The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014
| Title | Ref | Text |
|---|---|---|
| CoCP Part B | GREPS1 | Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders. |
| Detailed design approval for permanent above-ground structures | GREPS2 | (1) Construction of any permanent above-ground structure shall not commence until details of the design (including external appearance and materials), which shall accord with the indicative features on the Proposed site features plan (Drawing Nos. DCO-PP-23X-GREPS-240010), the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Details of works to listed buildings and structures | GREPS3 | (1) Works to the East Beam Engine House shall not commence until details of those works, which shall accord with the design principles for this site, indicative plans, sections and elevations (Drawing Nos. DCO-PP-23X-GREPS-240012, DCO-PP-23X-GREPS-240014 – rev 1, DCO-PP-23X-GREPS-240015 – rev 1, DCO-PP-23X-GREPS-240018 – rev 1, DCO-PP-23X-GREPS-240019 – rev 1, DCO-PP-23X-GREPS-240021 – rev 1, DCO-PP-23X-GREPS-240022 – rev 1, DCO-PP-23X-GREPS-240023 – rev 1, DCO-PP-23X-GREPS-240026) and the approved maximum extent of loss of listed structures (Drawing Nos. DCO-PP-23X-GREPS-240020 – rev 1 and DCO-PP-23X-GREPS-240024 – rev 1), are submitted to and approved by the relevant planning authority in consultation with the HBMCE— (2) The details required shall include the following— detailed drawings showing all fixings to the East Beam Engine House detailed drawings of the lantern, fenestration and openings to the East Beam Engine House construction method statement including engineering drawings a list of proposed materials. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE. |
| Details of works to listed buildings | GREPS4 | (1) Works to the listed sunken staircase to the west of the podium of the East Beam Engine House over the auxiliary pump chamber (as relevant) shall not commence until the following details are submitted to and approved by the relevant planning authority in consultation with the HBMCE— works to protect the entrance podium and East Beam Engine House works to remove the sunken staircase including the western wall, store and re-use the York stone steps and bricks for the western wall and re-use the historic hand rail posts on the entrance podium to the east of the stairs. (2) Materials of heritage significance in b above shall be re-used in accordance with the principles set out in Section 3.6 of the Heritage Statement. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE. |
| Protective works to listed buildings | GREPS5 | (1) Works to the East Beam Engine House shall not commence until details of the protective measures to prevent strike damage to the Grade II listed beam engine houses, and central boiler house, the Grade II listed coal sheds, and the Grade II listed Network Rail viaduct are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE. |
| Landscaping works | GREPS6 | (1) Construction of the permanent above-ground structures shall not commence until details of the landscaping works, which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) Unless otherwise agreed by the relevant planning authority, the landscaping information required in paragraph (1) above shall comprise details of all hard and soft landscaping works including: a. location, quantity, species, size and density of any proposed planting b. cultivation, importation of materials and other operations to ensure plant establishment c. monitoring and maintenance (including any maintenance or restoration of landscaping required after tunnel commissioning) d. proposed finished ground levels e. hard-surfacing materials f. minor structures such as furniture, refuse or other storage units, signs and lighting g. retained historic landscape features and proposals for restoration, where relevant h. a programme for implementation of all landscaping works i. details of fencing/enclosures j. vehicular and pedestrian access, parking and circulation areas, (including details of areas of public access) k. proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports l. details of existing trees to be retained (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. (4) The approved landscaping works shall be carried out by suitably trained or qualified personnel to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice. Replacement trees and shrubs (5) If, within a period of five years from the date of the planting of any tree or shrub, that tree or shrub (or any tree or shrub planted to replace it) is uprooted or destroyed or dies, another tree or shrub of the same species and size as that originally planted shall be planted in the same place, unless the relevant planning authority approves any variation. |
| Contaminated land | GREPS7 | Site-specific remediation strategy (1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Archaeology | GREPS8 | (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body. |
| Construction traffic management plan | GREPS9 | (1) Work No.23a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Travel plan | GREPS10 | (1) Work No. 23a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 23a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Specification of accesses (construction and operational) | GREPS11 | (1) No alterations shall be made to any existing access or any new access provided until details of the design, which shall accord with the design principles for this site, are submitted to and approved by the local highway authority. Any such works shall be completed prior to their use. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the highway authority. |
| Surface water drainage | GREPS12 | (1) Construction of the permanent above-ground structures or landscaping shall not commence until details of the surface water drainage system (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development. |
| Operational noise | GREPS13 | (1) Use of the authorised development shall not commence until a noise report is submitted to and approved by the relevant planning authority. This report shall demonstrate that baseline noise design rating levels for plant and machinery are 5dB (A) below the typical background noise level , as defined in British Standard 4142—1997, at the nearest residential receptor over the operational period of the plant. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
King Edward Memorial Park Foreshore
23
The table below sets out the specific requirements for the King Edward Memorial Park Foreshore site—
| Title | Ref | Text |
|---|---|---|
| CoCP Part B | KEMPF1 | Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders. |
| Location of permanent works | KEMPF2 | (1) The permanent foreshore structure and river wall shall not extend beyond the alignment shown on the Site works parameter plan. (2) Should the alignment be less than the maximum extent shown on the Site works parameter plan, details of the amended alignment, which shall accord with the design principles for this site, shall be submitted to and approved by the relevant planning authority in consultation with the Port of London Authority and the Environment Agency and thereafter be carried out in accordance with the approved details. |
| Detailed design approval for permanent above-ground structures | KEMPF3 | (1) Construction of any permanent above-ground structure shall not commence until details of the design (including size, external appearances and materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Detailed design approval for signature ventilation columns | KEMPF4 | (1) Construction of the ventilation columns shall not commence until details of the height, dimensions, external appearance and materials, which shall accord with the design principles for this site are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The ventilation columns at this site shall not exceed 6.5 metres in height. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE. (4) Notwithstanding the notes on drawing DCO-PP-900-ZZZZZ-290003 – Rev 2 there is no requirement for the signature design to be used at this site. |
| Detailed design approval for river wall and foreshore structure | KEMPF5 | (1) Construction of Work No. 24b (iv) shall not commence until details of the design (including external appearance and materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency in respect of land based access to flood defences and potential for ecological enhancements. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency. |
| Landscaping works | KEMPF6 | (1) Construction of the permanent above-ground structures shall not commence until details of the landscaping works (excluding details for approval under Requirement KEMPF7), which shall accord with the indicative features on the Proposed landscape plan (Drawing No. DCO-PP-24X-KEMPF-250009 – rev 1), the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority. (2) Unless otherwise agreed by the relevant planning authority, the landscaping information required in paragraph (1) above shall comprise details of all hard and soft landscaping works including: a. location, quantity, species, size and density of any proposed planting b. cultivation, importation of materials and other operations to ensure plant establishment c. monitoring and maintenance (including any maintenance or restoration of landscaping required after tunnel commissioning) d. proposed finished ground levels e. hard-surfacing materials f. minor structures such as furniture, refuse or other storage units, signs and lighting g. retained historic landscape features and proposals for restoration, where relevant h. a programme for implementation of all landscaping works i. details of fencing/enclosures j. vehicular and pedestrian access, parking and circulation areas, (including details of areas of public access) k. proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports l. details of existing trees to be retained (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. (4) The approved landscaping works shall be carried out by suitably trained or qualified personnel to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice. Replacement trees and shrubs (5) If, within a period of five years from the date of the planting of any tree or shrub, that tree or shrub (or any tree or shrub planted to replace it) is uprooted or destroyed or dies, another tree or shrub of the same species and size as that originally planted shall be planted in the same place, unless the relevant planning authority approves any variation. |
| Works to reconfigure the multi-purpose sports pitch, relocate the children’s play area and associated landscaping | KEMPF7 | (1) Construction shall not commence until details of the works to reconfigure the multi-purpose sports pitch, relocate the children’s play area and associated landscaping, which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority. (2) The details required in paragraph (1) above shall, unless otherwise agreed by the relevant planning authority, include— proposed finished ground levels hard-surfacing materials associated equipment or facilities for play implementation timetables for all landscaping works details of fencing/enclosures. (3) Construction of Work No. 24b(x) shall not commence until the details in paragraph (1) above have been implemented. (4) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Temporary works platform | KEMPF8 | (1) The temporary works platform shall not extend beyond the alignment shown on the Site works parameter plan. (2) Should the alignment be less than the maximum extent shown on the Site works parameter plan, construction of the temporary works platform shall not commence until details of the proposed structure(s) (including additional lengths of cofferdam, temporary decking areas and pontoons) are submitted to and approved by the Port of London Authority in consultation with the Environment Agency. |
| Contaminated land | KEMPF9 | Site-specific remediation strategy (1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Archaeology | KEMPF10 | (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body. |
| Construction traffic management plan | KEMPF11 | (1) Work No. 24a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Travel plan | KEMPF12 | (1) Work No. 24a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 24a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Specification of accesses (construction and operational) | KEMPF13 | (1) No alterations shall be made to any existing access or any new access provided until details of the design, which shall accord with the design principles for this site, are submitted to and approved by the local highway authority. Any such works shall be completed prior to their use. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the highway authority. |
| Surface water drainage | KEMPF14 | (1) Construction of the permanent above-ground structures or landscaping shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development. |
| Highway works | KEMPF15 | (1) Authorised development consisting of construction in or alteration of The Highway or the construction or alteration of any highway structures which form part of The Highway shall not commence until details of the design are submitted to and approved by the local highway authority. (2) The information required in paragraph 1 above shall include details of any permanent works for a new or altered surface and foul water drainage system for The Highway and any permanent works for a new or modified highway lighting scheme for The Highway. (3) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the local highway authority. |
| Section 106 Agreement / Undertaking | KEMPF16 | The authorised development shall not commence on this site unless and until the undertaker enters into the King Edward Memorial Park Foreshore Section 106 Agreement / Undertaking (in accordance with the obligations specified in the draft at doc. ref. APP119.15). |
| Commissioning works | KEMPF17 | (1) On or before the completion of the landscaping works approved further to requirement KEMPF6 (landscaping), the undertaker shall give notice to the relevant planning authority. (2) (Save for works carried out in accordance with (5) below) within 1 month of the notice under (1) the undertaker shall: a. remove all hoarding or other temporary enclosure from the site; and b. make the site publically accessible in accordance with the approved landscape scheme. (3) The undertaker shall provide a ‘commissioning notice’ to the relevant planning authority at least 2 months before undertaking any commissioning works. The notice shall include: a. a programme for the commissioning works; and b. a location plan for any fencing or hoarding associated with those works (including identifying areas to be accessible to the public). (4) The undertaker shall provide a ‘commissioning confirmation notice’ 21 days prior to starting the commissioning works, confirming the date of commencement of commissioning. (5) The commissioning works shall be undertaken in accordance with the programme in the commissioning notice and the location plan unless otherwise agreed with the relevant planning authority. |
| Working hours | KEMPF18 | Notwithstanding anything said in the CoCP Part B and any other provisions or requirements, unless otherwise agreed with the relevant planning authority standard working hours at King Edward Memorial Park Foreshore site shall not include 08:00 to 13:00 Saturday. The maintenance period will not be limited during the period and will include 08:00 to 13:00 Saturdays. |
Bekesbourne Street
24
The table below sets out the specific requirements for the Bekesbourne Street site—
| Title | Ref | Text |
|---|---|---|
| CoCP Part B | BEKST1 | Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders. |
| Detailed design approval for kiosk | BEKST2 | (1) Construction of the kiosk shall not commence until details of the design (including external appearance and materials), which shall accord with the indicative features on the Proposed landscape plan (Drawing No. DCO-PP-25X-BEKST-260006 – rev 1), the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Contaminated land | BEKST3 | Site-specific remediation strategy (1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in 3 and 4 below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Archaeology | BEKST4 | (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body. |
| Construction traffic management plan | BEKST5 | (1) Work No.25 shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Section 106 Agreement / Undertaking | BEKST6 | The authorised development shall not commence on this site unless and until the undertaker enters into the Bekesbourne Street Section 106 Agreement / Undertaking (in accordance with the obligations specified in the draft at doc. ref. APP119.15). |
| Bekesbourne Street parking | BEKST7 | There shall be no permanent loss of on-street parking on Bekesbourne Street. |
| Street Trees | BEKST8 | (1) Prior to completion of Work No. 25 a scheme of replacement street tree planting shall be submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. (3) The approved landscaping works shall be carried out by suitably trained or qualified personnel to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice. Replacement trees and shrubs (4) If, within a period of five years from the date of the planting of any tree or shrub, that tree or shrub, or any tree or shrub planted to replace it is uprooted or destroyed or dies, another tree or shrub of the same species and size as that originally planted shall be planted in the same place, unless the relevant planning authority approves any variation. |
| Heritage interpretation | BEKST9 | (1) Prior to completion of the works (save for commissioning) any relevant details applicable to this site from the project wide heritage strategy required by PW11 shall be submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
Abbey Mills Pumping Station
25
The table below sets out the specific requirements for the Abbey Mills Pumping Station site—
| Title | Ref | Text |
|---|---|---|
| CoCP Part B | ABMPS1 | Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders. |
| Detailed design approval for permanent above-ground structures | ABMPS2 | (1) Construction of any permanent above-ground structure shall not commence until details of the design (including size, external appearances and materials), which shall accord with the design principles for this site and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the HBMCE. |
| Contaminated land | ABMPS3 | Site-specific remediation strategy (1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Archaeology | ABMPS4 | (1) No excavation shall be carried out until a SSAWSI (which shall accord with the OAWSI) is submitted to and approved by the relevant planning authority in consultation with the HBMCE. (2) The authorised development shall be carried out in accordance with the approved details by a suitably qualified person or body. |
| Construction traffic management plan | ABMPS5 | (1) Work No. 26a shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Travel plan | ABMPS6 | (1) Work No. 26a shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 26a and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Surface water drainage | ABMPS7 | (1) Construction of the permanent above-ground structures or landscaping shall not commence until details of the surface water drainage system for this site (including means of pollution control, an assessment of the hydrological and hydrogeological context and how the scheme shall be maintained and managed following completion), which shall accord with the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the Environment Agency. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with the Environment Agency, and completed prior to use of the authorised development. |
| Heritage interpretation | ABMPS8 | (1) Prior to completion of the works (save for commissioning) any relevant details applicable to this site from the project wide heritage strategy required by PW11 shall be submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
Beckton Sewage Treatment Works
26
The table below sets out the specific requirements for the Beckton Sewage Treatment Works site—
| Title | Ref | Text |
|---|---|---|
| CoCP Part B | BESTW1 | Until completion of construction the authorised development shall be carried out in accordance with the CoCP Part A subject to the site specific variations set out in CoCP Part B for this site, unless otherwise agreed with the relevant planning authority in consultation with other relevant stakeholders. |
| Contaminated land | BESTW2 | Site-specific remediation strategy (1) No works shall be carried out at this site (except for demolition of existing buildings, works in the highway including site access, works to trees and installation of monitoring equipment), unless otherwise agreed, until the following are submitted to and approved by the relevant planning authority in consultation with the Environment Agency— a. a preliminary risk assessment and site investigation scheme which identifies— all previous uses potential contaminants associated with those uses a conceptual model of the site indicating sources, pathways and receptors a qualitative risk assessment of any potentially unacceptable risks arising from contamination at the site a proposed site investigation scheme providing information for a detailed quantitative assessment of the risk to all receptors that may be affected, including those off-site. b. a remediation strategy which includes— a detailed quantitative risk assessment an options appraisal giving full details of the remediation measures required and how they shall be carried out a verification plan providing details of the data to be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action a programme for the submission of elements detailed in (3) and (4) below. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Verification report (3) Prior to completion of the works, a verification report demonstrating completion of the works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The report shall include results of sampling and monitoring carried out in accordance with the approved details to demonstrate that the site remediation criteria were met. It shall also include a plan for long-term monitoring of pollutant linkages, maintenance and arrangements for contingency action as identified in the verification plan. (4) The long-term monitoring and maintenance plan shall be implemented in accordance with the approved details, unless otherwise agreed with the relevant planning authority in consultation with the Environment Agency. Unexpected contamination (5) If, in carrying out any works on this site, contamination not previously identified is found to be present, then unless otherwise agreed by the relevant planning authority, no further development or works shall be carried out in the part of the site in which the contamination is identified until a remediation strategy is submitted to and approved by the relevant planning authority in consultation with the Environment Agency. The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
| Construction traffic management plan | BESTW3 | (1) Work No. 27 shall not commence until a traffic management plan (which shall accord with the CoCP) is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Travel plan | BESTW4 | (1) Work No. 27 shall not commence until a site-specific construction workforce travel plan, which shall accord with the Draft Project Framework Travel Plan, is submitted to and approved by the relevant planning authority in consultation with TfL. (2) The approved travel plan(s) shall be implemented from commencement of Work No. 27 and remain in place for the duration of the construction works, unless otherwise approved by the relevant planning authority in consultation with TfL. |
| Design Principles | BESTW5 | Work No. 27 shall be undertaken in accordance with Design Principles BESTW.01 – 05, unless otherwise approved by the relevant planning authority. |
| Heritage interpretation | BESTW6 | (1) Prior to completion of the works (save for commissioning) any relevant details applicable to this site from the project wide heritage strategy required by PW11 shall be submitted to and approved by the relevant planning authority. (2) The authorised development shall be carried out in accordance with the approved details, unless otherwise approved by the relevant planning authority. |
SCHEDULE 4 — STREETS SUBJECT TO STREET WORKS
| Borough | Street subject to street works | Relevant Site |
|---|---|---|
| London Borough of Ealing | Canham Road Warple Way Stanley Gardens | Acton Storm Tanks |
| London Borough of Hammersmith and Fulham | Chancellor’s Road Distillery Road | Hammersmith Pumping Station |
| London Borough of Wandsworth | The Embankment Lower Richmond Road Putney High Street Putney Bridge Glendarvon Street | Putney Embankment Foreshore |
| London Borough of Hammersmith and Fulham | Carnwath Road Wandsworth Bridge Road | Carnwath Road Riverside |
| London Borough of Wandsworth | Dormay Street The Causeway Armoury Way | Dormay Street |
| London Borough of Wandsworth | Neville Gill Close Buckhold Road | King George’s Park |
| London Borough of Wandsworth | York Road York Gardens | Falconbrook Pumping Station |
| Royal Borough of Kensington and Chelsea | Lots Road | Cremorne Wharf Depot |
| Royal Borough of Kensington and Chelsea | Chelsea Embankment The Bull Ring | Chelsea Embankment Foreshore |
| London Borough of Wandsworth | Kirtling Street Cringle Street | Kirtling Street |
| London Borough of Wandsworth | Nine Elms Lane | Heathwall Pumping Station |
| London Borough of Lambeth | Albert Embankment | Albert Embankment Foreshore |
| London Borough of Lambeth | Lambeth Palace Road Albert Embankment | Victoria Embankment Foreshore |
| London Borough of Southwark | Blackfriars Road | Blackfriars Bridge Foreshore |
| City of Westminster | Victoria Embankment | Victoria Embankment Foreshore |
| City of London | Victoria Embankment Blackfriars Underpass New Bridge Street Blackfriars Bridge Blackfriars Bridge head Blackfriars Road White Lion Hill Thames Path | Blackfriars Bridge Foreshore |
| London Borough of Southwark | Maguire Street Gainsford Street Shad Thames | Shad Thames Pumping Station |
| London Borough of Southwark | Chambers Street Loftie Street Bevington Street Bermondsey Wall West East Lane | Chambers Wharf |
| London Borough of Southwark | Chilton Grove Croft Street | Earl Pumping Station |
| London Borough of Lewisham | Chilton Grove Yeoman Street Croft Street | Earl Pumping Station |
| London Borough of Lewisham | Deptford Church Street Crossfield Street Coffey Street | Deptford Church Street |
| Royal Borough of Greenwich | Norman Road Greenwich High Road Unnamed pedestrian/cycle route between Norman Road and Creekside | Greenwich Pumping Station |
| London Borough of Tower Hamlets | Glamis Road | King Edward Memorial Park Foreshore |
| London Borough of Tower Hamlets | Bekesbourne Street Ratcliffe Lane | Bekesbourne Street |
| London Borough of Newham | Gay Road Abbey Lane | Abbey Mills |
| London Borough of Newham | Jenkins Lane | Beckton Sewage Treatment Works |
SCHEDULE 5 — STREETS SUBJECT TO ALTERATION OF LAYOUT
| Borough | Street to be altered | Description of alteration | Relevant Site |
|---|---|---|---|
| London Borough of Ealing | Canham Road | Works to provide site access, temporary removal of on street parking, introduction of temporary waiting restrictions and footway widening works. | Acton Storm Tanks |
| London Borough of Ealing | Warple Way | Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions | Acton Storm Tanks |
| London Borough of Ealing | Stanley Gardens | Works associated with the temporary modification to kerb line, temporary removal of on street parking and introduction of temporary waiting restrictions | Acton Storm Tanks |
| London Borough of Hammersmith and Fulham | Distillery Road | Works to provide site accesses | Hammersmith Pumping Station |
| London Borough of Hammersmith and Fulham | Chancellor’s Road | Temporary removal of on street parking and introduction of temporary waiting restrictions. Modification to kerb line on its junction with Distillery Road | Hammersmith Pumping Station |
| London Borough of Wandsworth | The Embankment | Works to provide site access, temporary removal of on street parking, the introduction of temporary waiting restrictions, formation of access to temporary slipway, temporary suspension of one-way, kerb line modifications and temporary removal of traffic island | Putney Embankment Foreshore |
| Works associated with environmental enhancement including footway surfacing and street furniture | |||
| London Borough of Wandsworth | Glendarvon Street | Temporary removal of on street parking and introduction of waiting restrictions | Putney Embankment Foreshore |
| London Borough of Wandsworth | Lower Richmond Road | Installation of ducting within carriageway and pedestrian site access gate | Putney Embankment Foreshore |
| London Borough of Wandsworth | Putney High Street/Putney Bridge | Installation of vent column | Putney Embankment Foreshore |
| Hammersmith and Fulham | Carnwath Road | Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions, footway and junction modifications at its junction with Wandsworth Bridge Road | Carnwath Road Riverside |
| Hammersmith and Fulham | Wandsworth Bridge Road | Modification to traffic signalised junction | Carnwath Road Riverside |
| London Borough of Wandsworth | Dormay Street | Works to provide site access | Dormay Street |
| London Borough of Wandsworth | The Causeway | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions | Dormay Street |
| London Borough of Wandsworth | Armoury Way | Temporary kerb line and junction modifications | Dormay Street |
| London Borough of Wandsworth | Neville Gill Close | Provision of construction access, temporary modification to kerb lines and pedestrian refuge | King George’s Park |
| London Borough of Wandsworth | Buckhold Road | Modification to kerb lines, pedestrian refuge and park entrance | King George’s Park |
| London Borough of Wandsworth | York Road | Works to provide site accesses and works associated with the relocation of bus stop facilities | Falconbrook Pumping Station |
| London Borough of Wandsworth | York Gardens | Woks to provide site access and temporary removal of parking | Falconbrook Pumping Station |
| Royal Borough of Kensington and Chelsea | Lots Road | Works to provide site access, temporary removal of on street parking and introduction of temporary waiting restrictions | Cremorne Wharf Depot |
| Royal Borough of Kensington and Chelsea | Chelsea Embankment | Works to provide site accesses Works to facilitate the provision of traffic management including provision of a temporary formal crossing, temporary removal of traffic island, provision of site hoarding Works associated with environmental enhancement including footway surfacing and street furniture | Chelsea Embankment Foreshore |
| Royal Borough of Kensington and Chelsea | The Bull Ring | Works associated with environmental enhancement including footway and carriageway surfacing and street furniture | Chelsea Embankment Foreshore |
| London Borough of Wandsworth | Kirtling Street | Works to provide site access, the provision of traffic management, temporary removal of on street parking and introduction of temporary waiting restrictions Works to undertake environmental enhancements | Kirtling Street |
| London Borough of Wandsworth | Cringle Street | Works to provide site access Works to undertake carriageway crossing for services Works associated with environmental enhancement including footway surfacing and street furniture | Kirtling Street |
| London Borough of Wandsworth | Nine Elms Lane | Works to provide site access Works associated with environmental enhancement including footway surfacing, tree planting, and street furniture | Heathwall Pumping Station |
| London Borough of Lambeth | Albert Embankment | Works to provide site access | Albert Embankment Foreshore |
| City of Westminster | Victoria Embankment | Works to provide site access. Works to facilitate the provision of traffic management, modification to waiting restrictions, removal of central carriageway reserve, provision of site hoarding, removal of cycle parking station Works to facilitate the temporary and permanent provision of access to boat moorings Works associated with environmental enhancement including footway surfacing and street furniture Works to construct a ramp and stairs on the footway | Victoria Embankment Foreshore |
| City of London | Victoria Embankment / Blackfriars Underpass / Blackfriars Bridge head / Blackfriars Bridge | Works to provide site access. Provision of traffic management including modification to waiting restrictions/loading bays, provision of site hoarding Works to facilitate the temporary and permanent provision of access to boat moorings Works associated with environmental enhancement including footway surfacing, step access from Blackfriars Bridge, lift access from Blackfriars Bridge, and street furniture Works to construct a ramp and stairs on the footway | Blackfriars Bridge Foreshore |
| City of London | New Bridge Street / Blackfriars Bridge / Blackfriars Bridge head | Provision of Temporary traffic management Provision of pedestrian lift | Blackfriars Bridge Foreshore |
| City of London | White Lion Hill | Modification of kerb, boundary wall, railing and provision of loading bay | Blackfriars Bridge Foreshore |
| London Borough of Southwark | Maguire Street and Shad Thames | Works to provide site access Works for the provision of traffic management, provision of temporary turning head, temporary removal of on street parking, introduction of temporary waiting restrictions and works for the provision of chambers, pipeline and ducts | Shad Thames Pumping Station |
| London Borough of Southwark | Gainsford Street | Works for the provision of in sewer equipment | Shad Thames Pumping Station |
| London Borough of Southwark | Chambers Street | Works to provide site access The temporary removal of on street parking and introduction of temporary waiting restrictions | Chambers Wharf |
| London Borough of Southwark | Loftie Street | Works to provide site access | Chambers Wharf |
| London Borough of Southwark | Bevington Street | The temporary removal of on street parking and introduction of temporary waiting restrictions, provision of temporary pedestrian refuge | Chambers Wharf |
| London Borough of Southwark | Croft Street | The temporary removal of on street parking and introduction of temporary waiting restrictions modification to traffic calming features Service connection to existing sewer | Earl Pumping Station |
| London Borough of Southwark | Chilton Grove | Works to provide site access and service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions | Earl Pumping Station |
| London Borough of Lewisham | Croft Street | Works to provide site access The temporary removal of on street parking and introduction of temporary waiting restrictions, modification to traffic calming features. Service connection to existing sewer | Earl Pumping Station |
| London Borough of Lewisham | Yeoman Street | Works to provide site access, service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions | Earl Pumping Station |
| London Borough of Lewisham | Chilton Grove | Works to provide site access, service connections to existing sewer, temporary removal of traffic calming, on street parking and introduction of temporary waiting restrictions | Earl Pumping Station |
| London Borough of Lewisham | Deptford Church Street | Works associated with the temporary suspension of the pedestrian crossing, provision of temporary pedestrian crossing, temporary removal of central carriageway divide, temporary removal of bus lanes. Temporary relocation of bus stops introduction of temporary waiting restrictions Works associated with environmental enhancement including footway surfacing and street furniture | Deptford Church Street |
| London Borough of Lewisham | Coffey Street | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions Works associated with temporary one way use, including associated signs Works associated with environmental enhancement including footway surfacing and street furniture | Deptford Church Street |
| London Borough of Lewisham | Crossfield Street | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions. Works associated with temporary one way use, including associated signs Works to form a temporary traffic management system and emergency evacuation point Works associated with the provision of a temporary section of carriageway linking Crossfield Road to Coffey Street Works associated with environmental enhancement including footway surfacing and street furniture | Deptford Church Street |
| Royal Borough of Greenwich | Norman Road | Works to provide site access | Greenwich Pumping Station |
| Royal Borough of Greenwich | Greenwich High Road | Works to provide site access | Greenwich Pumping Station |
| Royal Borough of Greenwich | Unnamed pedestrian/cycle route between Norman Road and Creekside | Temporary diversion of route and associated works | Greenwich Pumping Station |
| London Borough of Tower Hamlets | Glamis Road | Works to provide site access Temporary removal of on street parking and introduction of temporary waiting restrictions, modification to traffic signal stop lines | King Edward Memorial Park Foreshore |
| London Borough of Tower Hamlets | Bekesbourne Street | Temporary removal of on street parking and introduction of temporary waiting restrictions, provision of construction area, provision of plant (control kiosk) | Bekesbourne Street |
| London Borough of Tower Hamlets | Ratcliffe Lane | Provision of construction area, provision of plant (vent pipe), temporary removal of on street parking and introduction of temporary waiting restrictions | Bekesbourne Street |
| London Borough of Newham | Gay Road | Works to provide site access, temporary removal of on street parking, and the introduction of temporary waiting restrictions | Abbey Mills Pumping Station |
| London Borough of Newham | Abbey Lane | Temporary removal of on street parking and introduction of temporary waiting restrictions | Abbey Mills Pumping Station |
| London Borough of Newham | Jenkins Lane | Works to provide construction / permanent site access | Beckton Sewage Treatment Works |
SCHEDULE 6 — STREETS TO BE STOPPED UP
| Borough | Street to be stopped up | Extent of stopping up | Relevant site |
|---|---|---|---|
| London Borough of Wandsworth | Dormay Street | 170 sqm of public highway from a point 85m from its junction with Armoury Way to its northerly point | Dormay Street |
| London Borough of Tower Hamlets | Bekesbourne Street | West side parking bays between points 18m and 40m south of its junction with Ratcliffe Road | Bekesbourne Street |
| City of London | Access steps from Blackfriars Bridge and river embankment | West side stepped access from Blackfriars Bridge and the lower level river embankment walkway | Blackfriars Bridge Foreshore |
SCHEDULE 7 — PUBLIC RIGHTS OF WAY AND PERMISSIVE PATHS TO BE EXTINGUISHED
| Area | Route to be extinguished | Extent of extinguishment | Relevant site |
|---|---|---|---|
| London Borough of Wandsworth | Right of way | From Buckhold Road for a distance of 40m in a south-easterly direction as referenced on access plan DCO-PP-09X-KNGGP-110003 | King George’s Park |
| London Borough of Lambeth | Thames Path | A 40m section of the Thames Path fronting Camelford House north of Lack’s Dock as referenced on access plan DCO-PP-15X-ALBEF-170005 – rev 3 | Albert Embankment Foreshore |
| City of London | Thames Path / city walkway | A section of Thames Path / city walkway between Blackfriars Bridge and a point 190m west as referenced on access plan DCO-PP-17X-BLABF-190005 – rev 2 | Blackfriars Bridge Foreshore |
SCHEDULE 8 — STREETS AND RIGHTS OF WAY ETC. TO BE TEMPORARILY STOPPED UP
| Borough | Street, right of way, city walkway, or permissive path to be temporarily stopped up | Extent of temporary stopping up | Relevant Site |
|---|---|---|---|
| London Borough of Ealing | Canham Road | South side between point 70m west of its junction with Warple Way and a point 35m east of its junction with Stanley Gardens | Acton Storm Tanks |
| London Borough of Ealing | Warple Way | West side between points 50m and 70m south of Cobbold Road | Acton Storm Tanks |
| London Borough of Ealing | Stanley Gardens | West side between its junction with Canham Road and a point 30m north of that junction | Acton Storm Tanks |
| London Borough of Hammersmith and Fulham | Chancellor’s Road | Between points 65m and 95m southwest of Distillery Road Southeast side between Distillery Road and a point 25m northeast of that junction | Hammersmith Pumping Station |
| London Borough of Hammersmith and Fulham | Distillery Road | Southwest side between its junction with Chancellor’s Road and a point 90m southeast of that junction | Hammersmith Pumping Station |
| London Borough of Wandsworth | Putney High Street | East side between points 15m south and 20m north of its junction with Lower Richmond Road | Putney Embankment Foreshore |
| London Borough of Wandsworth | Lower Richmond Road | North side between points 10m west and 70m east of its junction with Embankment | Putney Embankment Foreshore |
| London Borough of Wandsworth | Embankment and Thames path | Northern footway between its junction with Lower Richmond Road and a point 70m west of that junction North east side between Glendarvon Street and Thames Place | Putney Embankment Foreshore |
| London Borough of Wandsworth | Embankment Public Slipways | Slipway adjacent to Waterman’s Green and Putney slipway (part) opposite the marine chandelery - Chas Newen’s Marine (The Boat House) | Putney Embankment Foreshore |
| Hammersmith and Fulham | Carnwath Road | South side between points 50m and 180m west of its junction with Peterborough Road and from its junction with Wandsworth Bridge Road to a point 60m west | Carnwath Road Riverside |
| Hammersmith and Fulham | Wandsworth Bridge Road | Southside between a point 10m north and 30m south of its junction with Carnwath Road | Carnwath Road Riverside |
| Hammersmith and Fulham | Thames Path | From its access adjacent to number 31 Carnwath Road to a point 145m west of Wandsworth Bridge | Carnwath Road Riverside |
| London Borough of Wandsworth | Dormay Street | East side between a point 65m north of its junction with Armoury Way to its most northern limit | Dormay Street |
| London Borough of Wandsworth | The Causeway | West side between points 160m and 190m from its junction with Dormay Street | Dormay Street |
| London Borough of Wandsworth | Neville Gill Close | From its junction with Buckhold Road to a point 40m south of that junction | King George’s Park |
| London Borough of Wandsworth | Buckhold Road | Between points 20m southwest and 20m north-east of its junction with Neville Gill Close | King George’s Park |
| London Borough of Wandsworth | Right of way | From Buckhold Road to a point 40m southeast | |
| London Borough of Wandsworth | York Road | East side between points 70m and 140m north of Plough Lane and 15m and 90m northeast of Bridges Court | Falconbrook Pumping Station |
| Royal Borough of Kensington and Chelsea | Lots Road | Southeast side between points 10m northeast and 10m southwest and points 40m and 55m southwest of its junction with Ashburnham Road | Cremorne Wharf Depot |
| Royal Borough of Kensington and Chelsea | Chelsea Embankment | North side between points 70m and 200m, and points 230m and 340m west of Chelsea Bridge Road. South side between point 180m and 340m west of Chelsea Bridge Road | Chelsea Embankment Foreshore |
| Royal Borough of Kensington and Chelsea | The Bull Ring | The area of carriageway and footway forming and known as the Bull Ring | Chelsea Embankment Foreshore |
| Royal Borough of Kensington and Chelsea | Thames Path | Between points 180m and 350m west of Chelsea Bridge Road | Chelsea Embankment Foreshore |
| London Borough of Wandsworth | Kirtling Street | Its northern loop between its western junctions with Cringle Street and its most north easterly point | Kirtling Street |
| London Borough of Wandsworth | Cringle Street | Between its eastern and western junction with Kirtling Street | Kirtling Street |
| London Borough of Wandsworth | Thames Path | Kirtling street from its western junction with Cringle Street to its most north easterly point on Kirtling Street | Kirtling Street |
| London Borough of Wandsworth | Nine Elms Lane | North side between points 40m and 130m west of its junction with Ponton Road | Heathwall Pumping Station |
| London Borough of Wandsworth | Thames Path | North side between points 40m and 130m west of its junction with Ponton Road | Heathwall Pumping Station |
| London Borough of Lambeth | Albert Embankment | West side between points 220m and 250m north of its junction with Bridge Foot | Albert Embankment Foreshore |
| London Borough of Lambeth | Thames Path | From a point north of the building Peninsula Heights to Vauxhall Bridge | Albert Embankment Foreshore |
| City of Westminster | Victoria Embankment | East side between Northumberland Avenue and a point approximately 50 metres south of Horse Guards Avenue including central reserve West side northbound offside running lane including central reserve between Northumberland Avenue and Horse Guards Avenue | Victoria Embankment Foreshore |
| City of Westminster | Thames Path | Victoria Embankment Between Northumberland Avenue and and a point approximately 50 metres south of Horse Guards Avenue | Victoria Embankment Foreshore |
| City of London | Victoria Embankment / Blackfriars Underpass including access ramps and Thames path and city walkway and pedestrian subway and stepped access from Blackfriars Bridge to Victoria Embankment | Southern side between its junction with New Bridge Street and a point 180m west of its junction with Temple Avenue East/west pedestrian subway (Thames Path) under Blackfriars Bridge and north/south pedestrian subway connecting Embankment / Thames Path with Blackfriars Station, including stepped accesses (east and west) | Blackfriars Bridge Foreshore |
| City of London | City Walkway / Riverside Walkway / Thames Path | Between points 10m and 60m to the east of Blackfriars Rail Bridge | Blackfriars Bridge Foreshore |
| City of London | New Bridge Street | From its junction with Blackfriars Underpass westbound access ramp to a point 60m north of that junction | Blackfriars Bridge Foreshore |
| London Borough of Southwark | Maguire Street | From its junction with Gainsford Street to a point 80m northeast of that junction | Shad Thames Pumping Station |
| London Borough of Southwark | Gainsford Street | Between its junction with Shad Thames and a point 25m north west of its junction with Maguire Street | Shad Thames Pumping Station |
| London Borough of Southwark | Bevington Street | From its junction with Chambers Street to a point 40m south of that junction | Chambers Wharf |
| London Borugh of Southwark | Chilton Grove | Between its junction with Croft Street and a point 50m northeast of that junction | Earl Pumping Station |
| London Borough of Southwark | Croft Street | Between points 30m and 80m southeast of its junction with Chilton Grove | Earl Pumping Station |
| London Borough of Lewisham | Chilton Grove | Between its junction with Croft Street and a point 50m north east of that junction | Earl Pumping Station |
| London Borough of Lewisham | Yeoman Street | Southwest side from its junction with Chilton Grove to a point 80m southeast of that junction | Earl Pumping Station |
| London Borough of Lewisham | Croft Street | Between points 30m and 80m southeast of its junction with Chilton Grove | Earl Pumping Station |
| London Borough of Lewisham | Deptford Church Street | Between point 30m south of Crossfield Street to a point 70m north of its junction with Berthon Street | Deptford Church Street |
| London Borough of Lewisham | Coffey Street | Between Deptford Church Street and a point 60m west | Deptford Church Street |
| London Borough of Lewisham | Crossfield Street | From its junction with Coffey Street to a point 50m northwest of that junction and between points 70m and 105m northwest of its junction with Deptford Church Street | Deptford Church Street |
| Royal Borough of Greenwich | Greenwich High Road | North side between points 40m and 60m southwest of its junction with Norman Road | Greenwich Pumping Station |
| Royal Borough of Greenwich | Norman Road | West Side between points 75m and 200m north of its junction with Greenwich High Street | Greenwich Pumping Station |
| Royal Borough of Greenwich | Unnamed pedestrian/cycle route between Norman Road and Creekside | From its junction with Norman Road to a point 100m west | Greenwich Pumping Station |
| London Borough of Tower Hamlets | Glamis Road | East side between points 5m and 30m north of its junction with Shadwell Pierhead West side between its junction with The Highway to a point 45m south of that junction | King Edward Memorial Park Foreshore |
| London Borough of Tower Hamlets | Thames Path | Permissive path through King Edward Memorial Park from the park entrance on the river front at Free Trade Wharf to a point 115m west | King Edward Memorial Park Foreshore |
| London Borough of Tower Hamlets | Bekesbourne Street | From a point 20m north of Ratcliffe Lane to a point 60m south of that junction | Bekesbourne Street |
| London Borough of Tower Hamlets | Ratcliffe Lane | From a point 10m west of Bekesbourne Street to a point 30m east of that junction | Bekesbourne Street |
| London Borough of Newham | Gay Road | South side between point 30m and 50m east of its junction with Riverside Road | Abbey Mills Pumping Station |
| London Borough of Newham | Thames Path | East side of Prescott Channel, for a distance of 90m south of Three Mills Lock | Abbey Mills Pumping Station |
SCHEDULE 9 — ACCESS TO WORKS
| Borough | Description of access | Construction or Permanent | Relevant Site |
|---|---|---|---|
| London Borough of Ealing | Access from Canham Road as labelled Ac on access plan DCO-PP-02X-ACTST-050003 Access from Canham Road as labelled Ap on access plan DCO-PP-02X-ACTST-050003 Access from Warple Way as labelled Ac on access plan DCO-PP-02X-ACTST-050003 Access from Warple Way as labelled Ap on access plan DCO-PP-02X-ACTST-050003 (existing access) | Construction Access Permanent Access Construction Access Permanent Access | Acton Storm Tanks |
| London Borough of Hammersmith and Fulham | Access from Distillery Road as labelled Ac on access plan DCO-PP-03X-HAMPS-060003 Access from Distillery Road as labelled Ap on access plan DCO-PP-03X-HAMPS-060003 Access from Chancellor’s Road as labelled Ap on access plan DCO-PP-03X-HAMPS-060003 (2 existing accesses) | Construction Access Permanent Access Permanent Access | Hammersmith Pumping Station |
| London Borough of Richmond-upon-Thames | Access from Queen Elizabeth Walk as labelled Ac on access plan DCO-PP-04X-BAREL-070003 (existing access) Access from Queen Elizabeth Walk as labelled Ap on access plan DCO-PP-04X-BAREL-070003 | Construction Access Permanent Access | Barn Elms |
| London Borough of Wandsworth | Access from Embankment as labelled Ac on access plan DCO-PP-05X-PUTEF-080003 – rev 1 Access (pedestrian) from Lower Richmond Road as labelled Ac on access plan DCO-PP-05X-PUTEF-080003 – rev 1 Access from Embankment as labelled Ac on access plan DCO-PP-05X-PUTEF-080004 (3 accesses) Access from Embankment as labelled At on access plan DCO-PP-05X-PUTEF-080004 Access from Embankment as labelled Ap on access plan DCO-PP-05X-PUTEF-080003 – rev 1 | Construction Access Construction Access Construction Access Construction Access Permanent Access | Putney Embankment Foreshore |
| Hammersmith and Fulham | Access from Carnwath Road as labelled Ac on access plan DCO-PP-06X-CARRR-090003 (3 accesses - 2 existing) Access from Carnwath Road as shown on access plan DCO-PP-06X-CARRR-090003 | Construction Access Permanent Access | Carnwath Road Riverside |
| London Borough of Wandsworth | Access from Dormay Street as labelled Ac on access plan DCO-PP-08X-DRMST-100003 Access from Dormay Street as labelled Ap on access plan DCO-PP-08X-DRMST-100003 Access from The Causeway as shown on access plan DCO-PP-08X-DRMST-100003 Access to The Causeway as labelled Ac on access plan DCO-PP-08X-DRMST-100003 | Construction Access Permanent Access Construction Access Construction Access | Dormay Street |
| London Borough of Wandsworth | Access from Neville Gill Close as shown on access plan DCO-PP-09X-KNGGP-110003 Access from Neville Gill Close as shown on access plan DCO-PP-09X-KNGGP-110003 | Construction Access Permanent Access | King George’s Park |
| London Borough of Wandsworth | Access from York Road as labelled Ac on access plan DCO-PP-10X-FALPS-120003 (2 accesses) Access from York Gardens as labelled Ap on access plan DCO-PP-10X-FALPS-120003 Access from Newcomen Road/ Lavender Road as labelled Ap on access plan DCO-PP-10X-FALPS-120003 (existing access) | Construction Access Permanent Access Permanent Access | Falconbrook Pumping Station |
| Royal Borough of Kensington and Chelsea | Access from Lots Road as labelled Ac on access plan DCO-PP-11X-CREWD-130003 (2 existing accesses) Access from Lots Road as labelled Ap on access plan DCO-PP-11X-CREWD-130003 (2 existing accesses) | Construction Access Permanent Access | Cremorne Wharf Depot |
| Royal Borough of Kensington and Chelsea | North side Accesses from Chelsea Embankment as labelled Ac on access plan DCO-PP-12X-CHEEF-140003 – rev 1 (2 accesses) Access from Chelsea Embankment as labelled Ap on access plan DCO-PP-12X-CHEEF-140003 – rev 1 South side Access from Chelsea Embankment as shown on access plan DCO-PP-12X-CHEEF-140003 – rev 1 Access from Chelsea Embankment as shown on access plan DCO-PP-12X-CHEEF-140003 – rev 1 | Construction Access Permanent Access Construction Access Permanent Access | Chelsea Embankment Foreshore |
| London Borough of Wandsworth | Access from Kirtling Street as labelled Ac on access plan DCO-PP-13X-KRTST-150003 – rev 1 (2 accesses) Access from Kirtling Street as labelled Ap on access plan DCO-PP-13X-KRTST-150003 – rev 1 Access from Cringle Street as labelled Ac on access plan DCO-PP-13X-KRTST-150003 – rev 1 (2 accesses) Access from Cringle Street as labelled Ap on access plan DCO-PP-13X-KRTST-150003 – rev 1 (2 accesses) | Construction Access Permanent Access Construction Access Permanent Access | Kirtling Street |
| London Borough of Wandsworth | Access from Nine Elms Lane as labelled Ac on access plan DCO-PP-14X-HEAPS-160003 – rev 2 (2 accesses, existing) Access from Nine Elms Lane as labelled Ap on access plan DCO-PP-14X-HEAPS-160003 – rev 2 (4 accesses, existing) | Construction Access Permanent Access | Heathwall Pumping Station |
| London Borough of Lambeth | Access from Albert Embankment as labelled Ac on access plan DCO-PP-15X-ALBEF-170005 – rev 3 (2 accesses, 1 to the south of Camelford House and 1 to the north of Camelford House, south of Tintagel House) Access from Albert Embankment as labelled Ap on access plan DCO-PP-15X-ALBEF-170005 – rev 3 (existing access) | Construction Access Permanent Access | Albert Embankment Foreshore Albert Embankment Foreshore |
| City of Westminster | Access from Victoria Embankment as shown on access plan DCO-PP-16X-VCTEF-180005 – rev 2 Access from Victoria Embankment as shown on access plan DCO-PP-16X-VCTEF-180005 – rev 2 | Construction Access Permanent Access | Victoria Embankment Foreshore |
| City of London | Access from New Bridge Street as labelled Ac on access plan DCO-PP-17X-BLABF-190005 – rev 2 Access from Victoria Embankment/Blackfriars Underpass as shown on access plan DCO-PP-17X-BLABF-190005 – rev 2 Access from Victoria Embankment/Blackfriars Underpass as labelled Ap on access plan DCO-PP-17X-BLABF-190005 – rev 2 | Construction Access Construction Access Permanent Access | Blackfriars Bridge Foreshore |
| London Borough of Southwark | Access from Maguire Street as labelled Ac on access plan DCO-PP-18X-SHTPS-200003 Access from Maguire Street as labelled Ap on access plan DCO-PP-18X-SHTPS-200003 (2 accesses - 1 existing) | Construction Access Permanent Access | Shad Thames Pumping Station |
| London Borough of Southwark | Access from Chambers Street as labelled Ac on access plan DCO-PP-19X-CHAWF-210003 (existing access) Access from Loftie Street as labelled Ap on access plan DCO-PP-19X-CHAWF-210003 (existing access) | Construction Access Permanent Access | Chambers Wharf |
| London Borough of Lewisham | Access from Yeoman Street as labelled Ac on access plan DCO-PP-21X-EARPS-220003 (2 accesses- 1 existing) Access from Chilton Grove as labelled Ac on access plan DCO-PP-21X-EARPS-220003 (existing access) Access from Croft Street as shown on access plan DCO-PP-21X-EARPS-220003 Access from Yeoman Street as labelled Ap on access plan DCO-PP-21X-EARPS-220003 (existing access) Access from Chilton Grove as labelled Ap on access plan DCO-PP-21X-EARPS-220003 (existing access) Access from Croft Street as shown on access plan DCO-PP-21X-EARPS-220003 | Construction Access Construction Access Construction Access Permanent Access Permanent Access Permanent Access | Earl Pumping Station |
| London Borough of Lewisham | Access from Coffey Street as shown on access plan DCO-PP-22X-DEPCS-230003 Access from Crossfield Street as shown on access plan DCO-PP-22X-DEPCS-230003 Access from Coffey Street as shown on access plan DCO-PP-22X-DEPCS-230003 (2 accesses) Access from Crossfield Street as shown on access plan DCO-PP-22X-DEPCS-230003 | Construction Access Construction Access Permanent Access Permanent Access | Deptford Church Street |
| Royal Borough of Greenwich | Access from Norman Road as labelled Ac on access plan DCO-PP-23X-GREPS-240003 (4 accesses - 3 existing) | Construction Access | Greenwich Pumping Station |
| Access from Greenwich High Road as labelled Ac on access plan DCO-PP-23X-GREPS-240003 (existing access) | Construction Access | ||
| Access from Norman Road as shown on access plan DCO-PP-23X-GREPS-240003 (existing access) | Permanent Access | ||
| Access from Greenwich High Road as labelled Ap on access plan DCO-PP-23X-GREPS-240003 (existing access) | Permanent Access | ||
| London Borough of Tower Hamlets | Access from Glamis Road as labelled Ac on access plan DCO-PP-24X-KEMPF-250003 – rev 1 | Construction Access | King Edward Memorial Park Foreshore |
| Access from Glamis Road as labelled Ap on access plan DCO-PP-24X-KEMPF-250003 – rev 1 | Permanent Access | ||
| London Borough of Tower Hamlets | Access from Bekesbourne Street as labelled Ac on access plan DCO-PP-25X-BEKST-260002 | Construction Access | Bekesbourne Street |
| Access from Bekesbourne Street as labelled Ap on access plan DCO-PP-25X-BEKST-260002 | Permanent Access | ||
| London Borough of Newham | Access from Gay Road as labelled Ac on access plan DCO-PP-26X-ABMPS-270004 (existing access) | Construction Access | Abbey Mills Pumping Station |
| Access from Gay Road as labelled Ap on access plan DCO-PP-26X-ABMPS-270004 (existing access) | Permanent Access | ||
| London Borough of Newham | Access from Jenkins Lane as labelled Ac on access plan DCO-PP-27X-BESTW-280002 - rev 1 (2 accesses) | Construction Access | Beckton Sewage Treatment Works |
| Access from Jenkins Lane as labelled Ap on access plan DCO-PP-27X-BESTW-280002 – rev 1 (2 accesses) | Permanent Access |
SCHEDULE 10 — TRAFFIC REGULATION
PART 1 — TEMPORARY
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.