must pay back to that supplier the difference between the amount of that reserve payment and the reduced reserve payment now due from that supplier as soon as reasonably practicable.
13A

Regulation 14A has effect as if every reference to “the CFD counterparty” is to “a CFD counterparty” except the reference in paragraph (2), and the second reference in paragraph (5), which are to “that CFD counterparty”.

Determination of reduced total reserve amount

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.