The York Potash Harbour Facilities Order 2016
- (4) When signifying approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation, de-commissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works are to be carried out at the expense of the undertaker in either case without unnecessary delay and the undertaker must not commence the construction of the specified works until the engineer has notified the undertaker that the protective works have been completed to the engineer’s reasonable satisfaction.
6
- (1) Any specified work and any protective works to be constructed by virtue of paragraph 5(4) must, when commenced, be constructed—
- (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 5;
- (b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
- (c) in such manner as to cause as little damage as is possible to railway property; and
- (d) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic on it and the use by passengers of railway property.
- (2) If any damage to railway property or any such interference or obstruction is caused by the carrying out of, or in consequence of the construction of a specified work, the undertaker must, regardless of any such approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
- (3) Nothing in this Schedule imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents or any liability on Network Rail with respect of any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.
7
The undertaker must—
- (a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
- (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.
8
Network Rail must at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.
9
- (1) If any permanent or temporary alterations or additions to railway property, are reasonably necessary in consequence of the construction of a specified work, or during a period of 24 months after the completion of that work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations and additions may be carried out by Network Rail and if Network Rail gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
- (2) If during the construction of a specified work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work is to be constructed, Network Rail must assume construction of that part of the specified work and the undertaker must, regardless of any such approval of a specified work under paragraph 5(3), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work.
- (3) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 10(a), provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.
- (4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving is to be set off against any sum payable by the undertaker to Network Rail under this paragraph.
10
The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—
- (a) in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 5(3) or in constructing any protective works under the provisions of paragraph 5(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the approval by the engineer of plans submitted by the undertaker and the supervision by him of the construction of a specified work;
- (c) in respect of the employment or procurement of the services of any inspectors, signallers, watchkeepers and other persons whom it is reasonably necessary to appoint for inspecting, signalling, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;
- (d) in respect of any special traffic working resulting from any speed restrictions which may in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution of diversion of services which may be reasonably necessary for the same reason; and
- (e) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction or failure of a specified work.
11
- (1) In this paragraph—
- “EMI” means, subject to sub-paragraph (2), electromagnetic interference with Network Rail apparatus generated by the operation of the authorised development where such interference is of a level which adversely affects the safe operation of Network Rail’s apparatus; and
- “Network Rail’s apparatus” means any lines, circuits, wires, apparatus or equipment (whether or not modified or installed as part of the authorised works) which are owned or used by Network Rail for the purpose of transmitting or receiving electrical energy or of radio, telegraphic, telephonic, electric, electronic or other like means of signalling or other communications.
- (2) This paragraph applies to EMI only to the extent that such EMI is not attributable to any change to Network Rail’s apparatus carried out after approval of plans under paragraph 5(1) for the relevant part of the authorised works giving rise to EMI (unless the undertaker has been given notice in writing before the approval of those plans of the intention to make such change).
- (3) Subject to sub-paragraph (5), the undertaker must in the design and construction of the authorised works take all measures necessary to prevent EMI and must establish with Network Rail (both parties acting reasonably) appropriate arrangements to verify their effectiveness.
- (4) In order to facilitate the undertaker’s compliance with sub-paragraph (3)—
- (a) the undertaker must consult with Network Rail as early as reasonably practicable to identify all Network Rail’s apparatus which may be at risk of EMI, and must continue to consult with Network Rail (both before and after formal submission of plans under paragraph 5(1)) in order to identify all potential causes of EMI and the measures required to eliminate them;
- (b) Network Rail must make available to the undertaker all information in the possession of Network Rail reasonably requested by the undertaker in respect of Network Rail’s apparatus identified under sub-paragraph (a); and
- (c) Network Rail must allow the undertaker reasonable facilities for the inspection of Network Rail’s apparatus identified under sub-paragraph (a).
- (5) In any case where it is established that EMI can only reasonably be prevented by modifications to Network Rail’s apparatus, Network Rail must not withhold its consent unreasonably to modifications of Network Rail’s apparatus, but the means of prevention and the method of their execution must be selected in the reasonable discretion of Network Rail, and in relation to such modifications paragraph 5(1) has effect subject to this sub-paragraph.
- (6) If at any time prior to the completion of the authorised development and regardless of any measures adopted under sub-paragraph (3), the testing or commissioning of the authorised works causes EMI then the undertaker must immediately upon receipt of notification by Network Rail of such EMI either in writing or communicated orally (such oral communication to be confirmed in writing as soon as reasonably practicable after it has been issued) cease to use (or procure the cessation of use of) the undertaker’s apparatus causing such EMI until all measures necessary have been taken to remedy such EMI by way of modification to the source of such EMI or (in the circumstances, and subject to the consent, specified in sub-paragraph (5)) to Network Rail’s apparatus.
- (7) In the event of EMI having occurred—
- (a) the undertaker must afford reasonable facilities to Network Rail for access to the undertaker’s apparatus in the investigation of such EMI;
- (b) Network Rail must afford reasonable facilities to the undertaker for access to Network Rail’s apparatus in the investigation of such EMI; and
- (c) Network Rail must make available to the undertaker any additional material information in its possession reasonably requested by the undertaker in respect of Network Rail’s apparatus or such EMI.
- (8) Where Network Rail approves modifications to Network Rail’s apparatus under sub-paragraphs (5) or (6)—
- (a) Network Rail must allow the undertaker reasonable facilities for the inspection of the relevant part of Network Rail’s apparatus; and
- (b) any modifications to Network Rail’s apparatus approved under those sub-paragraphs must be carried out and completed by the undertaker in accordance with paragraph 6.
- (9) To the extent that it would not otherwise do so, the indemnity in paragraph 15(1) applies to the costs and expenses reasonably incurred or losses suffered by Network Rail through the implementation of the provisions of this paragraph (including costs incurred in connection with the consideration of proposals, approval of plans, supervision and inspection of works and facilitating access to Network Rail’s apparatus) or in consequence of any EMI to which sub-paragraph (6) applies.
- (10) For the purpose of paragraph 10(a) any modifications to Network Rail’s apparatus under this paragraph is to be deemed to be protective works referred to in that paragraph.
- (11) In relation to any dispute arising under this paragraph the reference in article 40 (arbitration) to the Institution of Civil Engineers is to be read as a reference to the Institution of Electrical Engineers.
12
If at any time after the completion of a specified work, not being a work vested in Network Rail, Network Rail gives notice to the undertaker informing it that the state of maintenance of any part of the specified work appears to be such as adversely affects the operation of railway property, the undertaker must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.
13
The undertaker must not provide any illumination or illuminated sign or signal on or in connection with a specified work in the vicinity of any railway belonging to Network Rail unless it must have first consulted Network Rail and it must comply with Network Rail’s reasonable requirements for preventing confusion between such illumination or illuminated sign or signal and any railway signal or other light used for controlling, directing or securing the safety of traffic on the railway.
14
Any additional expenses which Network Rail may reasonably incur in altering, reconstructing or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work must, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction or maintenance has been given to the undertaker, be repaid by the undertaker to Network Rail.
15
- (1) The undertaker must pay to Network Rail all reasonable costs, charges, damages and expenses not otherwise provided for in this Schedule which may he occasioned to or reasonably incurred by Network Rail—
- (a) by reason of the construction or maintenance of a specified work or the failure of such a work; or
- (b) by reason of any act or omission of the undertaker or of any person in its employ or of its contractors or others whilst engaged upon a specified work,
and the undertaker must indemnify and keep indemnified Network Rail from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission: and the fact that any act or thing may have been done by Network Rail on behalf of the undertaker or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under his supervision does not (if it was done without negligence on the part of Network Rail or of any person in its employ or of its contractors or agents) excuse the undertaker from any liability under the provisions of this sub-paragraph.
- (2) Network Rail must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of such a claim or demand is to be made without the prior consent of the undertaker.
- (3) The sums payable by the undertaker under sub-paragraph (1) include a sum equivalent to the relevant costs.
- (4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail must promptly pay to each train operator the amount of any sums which Network Rail receives under sub-paragraph (3) which relates to the relevant costs of that train operator.
- (5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs is, in the event of default, enforceable directly by any train operator concerned to the extent that such sums are payable to that operator under sub-paragraph (4).
- (6) In this paragraph—
- “the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in subparagraph (1); and
- “train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 (licences) of the Railways Act 1993.
16
Network Rail must, on receipt of a request from the undertaker, from time to time provide the undertaker free of charge with written estimates of the costs, charges, expenses and other liabilities for which the undertaker is or will become liable under this Schedule (including the amount of the relevant costs mentioned in paragraph 15) and with such information as may reasonably enable the undertaker to assess the reasonableness of any such estimate or claim made or to be made under this Schedule (including any claim relating to those relevant costs).
17
In the assessment of any sums payable to Network Rail under this Schedule no account is to be taken of any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the undertaker under this Schedule or increasing the sums so payable.
18
The undertaker and Network Rail may, subject in the case of Network Rail to compliance with the terms of its network licence, enter into, and carry into effect, agreements for the transfer to the undertaker of—
- (a) any railway property shown on the works plans and land plans and described in the book of reference;
- (b) any lands, works or other property held in connection with any such railway property; and
- (c) any rights and obligations (whether or not statutory) of Network Rail relating to any railway property or any lands, works or other property referred to in this paragraph.
19
Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part 1 of the Railways Act 1993.
20
The undertaker must give written notice to Network Rail if any application is proposed to be made by the undertaker for the Secretary of State’s consent, under article 8 (consent to transfer benefit of Order) and any such notice must be given no later than 28 days before any such application is made and must describe or give (as appropriate)—
- (a) the nature of the application to be made;
- (b) the extent of the geographical area to which the application relates; and
- (c) the name and address of the person acting for the Secretary of State to whom the application is to be made.
21
The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 38 (certification of plans etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in the form of a computer disc with read only memory.
SCHEDULE 8 — FOR THE PROTECTION OF NATIONAL GRID ELECTRICITY
Application
1
For the protection of National Grid referred to in this Schedule the following provisions, unless otherwise agreed between the undertaker and National Grid, have effect.
Interpretation
2
In this Schedule—
- “alternative apparatus” means appropriate alternative apparatus to the satisfaction of National Grid to enable National Grid to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means any electric lines or electrical plant as defined in the Electricity Act 198937, belonging to or maintained by National Grid, together with any replacement apparatus and such other apparatus constructed under the powers conferred by this Order that becomes operational apparatus of National Grid or any of its entities for the purposes of transmission, distribution or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
- “authorised works” has the same meaning as is given to the term “authorised development” in article 2 (interpretation) and for the purposes of this Schedule includes the use and maintenance of the authorised works;
- “functions” includes powers and duties;
- “in”, in a context referring to apparatus in land, includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of the undertaker including construct, use, repair, alter, inspect, renew or remove the apparatus;
- “National Grid” means National Grid Electricity Transmission Plc (company number 2366977), registered at 1-3 Strand, London WC2N 5EH) being a licence holder within the meaning of Part 1 of the Electricity Act 1989; and
- “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed.
3
Except for paragraphs 7 (retained apparatus: protection) and 8 (expenses) which apply in respect of the exercise of all or any powers under this Order affecting the rights and apparatus of National Grid, the provisions of this Schedule do not apply to apparatus in respect of which the relations between the undertaker and National Grid are regulated by the provisions of Part 3 of the 1991 Act.
Acquisition of land
4
- (1) Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference, the undertaker must not acquire any land interest or apparatus or override any easement or other interest of National Grid otherwise than by agreement.
- (2) As a condition of agreement between the parties in sub-paragraph (1), prior to the carrying out of any part of the authorised works (or within such other timeframe as may be agreed between the undertaker and National Grid) that are subject to the requirements of this Schedule that would cause any conflict with or breach the terms of any easement or other legal or land interest of National Grid or affects the provisions of any enactment or agreement regulating the relations between the undertaker and National Grid in respect of any apparatus laid or erected in land belonging to or secured by the undertaker, the undertaker must as National Grid reasonably requires enter into such deeds of consent, crossing agreements, variations to existing deeds of easements, agreements or such other legal interests in favour of National Grid or grant such new deeds of grant (upon such terms and conditions as may be agreed between the undertaker and National Grid acting reasonably and which must be no less favourable on the whole to National Grid unless otherwise agreed by National Grid) in order to verify, amend or replace the existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the other terms of this Schedule; and it is the responsibility of the undertaker to procure or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised works.
- (3) Where there is any inconsistency or duplication between the provisions set out in this Schedule relating to the relocation or removal of apparatus (including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by National Grid or other enactments relied upon by National Grid as of right or other use in relation to the apparatus, then the provisions in this Schedule prevail.
Removal of apparatus
5
- (1) If, in the exercise of the agreement reached in accordance with paragraph 4 or in any other authorised manner, the undertaker acquires any interest in any land in which any apparatus is placed, that apparatus must not be removed under this Schedule and any right of National Grid to maintain that apparatus in that land must not be extinguished until alternative apparatus has been constructed, and is in operation to the reasonable satisfaction of the National Grid in accordance with sub-paragraphs (2) to (5).
- (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, it must give to National Grid 56 days’ advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order National Grid reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to National Grid to its satisfaction (taking into account paragraph 8(1)) the necessary facilities and rights—
- (a) for the construction of alternative apparatus in other land of or land secured by the undertaker; and
- (b) subsequently for the maintenance of that apparatus.
- (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of or land secured by the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, National Grid must, on receipt of a written notice to that effect from the undertaker, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed except that this obligation does not extend to the requirement for National Grid to use its compulsory purchase powers to this end unless it elects to so do.
- (4) Any alternative apparatus to be constructed in land of or land secured by the undertaker under this Schedule must be constructed in such manner and in such line or situation as may be agreed between the undertaker and National Grid.
- (5) National Grid must, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to National Grid of any such facilities and rights as are referred to in sub-paragraphs (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the promoter to be removed under the provisions of this Schedule.
Facilities and rights for alternative apparatus
6
- (1) Where, in accordance with the provisions of this Schedule, the undertaker affords to or secures for National Grid facilities and rights in land for the construction, use, maintenance and protection of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between National Grid and the undertaker and must be no less favourable on the whole to National Grid than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless otherwise agreed by National Grid.
- (2) If the facilities and rights to be afforded by the undertaker and agreed with National Grid under sub-paragraph (1) in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to National Grid than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, then the matter must be referred to arbitration in accordance with paragraph 13 (arbitration), and the arbitrator must make such provision for the payment of compensation by the undertaker to National Grid as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
Retained apparatus: protection
7
- (1) Not less than 56 days before the commencement of any authorised works that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 5(2) or otherwise, the undertaker must submit to National Grid a plan of the works to be executed and seek from National Grid details of the underground extent of their electricity tower foundations if relevant.
- (2) In relation to works which will or may be situated on, over, under or within—
- (a) 15 metres measured in any direction of any apparatus; or
- (b) involve embankment works within 15 metres of any apparatus,
the plan to be submitted to National Grid under sub-paragraph (1) must include a method statement and describe—
- (i) the exact position of the works;
- (ii) the level at which these are proposed to be constructed or renewed;
- (iii) the manner of their construction or renewal including details of excavation, positioning of plant;
- (iv) the position of all apparatus;
- (v) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus;
- (vi) any intended maintenance regimes; and
- (vii) an assessment of risks of rise of earth issues.
- (3) In relation to any works which will or may be situated on, over, under or within 10 metres of any part of the foundations of an electricity tower or between any two or more electricity towers, the plan to be submitted under sub-paragraph (1) must, in addition to the matters set out in sub-paragraph (2), include a method statement describing—
- (a) details of any cable trench design including route, dimensions, clearance to pylon foundations;
- (b) demonstration that pylon foundations will not be affected prior to, during and post construction;
- (c) details of load bearing capacities of trenches;
- (d) details of cable installation methodology including access arrangements, jointing bays and backfill methodology;
- (e) a written management plan for high voltage hazard during construction and on-going maintenance of the cable route;
- (f) written details of the operations and maintenance regime for the cable, including frequency and method of access;
- (g) assessment of earth rise potential if reasonably required by the undertaker’s engineers; and
- (h) evidence that trench bearing capacity is to be designed to 26 tonnes to take the weight of overhead line construction traffic.
- (4) The undertaker must not commence any works to which sub-paragraphs (2) or (3) apply until National Grid has given written approval of the plan so submitted.
- (5) Any approval of National Grid required under sub-paragraphs (2) or (3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs (6) or 8); and
- (b) must not be unreasonably withheld or delayed.
- (6) In relation to any work to which sub-paragraphs (2) or (3) apply, National Grid may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any apparatus.
- (7) Works to which this paragraph applies must only be executed in accordance with the plan, submitted under sub-paragraph (1) or as relevant sub-paragraph (6), as approved or as amended from time to time by agreement between National Grid and the undertaker and in accordance with such reasonable requirements as may be made in accordance with sub-paragraphs (6) or (8) by National Grid for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and National Grid is entitled to watch and inspect the execution of those works.
- (8) Where National Grid requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved under this paragraph, must be carried out to National Grid’s satisfaction prior to the commencement of any authorised works (or any relevant part of the authorised works) for which protective works are required and National Grid must give 56 days’ notice of such works from the date of submission of a plan under this paragraph (except in an emergency).
- (9) If National Grid in accordance with sub-paragraph (6) or (8) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, sub-paragraphs (1) to (3) and (6) to (8) apply as if the removal of the apparatus had been required by the undertaker under paragraph 5(2).
- (10) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the authorised works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (11) The undertaker is not required to comply with sub-paragraph (1) where it needs to carry out emergency works as defined in the 1991 Act but in that case it must give to National Grid notice as soon as is reasonably practicable and a plan of those works and must—
- (a) comply with sub-paragraphs (6), (7) and (8) in so far as is reasonably practicable in the circumstances; and
- (b) comply with sub-paragraph (12) at all times.
- (12) At all times when carrying out any works authorised under the Order, the undertaker must comply with National Grid’s policies for development near overhead lines EN43-8 and HSE’s guidance note 6 “Avoidance of Danger from Overhead Lines”.
Expenses
8
- (1) Subject to the following provisions of this paragraph, the undertaker must pay to National Grid on demand all charges, costs and expenses reasonably anticipated or incurred by National Grid in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the execution of any authorised works as are referred to in this Schedule including without limitation—
- (a) any costs reasonably incurred by or compensation properly paid by National Grid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation all costs incurred by National Grid as a consequence of National Grid using its own compulsory purchase powers (with the agreement of the undertaker) to acquire any necessary rights under paragraph 7(3);
- (b) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
- (c) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (d) the approval of plans;
- (e) the carrying out of protective works, plus a capitalised sum to cover any additional costs to be incurred in maintaining and renewing permanent protective works; and
- (f) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Schedule.
- (2) The value of any apparatus removed under the provisions of this Schedule and which is not re-used as part of the alternative apparatus must be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
- (3) If in accordance with the provisions of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 40 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to National Grid by virtue of sub-paragraph (1) is to be reduced by the amount of that excess except where it is not possible in the circumstances to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs must be borne by the undertaker.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to National Grid in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on National Grid any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
Indemnity
9
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Schedule or in consequence of the construction, use, maintenance or failure of any of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of National Grid, or there is any interruption in any service provided, or in the supply of any goods, by National Grid, or National Grid becomes liable to pay any amount to any third party, the undertaker must—
- (a) bear and pay on demand the cost reasonably incurred by National Grid in making good such damage or restoring the supply; and
- (b) indemnify National Grid for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from National Grid, by reason or in consequence of any such damage or interruption or National Grid becoming liable to any third party other than arising from any default of National Grid.
- (2) The fact that any act or thing may have been done by National Grid on behalf of the undertaker or in accordance with a plan approved by National Grid or in accordance with any requirement of National Grid or under its supervision does not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of sub-paragraph (1) except where the undertaker fails to carry out and execute the works properly with due care and attention and in a skilful and professional manner or in a manner that does not accord with the approved plan.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of National Grid, its officers, servants, contractors or agents; and
- (b) any authorised works or any other works authorised by this Schedule carried out by National Grid as an assignee, transferee or lessee of the undertaker and with the benefit of the provisions of this Order under section 156 of the 2008 Act subject to the proviso that once such works become apparatus, any authorised works yet to be executed and not falling within this sub-paragraph are subject to the full terms of this Schedule including this sub-paragraph.
- (4) National Grid must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise is to be made without first consulting the undertaker and considering their representations.
Ground subsidence monitoring scheme in respect of National Grid’s apparatus
10
- (1) Any authorised works within 100 metres of any apparatus or alternative apparatus capable of interfering with or risking damage to National Grid’s apparatus must not commence until a scheme for monitoring ground subsidence (referred to in this paragraph as “the monitoring scheme”) has been submitted to and approved by National Grid, such approval not to be unreasonably withheld or delayed.
- (2) The ground subsidence monitoring scheme described in sub-paragraph (1) must set out—
- (a) the apparatus which is to be subject to such monitoring;
- (b) the extent of land to be monitored;
- (c) the manner in which ground levels are to be monitored;
- (d) the timescales of any monitoring activities; and
- (e) the extent of ground subsidence which, if exceeded, would require the promoter to submit for National Grid’s approval a ground subsidence mitigation scheme in respect of such subsidence in accordance with sub-paragraph (3).
- (3) The monitoring scheme required by sub-paragraphs (1) and (2) must be submitted at least 56 days prior to the commencement of any works authorised by this Order or comprised within the authorised development to which sub-paragraph (1) applies. Any requirements of National Grid must be notified within 28 days of receipt of the monitoring scheme. Thereafter the monitoring scheme must be implemented as approved, unless otherwise agreed in writing with National Grid.
- (4) As soon as reasonably practicable after any ground subsidence identified by the monitoring activities set out in the monitoring scheme has exceeded the level described in sub-paragraph (2)(e), a scheme setting out necessary mitigation measures (if any) for such ground subsidence (referred to in this paragraph as a “mitigation scheme”) must be submitted to National Grid for approval, such approval not to be unreasonably withheld or delayed; and any mitigation scheme must be implemented as approved, unless otherwise agreed in writing with National Grid save that National Grid retains the right to carry out any further necessary protective works for the safeguarding of their apparatus and can recover any such costs in line with paragraph 8 (expenses).
- (5) If the monitoring scheme or mitigation scheme would conflict with any aspect of any ground subsidence monitoring scheme or ground subsidence mitigation scheme approved by the local planning authority under Schedule 2 (requirements) the undertaker may submit a revised monitoring scheme or mitigation scheme to National Grid for its approval, such approval not to be unreasonably withheld or delayed; and the revised monitoring scheme or mitigation scheme must be implemented as approved, unless otherwise agreed in writing with National Grid.
Enactments and agreements
11
Except to the extent provided for to the contrary elsewhere in this Schedule or by agreement in writing between the undertaker and National Grid, nothing in this Schedule affects the provisions of any enactment or agreement regulating the relations between National Grid and the undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
12
- (1) Where in consequence of the proposed construction of any of the authorised development, National Grid or the undertaker requires the removal of apparatus under paragraph 5(2) or National Grid makes requirements for the protection or alteration of apparatus under paragraph 7, the undertaker must use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of National Grid’s undertaking and National Grid must use its reasonable endeavours to co-operate with the undertaker for that purpose.
- (2) For the avoidance of doubt whenever National Grid’s consent, agreement or approval to is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.
Access
13
If in consequence of the agreement reached in accordance with paragraph 4(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable National Grid to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
14
Except for differences or disputes arising under paragraphs 5(2), 5(4), 6(1), 7 and 9(5) any difference or dispute arising between National Grid and the undertaker under this Schedule must, unless otherwise agreed in writing between National Grid and the undertaker, be determined by arbitration in accordance with article 40 (arbitration).
Approval of Requirements
15
The undertaker must—
- (a) not without the prior approval of National Grid (such approval not to be unreasonably withheld or delayed) submit nor permit the submission of any plans, details, schemes, reports, arrangements, measures or programmes to the local planning authority under any requirement in Schedule 2 (requirements) that relate in whole or in part to any matter that affects or may affect National Grid’s apparatus including any alternative apparatus and/or in respect of any protective works required in connection with the undertaker’s apparatus under the terms of these protective provisions;
- (b) provide National Grid with copies of such plans, details, schemes, reports, arrangements, measures or programmes prior to submission to the local planning authority and take into account and incorporate any reasonable comments of National Grid; and
- (c) keep National Grid informed of the details of all material discussions and negotiations with the local planning authority relating to such plans, details, schemes, reports, arrangements, measures or programmes and give National Grid reasonable prior written notice of any meetings with the local planning authority relating to such matters and not object to National Grid and its consultants attending those meetings.
SCHEDULE 9 — FOR THE PROTECTION OF THE PIPELINE CORRIDOR AND PROTECTED CROSSINGS
Benefit of protective provisions
1
- (1) The following provisions of this Schedule have effect for the benefit of any owner of the protected land and any owner or operator of a pipeline within the pipeline corridor, unless otherwise agreed between the undertaker and the said owner or operator.
- (2) The provisions contained in paragraph 25 do not apply to the interests of Northumbrian Water Limited unless otherwise agreed between the undertaker and Northumbrian Water Limited.
Interpretation
2
In this Schedule—
- “access roads” means the access roads within the Order limits giving access to pipelines or protected crossings;
- “affected assets” means—underground pipelines where relevant works are to be carried out within the easement widths relating to that apparatus;apparatus on or above ground which would be physically affected by the relevant works;protected crossings where relevant works are to be carried out within 25 metres of the protected crossing concerned; andin relation to the exercise of an identified power, any apparatus in the protected land which would be affected by the exercise of that power.
- “apparatus” means pipelines and cables and includes—any structure existing at the time when a particular action is to be taken under this Schedule in which apparatus is or is to be lodged or which will give access to apparatus;any cathodic protection, coating or special wrapping of the apparatus; andall ancillary apparatus properly appurtenant to the pipelines, that would be treated as being associated with a pipe or systems of pipes under section 65(2) of the Pipe-Lines Act 196238), as if the pipelines were a “pipe-line” in section 65(1) of that Act;
- “cats easement” means the easement width of the cats pipeline;
- “cats pipeline” means the pipeline identified as “Gas BP Cats” on the conveyor route plans;
- “cats pipeline critical construction activities” means the following authorised works—excavation works within the cats easement;piling within 10 metres of the cats pipeline;backfilling and compaction work within the cats easement;erection of crash mats above the cats pipeline; andall lifting above the cats pipeline.
- “construction access plan” means a plan identifying how access will be maintained to pipelines, the protected crossings and the Wilton Complex during the proposed construction or maintenance work including—any restrictions on general access by owners of the protected land and operators of the pipelines, including the timing of restrictions;any alternative accesses or routes of access that may be available to the undertaker using the access roads;details of how the needs and requirements of owners of the protected land and operators of the pipelines (including their needs and requirements in relation to any major works that they have notified to the other operators of the protected land as at the date when the plan is published) have been taken into account in preparing the plan;details of how uninterrupted and unimpeded emergency access with or without vehicles will be provided at all times for owners of the protected land and operators of the pipelines; anddetails of how reasonable access with or without vehicles will be retained or an alternative provided for owners of the protected land and operators of the pipelines to inspect, repair, replace and maintain and ensure the continuing safety and operation or viability of the pipelines and protected crossings;
- “construction or maintenance works” means any works to construct, maintain, or decommission the authorised development;
- “damage” includes all damage including in relation to a pipeline leakage and the weakening of the mechanical strength of a pipeline;
- “easement width” means in respect of each pipeline the easement width shown on the conveyor route plans as adjusted if necessary (in respect of pipelines shown on the conveyor route plans) or added to (in respect of pipelines constructed after the date this Order is made) as a result of the pipeline survey;
- “engineer” means an engineer appointed by an owner or operator of a pipeline for the purposes of this Order;
- “major works” means works by any person requiring the closure, diversion or regulation of any roads serving the Wilton Complex;
- “Northumbrian Water Limited” means the company of that name (company number 02366703, whose registered office is at Northumbria House, Pity Me, Durham, DH1 5FJ);
- “operator” means any person who is responsible for the construction, operation, use, maintenance or renewal of any pipeline;
- “owner” means—in relation to the pipeline corridor, any person—with an interest in a pipeline in the pipeline corridor;with rights in, on, under or over the pipeline corridor in respect of a pipeline; orwith a pipeline or proposed pipeline in, on, under or over the pipeline corridor;in relation to the access roads, any person—with an interest in the access roads; orwith private rights of way on or over the access roads;in relation to the protected crossings, any person—with an interest in the protected crossings;with rights in relation to the protected crossings; orwith pipelines in or comprising the protected crossings; andin relation to protected land means any person falling within paragraphs (a) to (c) above.
- “pipelines” means the apparatus located in the pipeline corridor, or in or comprising a protected crossing at the time the pipeline survey is carried out or as may be added between the date of the pipeline survey and the commencement of works, providing that any such additions are notified to the undertaker as soon as reasonably practicable;
- “pipeline survey” means a survey of the pipeline corridor and the protected crossings to establish if not known—the precise location of the pipelines and the protected crossings;the specification of the pipelines and protected crossings including, where relevant, their composition, diameter, pressure and the products they are used to convey;any special requirements or conditions relating to the pipelines which differ from the requirements or conditions applying to standard pipelines of that type;the precise location of any easement widths or rights (where it is possible to establish this).
- “protected crossings” means—the tunnel under the River Tees which carries pipelines known as Tunnel 2; andthe apparatus under the River Tees known as the Breagh Pipeline;
- “protected land” means such parts of the Order land as fall within—the access roads;the pipeline corridor; orthe protected crossings;
- “relevant work” means a work which may have an effect on the operation, maintenance, abandonment of or access to any pipeline or a protected crossing;
- “specified persons” means—the following—Company Secretary, SABIC UK Petrochemicals Limited, Wilton Centre, Redcar, Cleveland, TS10 4RF in relation to SABIC UK Petrochemicals Limited;Operations Manager, Huntsman Polyurethanes, PO Box 99, Wilton, Redcar, TS10 4YA in relation to Huntsman Polyurethanes (UK) Limited;Company Secretary, INEOS UK SNS Limited, 4th Floor, 90 High Holborn, London WC1V 6LJ in relation to INEOS UK SNS Limited; andCATS Manager, CATS Terminal, Seal Sands Road, Seal Sands, Middlesbrough, Teesside TS1 1UB and Technical Director, CATS North Sea Limited, Wynyard Park House, Wynyard Avenue, Wynyard, Billingham TS22 STB in relation to CATS North Sea Limited, orsuch other person as they may notify to the undertaker in writing; orwhere a person for whose benefit these protective provisions have effect is not mentioned in paragraph (a)—that person where the person is not an incorporated body;the company secretary in relation to a company;the designated partner in relation to a limited liability partnership; orsuch other person as they may notify to the undertaker in writing;
- “unknown rights” means rights which are—not known at the date of the Order; oridentified as unknown in the book of reference,but not including any rights relating to pipelines (or access to pipelines) where a pipeline is shown on the pipeline survey;
- “Wilton Complex” means the land shown outlined in red on the Wilton Complex Plan;
- “Wilton Complex Plan” means the plan entitled “Location of Wilton Complex (Plan 1)” (drawing number T-MIS-0065-01);
- “works details” means the following—a description of the proposed works together with plans and sections of the proposed works where such plans and sections are reasonably required to describe the works concerned or their location;details of any proposed temporary crossing points under paragraph 10;details of methods and locations of any piling proposed to be undertaken under paragraph 14;details of methods of excavation and any zones of influence the undertaker has calculated under paragraph 15;details of methods and locations of any compaction of backfill proposed to be undertaken under paragraph 16;details of the location of any pipelines affected by the oversailing provisions in paragraph 17, including details of the proposed clearance;details of the method location and extent of any dredging, a technical assessment of the likely effect of the dredging on the protected crossings and any mitigation measures which are proposed to be put in place to prevent damage to the protected crossings;details of the undertaker and their principal contractors’ management of change procedures;details of the traffic management plan, which plan must include details of vehicle access routes for construction and operational traffic and which must assess the risk from vehicle movements and include safeguards to address identified risks;details of the electrical design of the authorised works in sufficient detail to allow an independent specialist to assess whether AC interference from the authorised development may cause damage to the cats pipeline;details (to include a dynamic analysis undertaken by the undertaker and provided to the cats pipeline operator) of the conveyor and conveyor support structure and the measures to be undertaken to ensure vibration does not impact on the cats pipeline;details of the lifting study during the construction phase, which must include a technical assessment of the protection of underground assets and which study must provide for individual lift plans;details of the lifting study during the operational phase, which must include a technical assessment of the protection of underground assets and which study must provide for individual lift plans;details of the means by which the entirety of the cats pipeline can be properly inspected and if necessary repaired during the construction and operation of the authorised development which must provide for an excavation to a depth of 0.6 metres below the cats pipeline and 2 metres either side of the centreline of the cats pipeline consistent with the relevant constructability notes;details of the emergency response plan as prepared in consultation with local emergency services and the pipeline operators;details of the assessment and monitoring work to be undertaken both prior to the construction of the authorised development and during the operation of the authorised development to ascertain any change or damage to the cats pipeline cathodic protection system and the proposed remedial works; andany further particulars provided in accordance with paragraph 4(2).
Pipeline survey
3
- (1) Before commencing any part of the authorised development in the pipeline corridor or which may affect a protected crossing the undertaker must—
- (a) carry out and complete the pipeline survey; and
- (b) comply with sub-paragraph (3) below.
- (2) The pipeline survey must be undertaken by a surveyor who is a member of the Royal Institute of Chartered Surveyors with at least 10 years’ experience of such surveys.
- (3) When the pipeline survey has been completed the undertaker must serve a copy of the pipeline survey on the owners and operators of the pipelines and protected crossings and invite them to advise the undertaker within 28 days of receipt of the survey if they consider that the pipeline survey is incomplete or inaccurate and if so in what respect following which the undertaker must finalise its pipeline survey.
Authorisation of works details affecting pipelines or protected crossings
4
- (1) Before commencing any part of a relevant work the undertaker must submit to the owners and any operators of any affected asset the works details and obtain a written acknowledgement of receipt of those works details from the specified persons in relation to the affected asset concerned.
- (2) The undertaker must as soon as reasonably practicable provide such further particulars as the owner or operator of any affected asset may, within 45 days from the receipt of the works details under sub-paragraph (1), reasonably require.
5
No part of a relevant work is to be commenced until one of the following conditions has been satisfied—
- (a) the works details supplied in respect of that relevant work under paragraph 4 have been authorised by the owner and operator of all the affected assets; or
- (b) the works details supplied in respect of that relevant work under paragraph 4 have been authorised by an expert under paragraph 7(3); or
- (c) authorisation is deemed to have been given in accordance with paragraph 7(1).
6
- (1) Any authorisation by the owner or operator of an affected asset required under paragraph 5(a) must not be unreasonably withheld but may be given subject to such reasonable conditions as the owner or operator of the affected asset may require to be made for—
- (a) the continuing safety and operation or viability of the affected asset; and
- (b) the requirement for the owner and operator of the affected asset to have—
- (i) uninterrupted and unimpeded emergency access with or without vehicles to the affected asset at all times; and
- (ii) reasonable access with or without vehicles to inspect, repair, replace and maintain and ensure the continuing safety and operation or viability of the affected asset.
- (2) Where the owner or operator of the cats pipeline can reasonably demonstrate that the authorised development will significantly adversely affect the safety of the cats pipeline the owner or operator is entitled to withhold their authorisation until the undertaker can demonstrate to the reasonable satisfaction of the owner or operator that the authorised development will not significantly adversely affect the safety of the cats pipeline.
- (3) The authorised development must be carried out in accordance with the works details authorised under paragraph 5 and any conditions imposed on the authorisation under paragraph 6(1).
- (4) Where there has been a reference to an expert in accordance with paragraph 7(2) and the expert gives authorisation, the authorised development must be carried out in accordance with the authorisation and conditions contained in the award of the expert under paragraph 7(3).
7
- (1) In the event that—
- (a) no response has been received to the submission of the works details under paragraph 4 within 45 days of the undertaker obtaining a written acknowledgment of receipt from a specified person under paragraph 4(1) and no further particulars have been requested under paragraph 4(2); or
- (b) authorisation has not been given within 30 days of the undertaker obtaining a written acknowledgment of receipt from a specified person of the further particulars supplied under paragraph 4(2),
approval of the works details is to be deemed to be given and the relevant works may commence.
- (2) In the event that—
- (a) the undertaker considers that the owner or operator has unreasonably withheld its authorisation under paragraph 6(1); or
- (b) the undertaker considers that an owner or operator has given its authorisation under paragraph 6(1) subject to unreasonable conditions,
the undertaker may refer the matter to an expert for determination under paragraph 34 .
- (3) Where the matter is referred to an expert under paragraph 7(2) the expert is to determine whether or not authorisation should be given and, if so, the conditions which should reasonably be attached to the authorisation under sub-paragraphs (a) and (b) of paragraph 6(1).
- (4) Where the undertaker considers that the owner or operator of the cats pipeline has unreasonably withheld its authorisation under paragraph 6(2) then the matter may be referred to an expert on the application of either party (after giving notice in writing to each other) appointed by the secretary of the United Kingdom Onshore Pipeline Association for determination under paragraph 34.
Notice of works
8
The undertaker must provide to the owner and operator of an affected asset a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions.
Further provisions about works
9
- (1) Before carrying out a relevant work the undertaker must—
- (a) provide the owners and any operators of any affected asset with baseline data for any existing cathodic protection of the asset; and
- (b) carry out a pipeline settlement and stress analysis to demonstrate any potential pipeline movement will not present an integrity risk to the affected asset.
- (2) The pipelines must be located by hand digging prior to the use of mechanical excavation provided that any excavation outside of 2 metres of the centreline of a pipeline may be dug by mechanical means.
- (3) The undertaker must engage an independent construction Quality Assurance Inspector to oversee cats pipeline critical construction activities during the construction phase.
10
- (1) Where temporary crossings for construction traffic are to be used, other than where the pipelines are under a carriageway of adequate standard of construction, then the crossing points must be suitably reinforced with sleepers or road plates or a specially constructed reinforced concrete raft or by installing a temporary bridge over the pipeline as necessary.
- (2) Details of proposed temporary crossing points referred to in sub-paragraph (1) must be notified to the owner and operator of the pipeline in accordance with paragraph 4.
11
During construction, an area equivalent to the easement widths of the pipelines (taken from the actual location of the pipelines shown on the pipeline survey) must be fenced off using some form of visual indication such as netlon fencing or “heras” type fence panels. Suitable signage warning of the danger of live pipelines must be erected at a minimum distance of every 50 metres.
12
No explosives are to be used within the protected land.
13
- (1) There must be no lifting over any exposed sections of the cats pipeline or live or vulnerable plant containing hazardous substances or pressure energy.
- (2) Any construction works above the buried sections of the cats pipeline require the protection of the cats pipeline.
- (3) All piling within 1.5 metres of the centreline of a pipeline must be non-percussive, except that in the case of the cats pipeline all piling within 10 metres of the centreline of the cats pipeline must be non-percussive.
14
- (1) Where piling is required within 50 metres of the centreline of a pipeline or which could have an effect on the operation or maintenance of a pipeline or access to a pipeline, details of the proposed method for and location of the piling must be provided to the owner and operator of the relevant pipeline for approval in accordance with paragraph 4.
- (2) Any proposed piling operations within—
- (a) 10 metres either side of the centreline of the cats pipeline require the crown of the pipeline to be physically exposed, so its location can be confirmed with the asset operator or owner as appropriate and where within 2 metres of the centreline of the cats pipeline it must be exposed by hand digging only; and
- (b) 5 metres either side of the centreline of the cats pipeline and, in addition to the obligations in paragraph 14(2)(a), require excavation to be carried out to a level below the depth of the pipeline, to ensure that no materials are present that could damage the pipeline if disturbed, in the presence of the asset owner or operator as appropriate.
- (3) All excavations within 2 metres of the centreline of the cats pipeline must be hand dug.
15
- (1) Where excavation of trenches (including excavation by dredging) adjacent to a pipeline affects its support, the pipeline must be supported in a manner approved by the owner and operator of the relevant pipeline.
- (2) Where the undertaker proposes to carry out excavations which might affect above ground structures such as pipeline supports in the pipeline corridor, the undertaker must calculate the zone of influence of those excavations and provide those calculations to the owner and operator of the pipeline under paragraph 4.
16
- (1) Where a trench is excavated across or parallel to the line of a pipeline, the backfill must be adequately compacted to prevent any settlement which could subsequently cause damage to the pipeline.
- (2) Proposed methods and locations of compacting must be notified to the owner and operator of the pipeline in accordance with paragraph 4.
- (3) Compaction testing must be carried out once back filling is completed to establish whether the backfill has been adequately compacted as referred to in sub-paragraph (1) and what further works may be necessary, and the results of such testing must be supplied to the owner and operator of the pipeline.
- (4) Where it is shown by the testing under sub-paragraph (3) to be necessary, the undertaker must carry out further compaction testing under sub-paragraph (1) and sub-paragraphs (1), (2) and (3) continue to apply until such time as the backfill has been adequately compacted.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.