The Network Rail (Ordsall Chord) Order 2015

Type Statutory-Instrument
Publication 2015-03-31
Last updated 2017-12-28
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (d) by reason of any act or omission of Network Rail or of any person in its employ or of its contractors or others whilst engaged upon the construction of any specified work or of a protective work,

and subject to sub-paragraph (4) Network Rail must effectively indemnify and hold harmless MSCC from and against all charges, claims, demands, expenses and liabilities arising out of any of the matters referred to in paragraphs (a), (b), (c) and (d).

  • (3) Nothing in this paragraph imposes any liability on Network Rail with respect to any losses, costs, charges, damages, expenses, claims or demand referred to in sub-paragraph (2) to the extent that they are attributable to negligence on the part of MSCC or of any person in its employ or its contractors or agents.
  • (4) The fact that any act or thing may have been done by MSCC on behalf of Network Rail does not (if it was done without negligence on the part of MSCC or any person in its employ or its contractor or agents) excuse Network Rail from any liability under the provisions of this paragraph.
  • (5) MSCC must give to Network Rail reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand must be made without the prior consent in writing of Network Rail (which must not be unreasonably withheld) which, if it notifies MSCC that it desires to do so, must have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand provided that no settlement or compromise of any such claim or demand is to be made without the consent of MSCC (which must not be unreasonably withheld). If consent is not given by Network Rail, MSCC must diligently defend such claim or demand.
39

Where under any provision of this Part of this Schedule MSCC or Network Rail (as the case may be) is entitled to a capitalised sum, it must provide such details of the formula by which the sum is calculated as may reasonably be requested by the party required to pay the sum.

40

Except as provided by this Order, nothing in this Order prejudices or derogates from the estates, rights, interests, privileges, liberties or franchises of MSCC or alters or diminishes any power, authority or jurisdiction vested in MSCC at the making of this Order.

41

Any differences arising between Network Rail and MSCC under this Part of this Schedule (other than a difference as to the meaning or construction of this Part of this Schedule) must be referred to and settled by arbitration in accordance with article 44 (arbitration).

PART 5 — FOR THE PROTECTION OF THE CANAL & RIVER TRUST

42
  • (1) The following provisions of this Part of this Schedule have effect unless otherwise agreed in writing between Network Rail and the Trust.
  • (2) In this Part of this Schedule—
  • “construction”, in relation to any specified work or protective work, includes— the execution and placing of that work; and any relaying, renewal or maintenance of that work as may be carried out during the period of 24 months from the completion of that work, and “construct” and “constructed” are construed accordingly;
  • “detriment” means any damage to the waterway or any other property of the Trust and, without limitation on the scope of that meaning, includes— any obstruction of, or interference with, or hindrance or danger to, navigation or to any use of the waterway (including towing paths); the erosion of the bed or banks of the waterway, or the impairment of the stability of any works, lands or premises forming part of the waterway; the deposit of materials or the siltation of the waterway so as to damage the waterway; the pollution of the waterway; any significant alteration in the water level of the waterway, or significant interference with the supply of water to it, or drainage of water from it; any harm to the ecology of the waterway (including any adverse impact on any site of special scientific interest comprised in the Trust’s network); and any interference with the exercise by any person of rights over the Trust’s network;
  • “the engineer” means an engineer appointed by the Trust for the purpose in question;
  • “plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction) and programmes;
  • “practical completion” means practical completion of all of the specified work notwithstanding that items which would ordinarily be considered snagging items remain outstanding, and the expression “practically complete” and “practically completed” are to be construed accordingly;
  • “protective work” means a work constructed under paragraph 47(3)(a);
  • “specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of the waterway, or may in any way affect the waterway;
  • “towing path” means the towing path forming part of the waterway;
  • “the Trust” means the Canal & River Trust;
  • “the Trust’s network” means the Trust’s network of waterways; and
  • “the waterway” means the Manchester, Bolton and Bury Canal, and includes any works, lands or premises belonging to the Trust, or under its management or control, that are held or used by the Trust in connection with that canal.
43
  • (1) Network Rail must not under the powers conferred by this Order acquire compulsorily any land of the Trust or any easement or other right over such land, or use any such land, unless such acquisition or use is with the consent of the Trust.
  • (2) Network Rail must not in the exercise of the powers conferred by this Order obstruct or interfere with pedestrian or vehicular access to the waterway unless such obstruction or interference with such access is with the consent of the Trust.
  • (3) Network Rail must not exercise the powers conferred by article 12(1) (temporary stopping up of streets) in relation to any way over land comprised in the waterway unless such exercise is with the consent of the Trust.
  • (4) Nothing in article 20 (temporary interference with river and waterway) authorises Network Rail—
  • (a) to discharge any water directly or indirectly into the waterway; or
  • (b) to carry out any works to, or make any opening in, or otherwise interfere with, the waterway (including its banks and bed),

except with the consent of the Trust and on terms that the Trust may reasonably require, and in accordance with plans approved by, and under the supervision (if given) of the engineer.

  • (5) Network Rail must not exercise any power conferred by this Order in such a way as to interfere with the supply of water to or the drainage of water from the waterway unless such exercise is with the consent of the Trust.
  • (6) Network Rail must not exercise the powers conferred by article 19 (power to survey and investigate land) and the powers conferred by article 20, or section 11(3) (powers of entry) of the 1965 Act in relation to the waterway unless such exercise is with the consent of the Trust.
  • (7) The consent of the Trust under sub-paragraphs (1) to (6) and the approval of plans under sub-paragraph (4) must not be unreasonably withheld or delayed but may be given subject to reasonable terms and conditions which in the case of article 17 (discharge of water) may include conditions—
  • (a) specifying the maximum volume of water which may be discharged in any period; and
  • (b) authorising the Trust on giving reasonable notice (except in an emergency, when the Trust may require immediate suspension) to Network Rail to require Network Rail to suspend the discharge of water or reduce the flow of water where this is necessary by reason of any operational or environmental requirement of the Trust.
44

Network Rail must not use any land or property of the Trust forming part of the waterway for the passage or siting of vehicles, plant or machinery employed in the construction of a specified work other than—

  • (a) with the consent in writing of the engineer whose consent must not be unreasonably withheld; and
  • (b) subject to compliance with such reasonable requirements as the engineer may from time to time specify—
  • (i) for the prevention of detriment; or
  • (ii) in order to avoid or reduce any inconvenience to the Trust, its officers and agents and all other persons lawfully on such land or property,

but nothing in this paragraph applies in relation to anything done in accordance with any approval given by the Trust under paragraph 47.

45

Where so required by the engineer Network Rail must to the reasonable satisfaction of the engineer fence off a specified work or a protective work or take such other steps as the engineer may require to be taken for the purpose of separating a specified work or a protective work from the waterway, whether on a temporary or permanent basis.

46
  • (1) Before the commencement of the initial construction of any part of the specified work and again following practical completion of the specified work Network Rail must bear the reasonable cost of the carrying out by a qualified engineer (“the surveyor”), to be approved by the Trust and Network Rail, of a survey (including a dip-survey to measure the depth of the waterway and a survey to measure the headroom of the existing road bridge over the waterway) (“the survey”) of so much of the waterway and of any land and works of Network Rail in existence at the date of the coming into force of this Order which may provide support for the waterway as will or may be affected by the specified works.
  • (2) For the purposes of the survey Network Rail must—
  • (a) on being given reasonable notice (except in case of emergency, when immediate access must be afforded) afford reasonable facilities to the surveyor for access to the site of the specified works and to any land and existing works of Network Rail which may provide support for the waterway as will or may be affected by the specified works; and
  • (b) supply the surveyor as soon as reasonably practicable with all such information as the surveyor may reasonably require with regard to such existing works of Network Rail and to the specified works or the method of their construction.
  • (3) The reasonable costs of the survey must include the costs of any dewatering or reduction of the water level of any part of the waterway (where reasonably required) which may be effected to facilitate the carrying out of the survey and the provisions of this Part of this Schedule apply with all necessary modifications to any such dewatering or reduction in the water level as though those measures were specified works.
  • (4) Copies of the report of the survey must be provided to both the Trust and Network Rail at no cost to the Trust.
47
  • (1) Network Rail must before commencing construction of any specified work including any temporary works supply to the Trust proper and sufficient plans of that work and such further particulars available to it as the Trust may within 14 days of the submission of the plans reasonably require for the approval of the engineer and must not commence such construction of a specified work until plans of that work have been approved in writing by the engineer or settled by arbitration.
  • (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld or delayed and must not be withheld in respect of a design which accords with the design drawings, and if within 56 days after such plans (including any other particulars reasonably required under sub-paragraph (1)) have been supplied to the Trust the engineer has not intimated disapproval of those plans and the grounds of disapproval the engineer is deemed to have approved the plans as submitted.
  • (3) When signifying approval of the plans the engineer may specify—
  • (a) any protective work (whether temporary or permanent) which in the reasonable opinion of the engineer should be carried out before the commencement of a specified work to prevent detriment; and
  • (b) such other requirements as may be reasonably necessary to prevent detriment,

and such protective works must be constructed by Network Rail or by the Trust at Network Rail’s request with all reasonable dispatch and Network Rail must not commence the construction of a specified work until the engineer has notified Network Rail that the protective works have been completed to the engineer’s reasonable satisfaction.

48

Without affecting its obligations under the provisions of this Part of this Schedule Network Rail must consult, collaborate with and respond constructively to any approach, suggestion, proposal or initiative made by the Trust on—

  • (a) the design and appearance of any specified works, including the materials to be used for their construction; and
  • (b) the environmental effects of the specified work,

and must have regard to such views as may be expressed by the Trust, to the extent that these accord with the design drawings and the requirements of the local planning authority, in response to such consultation pursuant in particular to the requirements imposed on the Trust by section 22 (general environmental and recreational duties) of the British Waterways Act 199552 and to the interest of the Trust in preserving and enhancing the environment of its waterways.

49

Network Rail must give to the engineer 56 days’ notice of its intention to commence the construction of any of the specified or protective works, or, in the case of repair carried out in an emergency, such notice as may be reasonably practicable so that, in particular, the Trust may where appropriate arrange for the publication of notices bringing those works to the attention of users of the Trust’s network.

50

Network Rail must provide and maintain at its own expense in the vicinity of the specified or protective works such temporary lighting and such signal lights for the control of navigation as the engineer may reasonably require during the construction or failure of the specified or protective works.

51
  • (1) Any specified or protective works must, when commenced, be constructed—
  • (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled in accordance with this Part of this Schedule and with any requirements made under paragraph 47(3) and paragraph 48;
  • (b) under the supervision (if given) and to the reasonable satisfaction of the engineer;
  • (c) in such manner as to cause as little detriment as is reasonably practicable; and
  • (d) in such manner as to cause as little inconvenience as is reasonably practicable to the Trust, its officers and agents and all other persons lawfully using the waterway, except to the extent that temporary obstruction has otherwise been agreed by the Trust.
  • (2) Nothing in this Order authorises Network Rail to make or maintain any permanent works in or over the waterway which will reduce the dimensions of the waterway or prevent the passage of any vessel which is at the date of this Order able to navigate along the waterway.
  • (3) Following the completion of the construction of the specified works Network Rail must restore the waterway to a condition no less satisfactory than its condition immediately prior to the commencement of those works.
52

Network Rail must not in the course of constructing a specified work or a protective work or otherwise in connection with those works do or permit anything which may result in the pollution of the waterway or the deposit of materials in it and must take such steps as the engineer may reasonably require to avoid or make good any breach of its obligations under this paragraph.

53
  • (1) Network Rail on being given reasonable notice must—
  • (a) at all times allow reasonable facilities to the engineer for access to a specified work during its construction; and
  • (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.
  • (2) The Trust on being given reasonable notice must—
  • (a) at all times afford reasonable facilities to Network Rail and its agents for access to any works carried out by the Trust under this Part of this Schedule during their construction; and
  • (b) supply Network Rail with such information as it may reasonably require with regard to such works or the method of constructing them and Network Rail must reimburse the Trust’s reasonable costs in relation to the supply of such information.
54

If at any time after the completion of a specified work or a protective work, not being a work vested in the Trust, the Trust gives notice to Network Rail informing it that the state of maintenance of the work appears to be such that the work is causing or likely to cause detriment, Network Rail must, on receipt of such notice, take such steps as may be reasonably necessary to put the work in such state of maintenance as not to cause such detriment.

55

Network Rail must repay to the Trust all fees, costs, charges and expenses reasonably incurred by the Trust—

  • (a) in constructing any protective works under paragraph 47(3)(a);
  • (b) in respect of the approval by the engineer of plans submitted by Network Rail and the supervision by the engineer of the construction or repair of a specified work and any protective works;
  • (c) in respect of the employment during the construction of the specified works or any protective works of any inspectors, watchkeepers and other persons whom it is reasonably necessary to appoint for inspecting, watching and lighting any waterway and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of the specified works or any protective works; and
  • (d) in bringing the specified works or any protective works to the notice of users of the Trust’s network.
56
  • (1) If any detriment is caused by the construction or failure of the specified works or the protective works carried out by Network Rail, Network Rail (if so required by the Trust) must make good such detriment and pay to the Trust all reasonable expenses to which the Trust may be put, and compensation for any loss which the Trust may sustain, in making good or otherwise by reason of the detriment.
  • (2) Network Rail is responsible for and must make good to the Trust all costs, charges, damages, expenses and losses not otherwise provided for in this Part of this Schedule which may be occasioned to or reasonably incurred by the Trust—
  • (a) by reason of the construction of a specified work or a protective work or the failure of such a work; or
  • (b) by reason of any act or omission of Network Rail or of any person in its employ or of its contractors or others whilst engaged upon the construction of a specified work or a protective work;

and subject to sub-paragraph (4) Network Rail must effectively indemnify and hold harmless the Trust from and against all claims and demands arising out of or in connection with any of the matters referred to in paragraphs (a) and (b).

  • (3) The fact that any act or thing may have been done by the Trust on behalf of Network Rail or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision or in accordance with any directions or awards of an arbitrator does not (if it was done without negligence on the part of the Trust or of any person in its employ or of its contractors or agents) excuse Network Rail from any liability under the provisions of this paragraph.
  • (4) The Trust must give Network Rail reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand is to be made without the prior consent of Network Rail.
57

Any difference arising between Network Rail and the Trust under this Part of this Schedule (other than a difference as to the meaning or construction of the Part of this Schedule) is to be referred to and settled by arbitration in accordance with article 44 (arbitration).

Signed

Signed by the authority of the Secretary of State

Martin Woods — Head of the Transport and Works Act Orders Unit — Department for Transport — 31st March 2015

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order authorises Network Rail Infrastructure Limited to construct and maintain a new chord railway, linking the Castlefield Junction line with the Chat Moss lines in the Ordsall area of Greater Manchester, including alterations to existing railway infrastructure. The new railway will provide a direct link between the three main stations in Manchester (Victoria, Oxford Road and Piccadilly) and will enable trains from the east of England to reach Manchester Airport without crossing the West Coast Main Line to the south of Manchester Piccadilly. The Order authorises the acquisition of land and rights in land, and the use of land, for this purpose.

Copies of the land plans, the works plans, the sections and the book of reference referred to in the Order may be inspected at the offices of the Company Secretary and Solicitor to Network Rail Infrastructure Limited at 1 Eversholt Street, London, NW1 2DN.

Footnotes

2

1992 c. 42. Section 1 was amended by the Planning Act 2008 (c.29), Schedule 2, paragraphs 51 and 52; section 5 was amended by S.I. 2012/1559

11

There are amendments to section 58 that are not relevant to this Order.

12

1923 c. 20. Section 79A was amended by section 48(1)(c) of the Coal Industry Nationalisation Act 1946 (c. 59). Section 85C was amended by virtue of section 17(2)(a) of the Interpretation Act 1978 (c. 30).

13

As amended by the Statute Law Revision Act 1892 (c. 19), Part 3 of Schedule 7 to the Justices of the Peace Act 1949 (c. 101) and section 46 of the Criminal Justice Act 1982 (c. 48).

14

As amended by the Statute Law Revision Act 1892 and Part 2 of Schedule 12 to the Transport Act 1962 (c. 46).

16

As amended by section 102 of, and Schedule 17 to, the Local Government Act 1985 (c. 51) and section 168(2) of, and Schedule 9 to, the New Roads and Street Works Act 1991 (c. 22).

17

As amended by section 42 of the Traffic Management Act 2004 (c.18).

18

1829 (10 Geo. IV.) c. xxxv.

19

1867 (30 & 31 Vict.) c. cxliv.

22

1991 c. 56. Section 106 was amended by sections 35(1) and (8) and 43(2) of, and Schedule 2 to, the Competition and Service (Utilities) Act 1992 (c. 43), sections 36(2) and 99 of the Water Act 2003 (c. 37) and paragraph 16(1) of Schedule 3 to the Flood and Water Management Act 2010 (c. 29).

24

As amended by section 4 of, and paragraph 13(2) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and S.I. 2009/1307.

27

As amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.

28

As amended by section 4 of, and paragraph 13(2) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and S.I. 2009/1307.

29

As amended by sections 62(3) and 139 of, and paragraphs 27 and 28 of Schedule 13, and Part 3 of Schedule 23, to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).

30

Section 272 was amended by paragraphs 103(1) and (2) of Schedule 17 to the Communications Act 2003 (c. 21).

32

1990 c. 43. Section 82 was amended by section 5(2) of the Noise and Statutory Nuisance Act 1993 (c. 40) and paragraph 6 of Schedule 17 to the Environment Act 1995 (c. 25).

33

Section 79(1) was amended by section 2(2) of the Noise and Statutory Nuisance Act 1993, section 120 of, and paragraph 2(a) of Schedule 17 and paragraph 89(2) of Schedule 22 to, the Environment Act 1995, sections 101(2) and 102(2) of the Clean Neighbourhoods and Environment Act 2005 (c. 16) and sections 109(2), 110(2), 111(2) and 112(2)(a) of the Public Health etc. (Scotland) Act 2008 (asp. 5).

34

1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15(3) of Schedule 15 to the Environmental Protection Act 1990 (c. 43), Schedule 24 to the Environment Act 1995 and paragraph 10 of Schedule 6 to the Building (Scotland) Act 2003 (asp. 8). Section 65 was amended by paragraph 15(4) of Schedule 15 to the Environmental Protection Act 1990 and Schedule 24 to the Environment Act 1995.

36

Section 90(2A) was inserted by section 16(1) of the Transport and Works Act 1992 (c. 42).

39

Section 58(1) was amended by section 16(3) of, and Schedule 5 to, the Compulsory Purchase (Vesting Declarations) Act 1981 (c. 66), section 4 of, and paragraph 29(1) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and S.I. 2009/1307.

41

Section 11 was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.

42

Section 12 was amended by section 56(2) of, and Part 1 of Schedule 9 to, the Courts Act 1971 (c. 23).

43

Section 13 was amended by sections 62(3), 139(4) to (9) and 146 of, and paragraphs 27 and 28 of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).

44

Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 and S.I. 2009/1307.

45

Sections 272 to 274 were amended by paragraph 103(1) and (2) of Schedule 17 to the Communications Act 2003 (c. 21).

46

Section 279(3) was amended by paragraphs 103(1) and (2), and section 280 was amended by paragraph 104, of Schedule 17 to the Communications Act 2003. Sections 280 and 282 were amended by S.I. 2009/1307.

47

The definition of “public utility undertakers” was amended by section 190(3) of, and part 1 of Schedule 27 to, the Water Act 1989 (c. 15) and section 112(4) of, and Schedule 18 to, the Electricity Act 1989 (c. 29).

50

See section 106.

51

1991 c.59. Section 23 was amended by section 120 of, and paragraph 192 of Schedule 22 to, the Environment Act 1995 (c. 25), paragraphs 25 and 32 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29) and S.I. 2013/755.

Editorial notes

53

Art. 1 in force at 21.4.2015, see art. 1

54

Art. 2 in force at 21.4.2015, see art. 1

55

Art. 3 in force at 21.4.2015, see art. 1

56

Art. 4 in force at 21.4.2015, see art. 1

57

Art. 5 in force at 21.4.2015, see art. 1

58

Art. 6 in force at 21.4.2015, see art. 1

59

Art. 7 in force at 21.4.2015, see art. 1

60

Art. 8 in force at 21.4.2015, see art. 1

61

Art. 9 in force at 21.4.2015, see art. 1

62

Art. 10 in force at 21.4.2015, see art. 1

63

Art. 11 in force at 21.4.2015, see art. 1

64

Art. 12 in force at 21.4.2015, see art. 1

65

Art. 13 in force at 21.4.2015, see art. 1

66

Art. 14 in force at 21.4.2015, see art. 1

67

Art. 15 in force at 21.4.2015, see art. 1

68

Art. 16 in force at 21.4.2015, see art. 1

69

Art. 17 in force at 21.4.2015, see art. 1

70

Art. 18 in force at 21.4.2015, see art. 1

71

Art. 19 in force at 21.4.2015, see art. 1

72

Art. 20 in force at 21.4.2015, see art. 1

73

Art. 21 in force at 21.4.2015, see art. 1

74

Art. 22 in force at 21.4.2015, see art. 1

75

Art. 23 in force at 21.4.2015, see art. 1

76

Art. 24 in force at 21.4.2015, see art. 1

77

Art. 25 in force at 21.4.2015, see art. 1

78

Art. 26 in force at 21.4.2015, see art. 1

79

Art. 27 in force at 21.4.2015, see art. 1

80

Art. 28 in force at 21.4.2015, see art. 1

81

Art. 29 in force at 21.4.2015, see art. 1

82

Art. 30 in force at 21.4.2015, see art. 1

83

Art. 31 in force at 21.4.2015, see art. 1

84

Art. 32 in force at 21.4.2015, see art. 1

85

Art. 33 in force at 21.4.2015, see art. 1

86

Art. 34 in force at 21.4.2015, see art. 1

87

Art. 35 in force at 21.4.2015, see art. 1

88

Art. 36 in force at 21.4.2015, see art. 1

89

Art. 37 in force at 21.4.2015, see art. 1

90

Art. 38 in force at 21.4.2015, see art. 1

91

Art. 39 in force at 21.4.2015, see art. 1

92

Art. 40 in force at 21.4.2015, see art. 1

93

Art. 41 in force at 21.4.2015, see art. 1

94

Art. 42 in force at 21.4.2015, see art. 1

95

Art. 43 in force at 21.4.2015, see art. 1

96

Art. 44 in force at 21.4.2015, see art. 1

97

Sch. 9 para. 1 in force at 21.4.2015, see art. 1

98

Sch. 9 para. 2 in force at 21.4.2015, see art. 1

99

Sch. 9 para. 3 in force at 21.4.2015, see art. 1

100

Sch. 9 para. 4 in force at 21.4.2015, see art. 1

101

Sch. 9 para. 5 in force at 21.4.2015, see art. 1

102

Sch. 9 para. 6 in force at 21.4.2015, see art. 1

103

Sch. 9 para. 7 in force at 21.4.2015, see art. 1

104

Sch. 9 para. 8 in force at 21.4.2015, see art. 1

105

Sch. 9 para. 9 in force at 21.4.2015, see art. 1

106

Sch. 11 para. 1 in force at 21.4.2015, see art. 1

107

Sch. 11 para. 2 in force at 21.4.2015, see art. 1

108

Sch. 12 para. 1 in force at 21.4.2015, see art. 1

109

Sch. 12 para. 2 in force at 21.4.2015, see art. 1

110

Sch. 12 para. 3 in force at 21.4.2015, see art. 1

111

Sch. 12 para. 4 in force at 21.4.2015, see art. 1

112

Sch. 12 para. 5 in force at 21.4.2015, see art. 1

113

Sch. 12 para. 6 in force at 21.4.2015, see art. 1

114

Sch. 12 para. 7 in force at 21.4.2015, see art. 1

115

Sch. 12 para. 8 in force at 21.4.2015, see art. 1

116

Sch. 12 para. 9 in force at 21.4.2015, see art. 1

117

Sch. 12 para. 10 in force at 21.4.2015, see art. 1

118

Sch. 12 para. 11 in force at 21.4.2015, see art. 1

119

Sch. 12 para. 12 in force at 21.4.2015, see art. 1

120

Sch. 12 para. 13 in force at 21.4.2015, see art. 1

121

Sch. 12 para. 14 in force at 21.4.2015, see art. 1

122

Sch. 12 para. 15 in force at 21.4.2015, see art. 1

123

Sch. 12 para. 16 in force at 21.4.2015, see art. 1

124

Sch. 12 para. 17 in force at 21.4.2015, see art. 1

125

Sch. 12 para. 18 in force at 21.4.2015, see art. 1

126

Sch. 12 para. 19 in force at 21.4.2015, see art. 1

127

Sch. 12 para. 20 in force at 21.4.2015, see art. 1

128

Sch. 12 para. 21 in force at 21.4.2015, see art. 1

129

Sch. 12 para. 22 in force at 21.4.2015, see art. 1

130

Sch. 12 para. 23 in force at 21.4.2015, see art. 1

131

Sch. 12 para. 24 in force at 21.4.2015, see art. 1

132

Sch. 12 para. 25 in force at 21.4.2015, see art. 1

133

Sch. 12 para. 26 in force at 21.4.2015, see art. 1

134

Sch. 12 para. 27 in force at 21.4.2015, see art. 1

135

Sch. 12 para. 28 in force at 21.4.2015, see art. 1

136

Sch. 12 para. 29 in force at 21.4.2015, see art. 1

137

Sch. 12 para. 30 in force at 21.4.2015, see art. 1

138

Sch. 12 para. 31 in force at 21.4.2015, see art. 1

139

Sch. 12 para. 32 in force at 21.4.2015, see art. 1

140

Sch. 12 para. 33 in force at 21.4.2015, see art. 1

141

Sch. 12 para. 34 in force at 21.4.2015, see art. 1

142

Sch. 12 para. 35 in force at 21.4.2015, see art. 1

143

Sch. 12 para. 36 in force at 21.4.2015, see art. 1

144

Sch. 12 para. 37 in force at 21.4.2015, see art. 1

145

Sch. 12 para. 38 in force at 21.4.2015, see art. 1

146

Sch. 12 para. 39 in force at 21.4.2015, see art. 1

147

Sch. 12 para. 40 in force at 21.4.2015, see art. 1

148

Sch. 12 para. 41 in force at 21.4.2015, see art. 1

149

Sch. 12 para. 42 in force at 21.4.2015, see art. 1

150

Sch. 12 para. 43 in force at 21.4.2015, see art. 1

151

Sch. 12 para. 44 in force at 21.4.2015, see art. 1

152

Sch. 12 para. 45 in force at 21.4.2015, see art. 1

153

Sch. 12 para. 46 in force at 21.4.2015, see art. 1

154

Sch. 12 para. 47 in force at 21.4.2015, see art. 1

155

Sch. 12 para. 48 in force at 21.4.2015, see art. 1

156

Sch. 12 para. 49 in force at 21.4.2015, see art. 1

157

Sch. 12 para. 50 in force at 21.4.2015, see art. 1

158

Sch. 12 para. 51 in force at 21.4.2015, see art. 1

159

Sch. 12 para. 52 in force at 21.4.2015, see art. 1

160

Sch. 12 para. 53 in force at 21.4.2015, see art. 1

161

Sch. 12 para. 54 in force at 21.4.2015, see art. 1

162

Sch. 12 para. 55 in force at 21.4.2015, see art. 1

163

Sch. 12 para. 56 in force at 21.4.2015, see art. 1

164

Sch. 12 para. 57 in force at 21.4.2015, see art. 1

165

Sch. 1 in force at 21.4.2015, see art. 1

166

Sch. 2 in force at 21.4.2015, see art. 1

167

Sch. 3 in force at 21.4.2015, see art. 1

168

Sch. 4 in force at 21.4.2015, see art. 1

169

Sch. 5 in force at 21.4.2015, see art. 1

170

Sch. 6 in force at 21.4.2015, see art. 1

171

Sch. 7 in force at 21.4.2015, see art. 1

172

Sch. 8 in force at 21.4.2015, see art. 1

173

Sch. 10 in force at 21.4.2015, see art. 1

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.