The Hornsea Two Offshore Wind Farm Order 2016

Type Statutory-Instrument
Publication 2016-08-16
Last updated 2018-05-08
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (24) The combined total area of the site of Work Nos. 8A and 8B must not exceed 49,326 square metres, excluding any area of land required for landscaping and mitigation.
  • (25) The electrical circuits comprised in Work Nos. 7A and 7B must be installed by use of a trenchless technique where crossing under a main river.
  • (26) The width of the corridor occupied by the connection comprised in Work Nos. 7A and 7B following completion of construction of those works must not exceed 30 metres, except where those works overlap with Work No. 5A, 5B, 6A or 6B in which case the width of the corridor occupied by the connection comprising Work Nos. 7A and 7B must not exceed 150 metres.

Colour and lighting

3

Except as otherwise required by Trinity House under Condition 4 of each of the deemed marine licences, the undertaker must exhibit such lights, with such shape, colour and character as required by the Air Navigation Order 2009[^f00043] or as otherwise directed by the Civil Aviation Authority or the Secretary of State for Defence.

Foundation methods

4

  • (1) The undertaker must in fixing to the seabed any structures comprised in Work Nos. 1A, 1B, 2A, 2B, 3A and 3B use one of the following methods—
  • (a) monopile foundations;
  • (b) jacket foundations supported by piles; or
  • (c) gravity base foundations.
  • (2) The undertaker must not use the monopile foundation method or any other method that includes braced monopiles to fix to the seabed any offshore HVDC converter substation.
  • (3) The following parameters apply in respect of the foundation methods used to fix wind turbine generators to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 2,827 square metres;
  • (ii) the number of piles per jacket must not exceed 12;
  • (iii) the diameter of each pile must not exceed 6 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and scour protection for each individual structure must not exceed 12,596 square metres;
  • (ii) the number of piles per jacket must not exceed 4;
  • (iii) the diameter of each pile must not exceed 21.1 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 7,543 square metres;
  • (ii) the seabed levelling diameter must not exceed 78 metres;
  • (iii) the cone diameter must not exceed 58 metres at its base.
  • (4) The following parameters apply in respect of the foundation methods used to fix offshore accommodation platforms to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,414 square metres;
  • (ii) the number of piles must not exceed 8;
  • (iii) the diameter of each pile must not exceed 3 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the number of piles per jacket must not exceed 4;
  • (iii) the diameter of each pile must not exceed 15 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the seabed levelling diameter must not exceed 70 metres;
  • (iii) the cone diameter must not exceed 50 metres at its base.
  • (5) The following parameters apply in respect of the foundation methods used to fix offshore HVAC collector substations to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,924 square metres;
  • (ii) the number of piles per jacket must not exceed 8;
  • (iii) the diameter of each pile must not exceed 3.5 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 12,723 square metres;
  • (ii) the number of piles per jacket must not exceed 8;
  • (iii) the diameter of each pile must not exceed 15 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the seabed levelling diameter must not exceed 70 metres;
  • (iii) the cone diameter must not exceed 50 metres at its base.
  • (6) The following parameters apply in respect of the foundation methods used to fix offshore HVDC converter substations to the seabed—
  • (a) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 17,318 square metres;
  • (ii) the number of jacket foundations per topside must not exceed 4;
  • (iii) the number of piles per topside must not exceed 72;
  • (iv) the number of piles per jacket must not exceed 18;
  • (v) the diameter of each pile must not exceed 3.5 metres;
  • (b) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 50,894 square metres;
  • (ii) the number of jacket foundations per topside must not exceed 4;
  • (iii) the number of piles per topside must not exceed 32;
  • (iv) the number of piles per jacket must not exceed 8;
  • (v) the diameter of each pile must not exceed 15 metres;
  • (c) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 27,300 square metres;
  • (ii) the number of pontoons for each individual structure must not exceed 3;
  • (iii) the pontoons must not exceed 170 metres in length or 35 metres in width.
  • (7) The following parameters apply in respect of the foundation methods used to fix the offshore reactive compensation substation to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection must not exceed 1,414 square metres;
  • (ii) the number of piles per jacket must not exceed 8;
  • (iii) the diameter of each pile must not exceed 3 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection must not exceed 6,362 square metres;
  • (ii) the number of piles per jacket must not exceed 4;
  • (iii) the diameter of each pile must not exceed 15 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the seabed levelling diameter must not exceed 70 metres;
  • (iii) the cone diameter must not exceed 50 metres at its base.
  • (8) The combined total volume of scour protection for the wind turbine generators and the offshore accommodation platforms forming part of the authorised development must not exceed 4,761,555 cubic metres.

Archaeology landward of mean low water springs

5

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until a written scheme for the investigation of areas of archaeological interest landward of MLWS has been submitted to and approved by the local planning authority.
  • (2) The scheme must identify areas where field work or a watching brief (or both) are required and the measures to be taken to evaluate, protect, record or preserve any significant archaeological remains that may be found.
  • (3) Any archaeological works or watching brief must be carried out—
  • (a) in accordance with the approved scheme;
  • (b) by a suitably qualified person or body approved by the local planning authority.
  • (4) Staged reports of the measures taken to evaluate, protect, record or preserve any significant archaeological remains that are found must be submitted to and approved by the local planning authority before the commencement of any works that would affect those remains.

Ecological management plan landward of mean low water springs

6

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until an ecological management plan relating to the land landward of MLWS based on the outline ecological management plan and reflecting the survey results and ecological mitigation measures included in the environmental statement has been submitted to and approved by the local planning authority in consultation with Natural England, the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.
  • (2) The ecological management plan must include an implementation timetable and must be carried out as approved.
  • (3) The ecological management plan must be submitted for approval at least 4 months before the intended start of construction unless otherwise agreed by the local planning authority in consultation with Natural England.

Code of construction practice

7

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until a code of construction practice relating to the Works landward of MLWS based on the outline code of construction practice has been submitted to and approved by the local planning authority.
  • (2) Before giving approval in the case of a construction traffic management plan referred to in sub-paragraph (3)(e) and a travel plan referred to in sub-paragraph (3)(l), the local planning authority must consult the highway authority and Highways England.
  • (3) The code of construction practice must include—
  • (a) an external lighting scheme for the construction phase;
  • (b) construction noise and vibration monitoring and management measures;
  • (c) air quality and dust monitoring and management measures during construction;
  • (d) a site waste management plan detailing sustainable site waste management measures;
  • (e) a construction traffic management plan;
  • (f) measures to prevent and control spillage of oil, chemicals and other potentially harmful liquids;
  • (g) details of the storage of materials during construction;
  • (h) measures for the protection of surface and ground water during construction;
  • (i) a communication plan;
  • (j) a health and safety plan, including details of how health and safety risks are to be identified and managed during construction;
  • (k) details of screening and fencing to be installed during construction; and
  • (l) a travel plan for the construction workforce to include details of—
  • (i) expected means of travel to and from the construction sites;
  • (ii) numbers of construction staff, working hours and modal split;
  • (iii) details of the number of car parking spaces to be provided on sites and if appropriate a car park management plan;
  • (iv) specification of measures to encourage sustainable travel to and from the construction site for construction staff;
  • (v) responsibility and timescales for implementing proposed measures;
  • (vi) targets for vehicle trips and modal splits;
  • (vii) formal monitoring regime for those targets; and
  • (viii) details of mess or canteen facilities for staff.
  • (4) All construction works must be undertaken in accordance with the approved code.

Landscape scheme

8

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until a landscape scheme has been submitted to and approved by the local planning authority.
  • (2) The landscape scheme must include the provisions of the outline landscape scheme and management plan, subject to any variation approved by the local planning authority, and, in addition details of—
  • (a) cultivation, importing of materials and other operations to ensure plant establishment;
  • (b) proposed finished ground levels;
  • (c) hard surfacing materials; and
  • (d) minor structures, refuse or other storage units, signs and lighting.

Implementation and maintenance of landscaping

9

  • (1) Landscape works must be carried out in accordance with the relevant landscape scheme approved under Requirement 8.
  • (2) Any tree or shrub planted as part of an approved landscape scheme that within a period of 5 years after planting, is removed, dies or becomes, in the opinion of the local planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless alternative timing or a different specimen is otherwise approved by the local planning authority.

Offshore decommissioning

10

No part of the authorised development seaward of MLWS may be commenced until a decommissioning programme in compliance with any notice served on the undertaker by the Secretary of State under section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval in relation to that part.

Highway accesses

11

  • (1) No permanent or temporary means of access to a highway to be used by vehicular traffic or any alteration to an existing means of access to a highway used by vehicular traffic may be commenced until details of the design and layout of such works have been submitted to and approved by the local planning authority in consultation with the highway authority.
  • (2) The highway accesses must be constructed in accordance with the approved details.

Contaminated land and groundwater scheme

12

  • (1) No part of the authorised development within the area of a local planning authority may be commenced until a scheme to deal with the contamination of any land (including groundwater) within the Order limits that is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to, and approved by, the local planning authority in consultation with the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.
  • (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the local planning authority, to identify the extent of any contamination and the remedial measures to be taken for that stage to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
  • (3) No remedial work constituting a material operation (as defined in section 155 of the 2008 Act) in respect of contamination of any land (including groundwater) within the Order limits may be carried out until the scheme has been approved.
  • (4) In carrying out the works for the authorised development, the undertaker must not conduct trenchless technique operations unless the scheme includes a hydrogeological risk assessment demonstrating that such operations are unlikely to cause an unacceptable risk to groundwater quality.
  • (5) Remediation must be carried out in accordance with the approved scheme.
  • (6) In this Requirement, “controlled waters” has the meaning given in Part 3 of the Water Resources Act 1991[^f00044].

Surface water drainage scheme

13

  • (1) No part of any electrical transmission station may be commenced until a detailed surface water drainage scheme based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the electrical transmission station has been submitted to and approved by the local planning authority, in consultation with the drainage board concerned within the meaning of section 23 of the Land Drainage Act 1991.
  • (2) Construction of the electrical transmission station must be carried out in accordance with the approved scheme.

Colour and detailed design approval: electrical transmission stations

14

  • (1) Unless otherwise agreed by the local planning authority, the electrical transmission stations must be coloured using one or more of the following colours—
  • (a) bluebell (RAL Code 270 50 30);
  • (b) lilac (RAL Code 270 60 25);
  • (c) chalk blue (RAL Code 270 70 20);
  • (d) Baltic blue (RAL Code 270 80 15);
  • (e) white lilac (RAL Code 270 85 10);
  • (f) blue white (RAL Code 270 90 05).
  • (2) Despite sub-paragraph (1), construction of Work No. 8A must not commence until details of the layout, scale and external appearance of that Work have been submitted to and approved by the local planning authority.
  • (3) Despite sub-paragraph (1), construction of Work No. 8B must not commence until details of the layout, scale and external appearance of that work have been submitted to and approved by the local planning authority.
  • (4) The construction of Work Nos. 8A and 8B must be carried out in accordance with the approved details.

Access road within plots 45 to 49

15

  • (1) The undertaker must not use the access road along the crest of the sea defences within the plots numbered 45 to 49 on the land plans during the construction of Work Nos. 4A, 4B, 5A, 5B, 6A and 6B.
  • (2) Except in an emergency, the access road along the sea defences within the plots numbered 45 to 49 on the land plans must not be used by the undertaker following the construction of Work Nos. 4A, 4B, 5A, 5B, 6A and 6B until a scheme for the protection of the sea defences from use of the access road by the undertaker during the operation and maintenance of the authorised development has been submitted to and approved by the Environment Agency, such approval not to be unreasonably withheld or delayed.
  • (3) If the Environment Agency fails to notify the undertaker of its decision on whether to give approval within 2 months of receiving the scheme for approval, the Environment Agency is deemed to have given approval.
  • (4) The use of the access road must be in accordance with the approved scheme.

Port traffic management plan

16

  • (1) No part of the authorised development seaward of MLWS (excluding ducting and related works which are an integral part of works landward of MLWS) may be commenced until—
  • (a) a traffic management plan for the onshore port-related traffic to and from the selected base port or ports for construction or operation (or both) of that part of the authorised development has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority; or
  • (b) the relevant planning authority has confirmed, after consultation with the relevant highway authority, that no traffic management plan is required for that part of the authorised development.
  • (2) All traffic management plans must be implemented as approved at all times specified within the relevant traffic management plan during the construction and operation of the authorised development.
  • (3) In this Requirement—
  • “relevant highway authority” means the highway authority in whose area the selected base port is located;
  • “relevant planning authority” means the local planning authority in whose area the selected base port is located;
  • “selected base port” means a port situated in England and/or Wales and used by management personnel for the construction or ongoing operational management of the authorised development (or both).

Employment and skills plan

17

  • (1) No part of the authorised development may be commenced until an employment and skills plan based on the outline employment and skills plan has been submitted to and approved by North Lincolnshire Council in consultation with North East Lincolnshire Council, East Lindsey District Council and the Humber Local Enterprise Partnership.
  • (2) The plan must include—
  • (a) proposals for the provision of information to the Humber Local Enterprise Partnership on the employment and supply chain opportunities associated with the construction, operation and maintenance of the authorised development including details of the core qualifications and skillsets required to access those opportunities;
  • (b) proposals for local advertising of employment and supply chain opportunities during the construction of the authorised development;
  • (c) proposals for the undertaker to provide outreach employment presentations during the period of construction of the authorised development at appropriate times and locations; and
  • (d) proposals for local advertising of employment and supply chain opportunities during the operation of the authorised development.
  • (3) The approved employment and skills plan must be implemented and maintained during the construction and operation of the authorised development.
  • (4) In this Requirement, “Humber Local Enterprise Partnership” means the local enterprise partnership established in June 2011 with the objective of promoting and developing the natural economic area surrounding the Humber estuary.

Offshore co-operation

18

  • (1) Before submitting the pre-construction plans and documentation required to be submitted to the MMO for approval under Condition 8 of each of the deemed marine licences, the undertaker in respect of the relevant licence must provide a copy of the plans and documentation to the other undertaker under this Order.
  • (2) The other undertaker must provide any comments on the plans and documentation to the first undertaker within 14 days of receipt.
  • (3) Each undertaker must participate in liaison meetings with the other undertaker as requested from time to time by the MMO in writing in advance; and the meetings must be chaired by the MMO and must consider such matters as are determined by the MMO relating to the efficient operation of a deemed marine licence where it has an impact on the efficient operation of any other deemed marine licence.

Compensation compounds

19

  • (1) The undertaker may exercise the powers conferred by this Order in relation to the compensation compounds shown coloured green on the compensation compounds plan only where—
  • (a) the undertaker exercises, or intends to exercise, the powers conferred by this Order in relation to the Order land shown hatched green on the compensation compounds plan; and
  • (b) sub-paragraph (4) applies.
  • (2) The undertaker may exercise the powers conferred by this Order only in relation to the compensation compound access coloured pink and labelled 14-A1c on the compensation compounds plan only where the undertaker exercises, or intends to exercise, the powers conferred by this Order in relation to the compensation compound shown coloured green and labelled 14-C3 on the compensation compounds plan in accordance with sub-paragraph (1).
  • (3) Where the undertaker exercises the powers conferred by this Order in relation to—
  • (a) the compensation compounds shown coloured green on the compensation compounds plan in accordance with sub-paragraph (1); or
  • (b) the compensation compound access coloured pink and labelled 14-A1c on the compensation compounds plan in accordance with sub-paragraph (2),

those powers may be exercised only for the benefit of the Hornsea Project One undertaker in connection with the carrying out of works authorised by the Hornsea One Offshore Wind Farm Order 2014.

  • (4) This sub-paragraph applies where—
  • (a) the carrying out of works authorised by this Order in the Order land shown hatched green on the compensation compounds plan would overlap temporally with the carrying out of works authorised by the Hornsea One Offshore Wind Farm Order 2014 in that land; or
  • (b) works authorised by this Order in the Order land shown hatched green on the compensation compounds plan are carried out and completed before the works authorised by the Hornsea One Offshore Wind Farm Order 2014 in that land commence.

Onshore decommissioning plan

20

  • (1) Within 3 months of the cessation of commercial operation of the connection works, an onshore decommissioning plan must be submitted to the local planning authority for its approval.
  • (2) The decommissioning plan must be implemented as approved.

North Coates airfield

21

No part of the authorised development may be commenced within half a mile of the perimeter of the North Coates airfield until a plan to secure its safe operation during the construction and operation of the authorised development has been submitted to and approved by the Secretary of State following consultation with the operator of North Coates airfield and the Civil Aviation Authority.

Control of noise during operational phase

22

  • (1) The combined rating level (LAr,Tr) of the noise emitted during normal operation from the electrical transmission station, converter and associated plant, must not exceed 35 decibels at any residential property that has planning permission on 1st December 2014.
  • (2) The assessment must be carried out in accordance with BS 4142:2014 “Methods for rating and assessing industrial and commercial sound”[^f00045].

Onshore co-operation

23

  • (1) Before submitting any plan or document required to be submitted for approval under the Requirements, the undertaker in respect of the works to which the plan or document relates must provide a copy of the plan or document to the other undertaker under this Order.
  • (2) The other undertaker must provide any comments on the plan or document to the first undertaker within 14 days of receipt.
  • (3) On submission of any plan or document referred to in sub-paragraph (1) for approval, the undertaker in respect of the works to which the plan or document relates must also submit any comments received from the other undertaker under sub-paragraph (2) or a statement confirming that no such comments were received.
  • (4) Each undertaker must participate in liaison meetings with the other undertaker as requested from time to time by the local planning authority in writing in advance; and the meetings must be chaired by the local planning authority and must consider such matters as are determined by the local planning authority relating to the efficient construction and operation of the Project A works and the shared works above MLWS where they have an impact on the efficient construction and operation of the Project B works and the shared works above MLWS (and vice versa).

Intertidal access management plan

24

  • (1) No part of the authorised development within the intertidal area may be commenced until an intertidal access management plan setting out details of the access routes to the intertidal area, the methods for accessing the intertidal area, the expected number of vehicles that will be accessing the intertidal area and the expected number of vehicle trips to the intertidal area required in relation to that part of the authorised development has been submitted to and approved by the local planning authority in consultation with Natural England.
  • (2) The undertaker must not exercise the power to maintain under article 7 (maintenance of authorised project) in the intertidal area until an intertidal access management plan setting out details of the access routes to the intertidal area, the methods for accessing the intertidal area, the expected number of vehicles that will be accessing the intertidal area and the expected number of vehicle trips to the intertidal area required for such maintenance activities has been submitted to and approved by the local planning authority in consultation with Natural England.
  • (3) If the local planning authority fails to notify the undertaker of its decision on whether to give approval within 2 months of receiving an intertidal access management plan for approval, the local planning authority is deemed to have given approval.
  • (4) The intertidal access management plan must be implemented as approved, unless otherwise agreed by the local planning authority.

25

  • (1) No construction of any wind turbine generator forming part of the authorised development may commence until the Secretary of State, having consulted with the operator, is satisfied that appropriate mitigation will be implemented and maintained for the life of the authorised development.
  • (2) In this Requirement—
  • “appropriate mitigation” means measures to mitigate any adverse impacts which the operation of the authorised development will have on the ability of the operator’s radar early warning system to ensure the safety of its Saturn, Mimas and Tethys offshore platforms during the life of the authorised development;
  • “operator” means ConocoPhillips (U.K.) Limited (company number 00524868) or successor operator of any of the Saturn, Mimas or Tethys offshore platforms;
  • “radar early warning system” means the radar early warning system used to monitor and track vessels proximate to the operator’s offshore facilities via radio and network links (which is comprised primarily of radars fitted on a number of operator’s offshore platforms and provides a multi-site, multi-sensor integrated marine surveillance system with logistic and emergency response co-ordination facilities).
  • (3) The undertaker must comply with all obligations contained within the appropriate mitigation for the life of the authorised development.

Requirement for written approval

26

Where the approval, agreement or confirmation of the Secretary of State, the local planning authority or another person is required under a Requirement, that approval, agreement or confirmation must be given in writing.

Amendments to approved plans, etc.

27

  • (1) Where a Requirement requires the authorised development to be carried out in accordance with a plan, scheme, code or details approved by the local planning authority or any other person (the “approved plan”), the approved plan must be taken to include any amendments that may subsequently be approved by the local planning authority or other person.
  • (2) Any amendments to the approved plan must be in accordance with the principles and assessments set out in the environmental statement; and approval for such amendments may be given only where it has been demonstrated to the satisfaction of the local planning authority or other person that the amendments are unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
  • (3) Where the approved plan is required to be approved after consultation with another person, any amendments may be approved only after consultation with that person.

SCHEDULE 2 — Streets subject to street works

(1) Area (2) Streets subject to street works
District of East Lindsey Permissive footpath along sea wall
District of East Lindsey Sheep Marsh Lane
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north
District of East Lindsey Sea Lane
District of East Lindsey Tetn/19/1 (public footpath)
District of East Lindsey North Coates Road
District of East Lindsey Tetn/343/1 (public footpath)
District of East Lindsey Tetn/12/5 (public footpath)
District of East Lindsey Tetn/13/5 (public footpath)
District of East Lindsey Unnamed highway east of New Delights access
District of East Lindsey Tetney Lock Road
District of East Lindsey Humberston Road (A1031)
District of East Lindsey Tetn/14/4 (public footpath)
District of East Lindsey Holton Road
District of East Lindsey HoLC/5/4 (public footpath)
District of East Lindsey Station Road, Tetney
District of East Lindsey HoLC/4/1 (public footpath)
District of East Lindsey Louth Road (A16)
District of East Lindsey High Street, North Thoresby (B1201)
District of East Lindsey Station Road, North Thoresby (B1201)
District of East Lindsey HoLC/10/1 (public footpath)
North East Lincolnshire Brigsley FP84 (public footpath)
North East Lincolnshire Brigsley FP83 (public footpath)
North East Lincolnshire Waithe Lane
North East Lincolnshire Brigsley BW75 (public bridleway)
North East Lincolnshire Waltham Road, Brigsley (B1203)
North East Lincolnshire Waltham Road, Barnoldby le Beck (C148)
North East Lincolnshire Bradley FP95 (public footpath)
North East Lincolnshire Bradley Road
North East Lincolnshire Bradley BW93 (public bridleway)
North East Lincolnshire Laceby FP95 (public footpath)
North East Lincolnshire Laceby BW97 (public bridleway)
North East Lincolnshire Laceby FP96 (public footpath)
North East Lincolnshire Grimsby Road (A46)
North East Lincolnshire Aylesby FP103 (public footpath)
North East Lincolnshire Aylesby FP110 (public footpath)
North East Lincolnshire Aylesby Road
North East Lincolnshire Aylesby BW108 (public bridleway)
North East Lincolnshire Beech Holt Lane
North East Lincolnshire Nooking Lane
West Lindsey District Wells Road
North East Lincolnshire Riby Road (A1173)
North East Lincolnshire Stallingborough FP26 (public footpath)
North East Lincolnshire Stallingborough FP24 (public footpath)
North East Lincolnshire Keelby Road
North East Lincolnshire Habrough FP4 (public footpath)
North East Lincolnshire Roxton Road south of A180 between Keelby and Immingham
North East Lincolnshire A180(T)
North East Lincolnshire Station Road, Habrough (B1210)
North East Lincolnshire Immingham Road (B1210)
North East Lincolnshire Habrough FP8 (public footpath)
North East Lincolnshire Habrough FP7 (public footpath)
North East Lincolnshire Killingholme Road/ Habrough Road
North Lincolnshire Council South Killingholme 94 (public footpath) FP/SKIL/94
North Lincolnshire Council Habrough Road/Faulding Lane
North Lincolnshire Council South Killingholme 87 (public footpath) FP/SKIL/87
North Lincolnshire Council Habrough Road
North Lincolnshire Council South Killingholme 88 (public footpath) FP/SKIL/88
North Lincolnshire Council Proposed A160 upgrade/realignment (HA Improvement Scheme)
North Lincolnshire Council Ulceby Road (A160)
North Lincolnshire Council Ulceby Road access to houses
North Lincolnshire Council Top Road
North Lincolnshire Council Currently unconstructed road on route of proposed cable route (part of the A160 improvement works) north of the A160 and west of Top Road (area hatched between points 119 and 120 on the onshore works plan 24)
North Lincolnshire Council South Killingholme 87 (public footpath) FP/SKIL/87
North Lincolnshire Council South Killingholme 85 (public footpath) FP/SKIL/85
North Lincolnshire Council Church Lane/ Nicholson Road
North Lincolnshire Council Chase Hill Road
North Lincolnshire Council Eastfield Road
North Lincolnshire Council Brick Lane/Dean Street
North Lincolnshire Council North Killingholme 86 (public footpath) FP/NKIL/86
North Lincolnshire Council North Killingholme 79 (public footpath) FP/NKIL/79

SCHEDULE 3 — Streets to be temporarily stopped up

(1) Area (2) Street to be temporarily stopped up (3) Extent of temporary stopping up
District of East Lindsey Permissive footpath Between points F1 and F2 as shown in a dotted black line on sheet 1 of the onshore works plans
District of East Lindsey Permissive footpath Between points F3 and F4 as shown in a dotted black line on sheet 1 of the onshore works plans
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north Between points 1 and 2 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north Between points 3 and 4 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north Between points 5 and 6 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Sea Lane Between points 7 and 8 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Footpath Tetn/19/1 Between points F5 and F6 as shown in a dotted black line on sheet 3 of the onshore works plans
District of East Lindsey Footpath Tetn/19/1 Between points F7 and F8 as shown in a dotted black line on sheet 3 of the onshore works plans
District of East Lindsey North Coates Road Between points 9 and 10 as shown hatched on sheet 4 of the onshore works plans
District of East Lindsey Footpath Tetn/13/5 Between points F9 and F10 as shown in a dotted black line on sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 11 and 12 as shown hatched on sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 13 and 14 as shown hatched on sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 15 and 16 as shown hatched on Sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 17 and 18 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 19 and 20 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Tetney Lock Road Between points 21 and 22 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Tetney Lock Road Between points 23 and 24 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Humberston Road Between points 25 and 26 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Footpath Tetn/14/4 Between points F11 and F12 as shown in a dotted black line on sheet 6 of the onshore works plans
District of East Lindsey Holton Road Between points 27 and 28 as shown hatched on sheet 6 of the onshore works plans
District of East Lindsey Holton Road Between points 121 and 122 as shown hatched on sheet 6 of the onshore works plans
District of East Lindsey Holton Road Between points 123 and 124 as shown hatched on sheet 6 of the onshore works plans
District of East Lindsey Footpath HoLC/5/4 Between points F13 and F14 as shown in a dotted black line on sheet 7 of the onshore works plans
District of East Lindsey Footpath HoLC/5/4 Between points F14 and F15 as shown in a dotted black line on sheet 7 of the onshore works plans
District of East Lindsey Station Road, Tetney Between points 29 and 30 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Station Road, Tetney Between points 31 and 32 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Station Road, Tetney Between points 33 and 34 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Footpath HoLC/4/1 Between points F16 and F17 as shown in a dotted black line on sheet 7 of the onshore works plans
District of East Lindsey Louth Road (A16) Between points 35 and 36 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Louth Road (A16) Between points 36 and 37 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Louth Road (A16) Between points 38 and 39 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Footpath HoLC/10/1 Between points F18 and F19 as shown in a dotted black line on sheet 8 of the onshore works plans
North East Lincolnshire Footpath FP84 Between points F18 and F21 as shown in a dotted black line on sheet 8 of the onshore works plans
North East Lincolnshire Footpath FP83 Between points F20 and F20.1 as shown in a dotted black line on sheet 8 of the onshore works plans
North East Lincolnshire Waithe Lane Between points 40 and 41 as shown hatched on sheet 8 of the onshore works plans
North East Lincolnshire Waithe Lane Between points 127 and 128 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waithe Lane Between points 42 and 43 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Bridleway BW75 Between points F22 and F23 as shown in a dotted black line on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (B1203) Between points 44 and 45 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (B1203) Between points 46 and 47 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (B1203) Between points 48 and 49 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (C148) Between points 50 and 51 as shown hatched on sheet 10 of the onshore works plans
North East Lincolnshire Bradley Road Between points 52 and 53 as shown hatched on sheet 11 of the onshore works plans
North East Lincolnshire Footpath FP95 Between points F24 and F25 as shown in a dotted black line on sheet 12 of the onshore works plans
North East Lincolnshire Footpath FP95 Between points F26 and F27 as shown in a dotted black line on sheet 12 of the onshore works plans
North East Lincolnshire Bradley Road Between points 54 and 55 as shown hatched on sheet 12 of the onshore works plans
North East Lincolnshire Bradley Road Between points 56 and 57 as shown hatched on sheet 12 of the onshore works plans
North East Lincolnshire Bridleway BW93 Between points F28 and F29 as shown in a dotted black line on sheet 12 of the onshore works plans
North East Lincolnshire Footpath FP95 Between points F30 and F31 as shown in a dotted black line on sheet 13 of the onshore works plans
North East Lincolnshire Bridleway BW97 Between points F32 and F33 as shown in a dotted black line on sheet 14 of the onshore works plans
North East Lincolnshire Footpath FP96 Between points F34 and F35 as shown in a dotted black line on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 58 and 59 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 60 and 61 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 62 and 63 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 64 and 65 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 60 and 65 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 58 and 62 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Footpath FP103 Between points F36 and F37 as shown in a dotted black line on sheet 15 of the onshore works plans
North East Lincolnshire Footpath FP110 Between points F38 and F39 as shown in a dotted black line on sheet 15 of the onshore works plans
North East Lincolnshire Aylesby Road Between points 66 and 67 as shown hatched on sheet 15 of the onshore works plans
North East Lincolnshire Bridleway BW108 Between points F40 and F41 as shown in a dotted black line on sheet 15 of the onshore works plans
North East Lincolnshire Beech Holt Lane/Nooking Lane Between points 68 and 69 as shown hatched on sheet 16 of the onshore works plans
West Lindsey District Wells Road Between points 70 and 71 as shown hatched on sheet 17 of the onshore works plans
North East Lincolnshire Riby Road (A1173) Between points 72 and 73 as shown hatched on sheet 18 of the onshore works plans
North East Lincolnshire Riby Road (A1173) Between points 74 and 75 as shown hatched on sheet 18 of the onshore works plans
North East Lincolnshire Footpath FP26 Between points F42 and F43 as shown in a dotted black line on sheet 19 of the onshore works plans
North East Lincolnshire Keelby Road Between points 76 and 77 as shown hatched on sheet 19 of the onshore works plans
North East Lincolnshire Keelby Road Between points 78 and 79 as shown hatched on sheet 19 of the onshore works plans
North East Lincolnshire Roxton Road Between points 80 and 81 as shown hatched on sheet 20 of the onshore works plans
North East Lincolnshire Roxton Road Between points 82 and 83 as shown hatched on sheet 20 of the onshore works plans
North East Lincolnshire Station Road (B1210) Between points 92 and 93 as shown hatched on sheet 22 of the onshore works plans
North East Lincolnshire Immingham Road (B1210) Between points 94 and 95 as shown hatched on sheet 23 of the onshore works plans
North East Lincolnshire Immingham Road (B1210) Between points 96 and 97 as shown hatched on sheet 23 of the onshore works plans
North East Lincolnshire Footpath FP8 Between points F44 and F45 as shown in a dotted black line on sheet 23 of the onshore works plans
North East Lincolnshire Footpath FP7 Between points F46 and F47 as shown in a dotted black line on sheet 23 of the onshore works plans
North East Lincolnshire Killingholme Road/ Habrough Road Between points 98 and 99 as shown hatched on sheet 23 of the onshore works plans
North Lincolnshire Council Footpath 94 Between points F48 and F49 as shown in a dotted black line on sheet 24 of the onshore works plans
North Lincolnshire Council Faulding Lane Between points 100 and 101 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council Footpath 87 Between points F50 and F51 as shown in a dotted black line on sheet 24 of the onshore works plans
North Lincolnshire Council Footpath 88 Between points F52 and F53 as shown in a dotted black line on sheet 24 of the onshore works plans
North Lincolnshire Council Habrough Road Between points 102 and 103 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council Ulceby Road (A160) Between points 104 and 105 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council On cable route – potential future road Between points 119 and 120 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council Top Road Between points 106 and 107 as shown hatched on sheet 25 of the onshore works plans
North Lincolnshire Council Footpath 87 Between points F54 and F55 as shown in a dotted black line on sheet 25 of the onshore works plans
North Lincolnshire Council Footpath 87 Between points F56 and F57 as shown in a dotted black line on sheet 25 of the onshore works plans
North Lincolnshire Council Church Lane Between points 108 and 109 as shown hatched on sheet 25 of the onshore works plans
North Lincolnshire Council Church Lane Between points 109 and 111 as shown hatched on sheet 25 of the onshore works plans
North Lincolnshire Council Chase Hill Road Between points 112 and 113 as shown hatched on sheet 26 of the onshore works plans
North Lincolnshire Council Chase Hill Road Between points 114 and 115 as shown hatched on sheet 26 of the onshore works plans
North Lincolnshire Council Brick Lane Between points 115 and 116 as shown hatched on sheet 26 and 27 of the onshore works plans
North Lincolnshire Council Footpath 86 Between points F58 and F59 as shown in a dotted black line on sheet 27 of the onshore works plans
North Lincolnshire Council Footpath 79 Between points F60 and F61 as shown in a dotted black line on sheet 27 of the onshore works plans
North Lincolnshire Council Footpath 86 Between points F62 and F65 as shown in a dotted black line on sheet 27 of the onshore works plans
North Lincolnshire Council Footpath 86 Between points F65 and F64 as shown in a dotted red line on sheet 27 of the onshore works plans
North Lincolnshire Council Chase Hill Road Between points 117 and 118 as shown hatched on sheet 27 of the onshore works plans

SCHEDULE 4 — Access to works

(1) Area (2) Description of Access
District of East Lindsey Between point A1 (north side of Sheep Marsh Lane) shown on sheet 1 of the onshore works plans and Work Nos. 5A, 5B, 6A, 6B, 7A and 7B
District of East Lindsey Between point A2 (unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries) shown on sheet 2 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A3 (north side of North Coates Road) shown on sheet 3 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A4 (south side of North Coates Road) shown on sheet 4 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A5 (north side of unnamed highway east of New Delights access) shown on sheet 4 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A51 (north side of Tetney Lock Road east of New Delights access) shown on sheet 4 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A52 (north side of unnamed highway east of New Delights access) shown on sheet 4 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A53 (north side of unnamed highway east of New Delights access) shown on sheet 4 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A6 (north side of Tetney Lock Road west of Cow Marsh Lane) shown on sheet 5 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A7 (south side of unnamed highway east of New Delights access) shown on sheet 5 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A8 (north side of unnamed highway east of New Delights access) shown on sheet 5 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A9 (north side of Tetney Lock Road east of Humberston Road) shown on sheet 5 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A10 (west side of Holton Road) shown on sheet 6 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A11 (south side of Holton Road) shown on sheet 6 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A12 (north side of Station Road) shown on sheet 7 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A13 (north side of Station Road to the west of the dismantled railway line) shown on sheet 7 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A14 (north side of Station Road) shown on sheet 7 of the onshore works plans and Work Nos. 7A and 7B
District of East Lindsey Between point A15 (west side of A16) shown on sheet 8 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A16 (west side of B1203, Waltham Road) shown on sheet 9 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A56 (east side of B1203, Waltham Road) shown on sheet 9 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A17 (south side of C148 Waltham Road) shown on sheet 10 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A18 (north side of C148 Waltham Road) shown on sheet 10 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A20 (west side of Bradley Road north of Waltham) shown on sheet 11 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A21 (west side of Bradley Road south of Netherwood Farm access point) shown on sheet 12 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A22 (west side of Bradley Road Netherwood Farm south access point) shown on sheet 12 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A23 (south-east side of A46 east of Laceby) shown on sheet 14 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A24 (north-west side of A46 east of Laceby) shown on sheet 14 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A25 (south-east side of Aylesby Road) shown on sheet 15 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A26 (north side of Beach Holt Lane/Nooking Lane west of Aylesby) shown on sheet 16 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A57 (north side of Nooking Lane west of Aylesby) shown on sheet 16 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A27 (south-east side of Wells Road) shown on sheet 17 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A28 (north-west side of Wells Road) shown on sheet 17 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A29 (east side of A1173) shown on sheet 18 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A30 (north-west side of A1173 at Stallingborough Grange Farm) shown on sheet 18 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A31 (south-east side of Keelby Road, north of Wood View) shown on sheet 19 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A32 (north-west side of Keelby Road north of Wood View) shown on sheet 19 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A33 (north-west side of Keelby Road north of Wood View) shown on sheet 19 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A34 (south-east side of Roxton Road south of railway) shown on sheet 20 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A35 (east side of Roxton Road north of railway) shown on sheet 20 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A36 (west side of Roxton Road north of railway) shown on sheet 20 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A39 (south-east side of B1210 Station Road south of A180) shown on sheet 22 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A40 (south side of B1210 Immingham Road) shown on sheet 23 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A41 (north side of B1210 Immingham Road) shown on sheet 23 of the onshore works plans and Work Nos. 7A and 7B
North East Lincolnshire Between point A42 (east side of Killingholme Road/Habrough Road, opposite Hill Farm) shown on sheet 23 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A43 (north side of Faulding Lane) shown on sheet 24 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A54 (west side of Habrough Road south of A160) shown on sheet 24 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A55 (east side of Habrough Road) shown on sheet 24 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A44 (residential access road north of A160, west of A160/Habrough Road roundabout) shown on sheet 24 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A45 (north-east side of Top Road) shown on sheet 25 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A46 (south side of Church Lane) shown on sheet 25 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A47 (north side of Church Lane) shown on sheet 25 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A48 (south side of Chase Hill Road west of Eastfield Road) shown on sheet 26 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A49 (north side of Chase Hill Road west of Eastfield Road) shown on sheet 26 of the onshore works plans and Work Nos. 7A and 7B
North Lincolnshire Between point A50 (Brick Lane, north side of Chase Hill Road) shown on sheet 26 of the onshore works plans and Work Nos. 7A and 7B

SCHEDULE 5 — Land in which only new rights, etc. may be acquired

(1) Number of land shown on land plans (2) Purpose for which rights may be acquired
1, 2, 3, 4, 19, 20, 21, 22, 23, 24, 26, 27, 28 To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 320-metre corridor within the Order land and to obtain access for such purposes
5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 25, 29, 30, 31, 32 To ground and lay anchor for vessels within the Order land
509, 510 To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within the Order land and to obtain access for such purposes
33, 511 To install, maintain and use an access track and to obtain access for such purposes
35 To install, retain, maintain and operate transition jointing bays for the connection of offshore cable circuits to onshore cable circuits and apparatus (and to impose requirements for their protection) within an up to 150-metre corridor within the Order land and to obtain access for such purposes
37, 38, 39, 67, 68, 69, 79, 80, 81, 83, 84, 85, 86, 87, 88, 92, 96, 97, 98, 99, 107, 113, 119, 123, 131, 132, 134, 135, 139, 140, 141, 147, 148, 149, 150, 151, 152, 153, 155, 161, 168, 169, 173, 175, 180, 183, 187, 188, 189, 190, 191, 192, 193, 194, 195, 196, 197, 198, 199, 200, 201, 202, 203, 204, 205, 206, 207, 208, 211, 215, 216, 217, 218, 219, 220, 221, 222, 223, 228, 232, 234, 248, 249, 250, 251, 252, 255, 256, 261, 262, 268, 275, 281, 282, 285, 289, 291, 293, 294, 295, 296, 297, 298, 299, 300, 307, 308, 309, 310, 311, 312, 313, 314, 317, 325, 327, 332, 333, 334, 338, 339, 342, 347, 352, 360, 361, 364, 365, 394, 403, 404, 411, 420, 421, 424, 426, 429, 430, 431, 432, 433, 434, 438, 439, 440, 445, 448, 449, 450, 451, 452, 453, 454, 459, 460, 461, 465, 466, 468, 471, 472, 476, 482, 486, 487, 488, 489, 490, 491, 492, 497, 499, 503 To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30-metre corridor within the Order land and to obtain access for such purposes
45, 46, 47, 48, 49 To install, maintain and use an access track and to obtain access for the purposes only of maintaining and operating the authorised project
273 To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30-metre corridor within the Order land and to obtain access for such purposes but not extending to breaking open the surface of the Order land
388, 437 To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30-metre corridor within the Order land
507, 519 To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within the Order land and to install, maintain and use an access track and to obtain access for such purposes
512, 521 To install, retain, maintain and operate services (and to impose requirements for their protection) within the Order land and to install, maintain and use an access road and to obtain access for such purposes

SCHEDULE 6 — Modification of compensation and compulsory purchase enactments for creation of new rights, etc.

Compensation enactments modified

1

The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right and in the case of the imposition of a restrictive covenant as they apply as respects compensation on the compulsory purchase of land and interests in land.

Land Compensation Act 1973 modified

2

  • (1) Without limiting paragraph 1, the Land Compensation Act 1973[^f00046] has effect subject to the modifications set out in sub-paragraphs (2) and (3).
  • (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4,—
  • (a) for “land is acquired or taken from”, substitute “a right or restrictive covenant over land is purchased from or imposed on the land of”; and
  • (b) for “acquired or taken from him”, substitute “over which the right is exercisable or the restrictive covenant enforceable”.
  • (3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5,—
  • (a) for “part” in paragraphs (a) and (b), substitute “a right over or restrictive covenant affecting land consisting”;
  • (b) for “severance”, substitute “right or restrictive covenant over or affecting the whole of the house, building or manufactory or of the house and the park or garden”;
  • (c) for “part proposed”, substitute “right or restrictive covenant proposed”; and
  • (d) for “part is”, substitute “right or restrictive covenant is”.

Compulsory Purchase Act 1965 modified

3

  • (1) The 1965 Act has effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right, or to the imposition under this Order of a restrictive covenant, as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land must be read (according to the requirements of the particular context) as referring to, or as including references to—
  • (a) the right acquired or to be acquired or the restrictive covenant imposed or to be imposed; or
  • (b) the land over which the right is or is to be exercisable or the restrictive covenant is or is to be enforceable.
  • (2) Without limiting sub-paragraph (1), Part 1 of the 1965 Act applies in relation to the compulsory acquisition under this Order of a right by the creation of a new right, or in relation to the imposition of a restrictive covenant, with the modifications specified in the following provisions of this Schedule.

4

For section 7 of the 1965 Act (measure of compensation in case of severance), substitute the following section—

(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the restrictive covenant but also to the damage (if any) to be sustained thereby by the owner of the land in relation to other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.

5

For section 8 of the 1965 Act (other provisions as to divided land), substitute the following section—

(8) (1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over, or a restrictive covenant affecting, land consisting of a house, building or manufactory or of a park or garden belonging to a house (the “relevant land”)— (a) a question of disputed compensation in respect of the purchase of the right or the imposition of the restrictive covenant would apart from this section fall to be determined by the Upper Tribunal (the “tribunal”); and (b) before the tribunal has determined that question the tribunal is satisfied that the person has an interest in the whole of the relevant land and is able and willing to sell that interest and— (i) where that land consists of a house, building or manufactory, that the right cannot be purchased or the restrictive covenant imposed without material detriment to that land; or (ii) where that land consists of such a park or garden, that the right cannot be purchased or the restrictive covenant imposed without seriously affecting the amenity or convenience of the house to which that land belongs, the Hornsea Two Offshore Wind Farm Order 2016 (the “Order”), in relation to that person, ceases to authorise the purchase of the right or the imposition of a restrictive covenant and be deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice is deemed to have been served in respect of that interest on such date as the tribunal directs. (2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) must be determined by the tribunal. (3) Where, in consequence of a determination of the tribunal that it is satisfied as mentioned in subsection (1), the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of 6 weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice.

6

The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—

  • (a) section 9(4) (refusal to convey, failure to make title, etc.);
  • (b) paragraph 10(3) of Schedule 1 (persons without power to sell their interests);
  • (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
  • (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),

are modified so as to secure that, as against persons with interests in the land that are expressed to be overridden by the deed, the right that is to be compulsorily acquired or the restrictive covenant that is to be imposed is vested absolutely in the acquiring authority.

7

Section 11 of the 1965 Act (powers of entry) is modified so as to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right or restrictive covenant, it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this purpose to have been created on the date of service of the notice); and sections 12 (unauthorised entry) and 13 (refusal to give possession to acquiring authority) of the 1965 Act[^f00047] are modified correspondingly.

8

Section 20 of the 1965 Act[^f00048] (tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.

9

Section 22 of the 1965 Act (interests omitted from purchase) is modified so as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired or to enforce the restrictive covenant imposed, subject to compliance with that section as respects compensation.

SCHEDULE 7 — Land of which temporary possession may be taken

PART 1 — Authorised project

(1) Area (2) Number of land shown on land plans (3) Purpose for which temporary possession may be taken (4) Relevant part of authorised project
In the County of Lincolnshire, East Lindsey District 36 Worksite and access for the construction and carrying out of the authorised project Work Nos. 5A, 5B, 6A, 6B, 7A and 7B
In the County of Lincolnshire, East Lindsey District 40, 41, 43, 44, 70, 71, 77, 93, 94, 100, 101, 102, 103, 104, 105, 106, 108, 109, 118, 124, 125, 126, 130, 137, 138, 154, 157, 158, 179, 184, 185 Worksite and access for the construction and carrying out of the authorised project Work Nos. 7A and 7B
In the County of Lincolnshire, East Lindsey District 34, 50, 53, 54, 56, 57, 58, 59, 60, 61, 62, 63, 64, 65, 66, 73, 74, 76, 78, 89, 90, 91, 110, 111, 112, 114, 115, 116, 117, 120, 121, 122, 127, 128, 129, 142, 143, 156, 159, 160, 162, 164, 165, 166, 167, 170, 171, 177, 178, 181, 182 Laying and use of temporary vehicular access track Work Nos. 7A and 7B
In the County of Lincolnshire, East Lindsey District 172, 174, 176 Laying of temporary public footpaths and bridleways Work Nos. 7A and 7B
In the County of North East Lincolnshire 213, 214, 224, 226, 229, 230, 245, 246, 247, 257, 258, 259, 277, 278, 280, 283, 284, 287, 288, 301, 302, 318, 319, 322, 324, 330, 331, 335, 336, 345, 346, 350, 351, 353, 356, 359, 362, 363, 372, 374, 392, 393, 395, 397, 401, 402, 405, 406, 407, 408, 412, 414, 419 Worksite and access for the construction and carrying out of the authorised project Work Nos. 7A and 7B
In the County of North East Lincolnshire 209, 210, 212, 231, 239, 241, 242, 264, 265, 266, 267, 269, 270, 271, 272, 274, 315, 316, 320, 337, 340, 341, 343, 355, 368, 370, 371, 375, 376, 377, 379, 381, 416, 418 Laying and use of temporary vehicular access track Work Nos. 7A and 7B
In the County of North East Lincolnshire 244, 290, 292, 326, 329 Laying of temporary public footpaths and bridleways Work Nos. 7A and 7B
In the County of North Lincolnshire 422, 423, 425, 427, 435, 436, 441, 442, 443, 444, 446, 455, 456, 458, 462, 463, 467, 469, 470, 473, 474, 477, 478, 479, 483, 484, 493, 496, 498 Worksite and access for the construction and carrying out of the authorised project Work Nos. 7A and 7B
In the County of North Lincolnshire 513, 514, 515, 520, 522 Laying and use of temporary vehicular access track Work Nos. 8A, 8B, 9A, 9B and 10
In the County of North Lincolnshire 502, 504, 505 Worksite and access for the construction and carrying out of the authorised project Work Nos. 7A, 7B, 8A, 8B, 9A and 9B
In the County of North Lincolnshire 508, 517, 518 Worksite and access for the construction and carrying out of the authorised project Work Nos. 8A, 8B, 9A and 9B

PART 2 — Compensation compounds

(1) Area (2) Number of land shown on land plans (3) Purpose for which temporary possession may be taken
In the County of Lincolnshire, East Lindsey District 72, 95, 136, 186 Compensation compound in respect of worksite and access
In the County of Lincolnshire, East Lindsey District 73, 185 Compensation compound access in respect of vehicular access track to and from a compensation compound
In the County of North East Lincolnshire 225, 233, 235, 243, 260, 276, 279, 286, 321, 328, 344, 348, 349, 354, 373, 396, 398, 409, 410, 413 Compensation compound in respect of worksite and access
In the County of North East Lincolnshire 239, 241, 242, 263, 293, 294, 296, 297, 355, 399, 400 Compensation compound access in respect of vehicular access track to and from a compensation compound
In the County of North Lincolnshire 428, 447, 457, 464, 475, 485, 494, 495, 501 Compensation compound in respect of worksite and access

PART 3 — Authorised project: access

(1) Area (2) Number of land shown on land plans
In the County of Lincolnshire, East Lindsey District 42, 51, 52, 55, 75, 82, 133, 144, 145, 146, 163
In the County of North East Lincolnshire 236, 237, 238, 240, 253, 254, 303, 304, 305, 306, 323, 357, 358, 366, 367, 369, 378, 380, 415, 417
In the County of North Lincolnshire 480, 481, 516

PART 4 — Compensation compounds: access

(1) Area (2) Number of land shown on land plans
In the County of North East Lincolnshire 240

SCHEDULE 8 — Marine Licence A1: Project A – Generation Assets

PART 1 — Licensed activities

Interpretation

1

  • (1) In this licence—
  • “2008 Act” means the Planning Act 2008;
  • “2009 Act” means the Marine and Coastal Access Act 2009;
  • “ancillary works” means the ancillary works described in clause 2 of Part 1 of this licence that are not development within the meaning of section 32 of the 2008 Act;
  • “Annex 1 habitat” means a habitat set out in Annex 1 to Council Directive 92/43/EEC of 21st May 1992 on the conservation of natural habitats and of wild fauna and flora;
  • “authorised deposits” means the substances and articles specified in clause 2(3) of Part 1 of this licence;
  • “authorised development” means the development described in Part 1 of Schedule 1 to the Order that is development within the meaning of section 32 of the 2008 Act;
  • “authorised project” means the authorised development and the ancillary works authorised by the Order;
  • “authorised scheme” means Work No. 1A described in clause 2 of Part 1 of this licence;
  • “commence” means the first carrying out of any part of the licensed activities, except for pre-construction surveys and monitoring; and “commencement” must be construed accordingly;
  • “Condition” means a condition set out in Part 2 of this licence;
  • “construction vessel” means any vessel involved in the course of or used for the construction and/or maintenance of the authorised project;
  • “debris” means items or equipment of a significant size left on the seabed being lost from survey or construction vessels or the structures comprised within the authorised scheme;
  • “EIA Regulations” means the Infrastructure Planning (Environmental Impact Assessment) Regulations 2009;
  • “electrical circuit” means a number of electrical conductors necessary to transmit electricity between 2 points within the authorised project, comprising—in the case of HVAC transmission, 3 conductors which may be bundled as 1 cable; andin the case of HVDC transmission 2 conductors, which may be attached together or take the form of single cables,and the electrical circuit may include 1 or more auxiliary cables (normally fibre-optic cables) for the purpose of control, monitoring, protection or general communications;
  • “enforcement officer” means a person authorised to carry out enforcement duties under Chapter 3 of Part 4 of the 2009 Act;
  • “environmental statement” means the document certified as the environmental statement by the Secretary of State under article 40 of the Order;
  • “gravity base foundation” means—a structure principally of concrete or steel (or both) that rests on the seabed due to its own weight and that of added ballast or to the weight of water above it and may include associated equipment including suction piles, J-tubes and access platforms; ora structure principally of concrete or steel (or both) consisting of a platform supported on 2 pontoons to which the platform is connected by columns which may be connected by braces;
  • “HVAC” means high voltage alternating current;
  • “HVDC” means high voltage direct current;
  • “in-principle monitoring plan” means the document certified as the in-principle monitoring plan by the Secretary of State under article 40 of the Order;
  • “intra-array electrical circuits” means the circuits described in clause 2(2)(b) of Part 1 of this licence;
  • “jacket foundation” means a lattice construction comprising tubular members and joints fixed to the seabed with piles (either driven/drilled piles or suction piles) which will include platforms and J-tubes and may include braced monopiles and a transition piece;
  • “Kingfisher Fortnightly Bulletin” means the bulletin published by the Humber Seafood Institute or such other alternative publication approved in writing by the MMO;
  • “LAT” means lowest astronomical tide;
  • “licensed activities” means the activities specified in Part 1 of this licence;
  • “maintain”, unless otherwise provided for, includes inspect, repair, adjust, alter, remove, reconstruct and replace any of the authorised development; and any derivative of “maintain” must be construed accordingly;
  • “Marine Noise Registry” means the online database maintained by the Joint Nature Conservation Committee on behalf of the Department for Environment, Food and Rural Affairs that records the spatial and temporal distribution of impulsive noise-generating activities in United Kingdom seas in order that they can be analysed to determine whether they may potentially compromise the achievement of good environmental status;
  • “MCA” means the Maritime and Coastguard Agency;
  • “MHWS” (mean high water springs) means the highest level which spring tides reach on average over a period of time;
  • “MMO” means the Marine Management Organisation;
  • “monopile foundation” means a foundation comprising a large diameter steel or concrete tube or pile driven vertically into the seabed, J-tubes and platforms and may include external structural devices such as bracing members or steel anchor wires and a transition piece;
  • “notice to mariners” includes any notice to mariners which may be issued by Admiralty, Trinity House, Queen’s harbourmasters, government departments and harbour and pilotage authorities;
  • “offshore accommodation platform” means a platform housing or incorporating temporary accommodation, landing ports for vessels and helicopters, standby electricity generation equipment, marking and lighting and other equipment facilities to assist in the co-ordination of marine activities related to the authorised scheme;
  • “offshore HVAC collector substation” means a structure serving as a collection point for the intra-array electrical circuits and containing equipment for the purpose of transforming the electricity generated at the wind turbine generators to a higher voltage; it may also include a helicopter platform;
  • “offshore HVDC converter substation” means a structure that contains equipment to convert HVAC electricity to HVDC electricity; it may also include a helicopter platform;
  • “Order” means the Hornsea Two Offshore Wind Farm Order 2016;
  • “Order limits” means the limits shown on the works plans within which the authorised project may be carried out;
  • “suction pile” means a large diameter steel cylinder that is fixed to the base of the foundation, partially penetrates the seabed and remains in place using its weight and hydrostatic pressure differential;
  • “survey vessel” means a vessel licensed to carry out environmental or engineering surveys;
  • “Trinity House” means the Corporation of Trinity House of Deptford Strond;
  • “UK Hydrographic Office” means the Hydrographic Office of the Ministry of Defence or any replacement body or successor to its functions;
  • “undertaker” means Optimus Wind Limited (company number 07883284) or, to the extent that the benefit of the provisions of the Order and related statutory rights in relation to Work No. 1A and such associated development or ancillary works has been transferred under article 35 of the Order to another person, that other person;
  • “vessel” means every description of vessel, however propelled or moved, and includes a non-displacement craft, a personal watercraft, a seaplane on the surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any other thing constructed or adapted for movement through, in, on or over water that is at the time in, on or over water;
  • “wind farm area” means the area within the limits of deviation for Work No. 1A whose co-ordinates are set out in Part 1 of Schedule 1 to the Order and shown on the works plans;
  • “wind turbine generator” means a structure comprising any or all of a tower, rotor, blades, nacelle and ancillary electrical and other equipment or structures, which may include lighting and a helicopter platform, fixed to a foundation;
  • “working day” means any day other than a Saturday, Sunday or public holiday in England and Wales;
  • “Work No. 1A” means an offshore wind generating station within the wind farm area and described as Work No. 1A in clause 2 of Part 1 of this licence;
  • “Work No. 1B” means an offshore wind generating station within the wind farm area and described as Work No. 1B in Part 1 of Schedule 1 to the Order;

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.