The Hornsea Two Offshore Wind Farm Order 2016

Type Statutory-Instrument
Publication 2016-08-16
Last updated 2018-05-08
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (1) Where the authorised development constructed seaward of MHWS or any part of it is abandoned or allowed to fall into decay, the Secretary of State may, following consultation with the undertaker, by notice in writing require the undertaker at its own expense—
  • (a) to repair and restore the authorised development or any part of it;
  • (b) to remove the authorised development or any part of it; and
  • (c) to restore the site to a safe and appropriate condition within an area and to such an extent as may be specified in the notice.
  • (2) If the undertaker fails to comply in any respect with a notice served under this article within the period of 30 days beginning with the date of service of the notice—
  • (a) the Secretary of State may take whatever steps the Secretary of State considers appropriate to achieve the result required by the notice;
  • (b) any expenditure incurred by the Secretary of State in doing so is recoverable from the undertaker.
  • (3) Nothing in this article limits the Secretary of State’s powers under Chapter 3 of Part 2 of the 2004 Act (decommissioning of offshore installations).

Transfer of benefit of Order

35

  • (1) Except as otherwise provided in this Order, the provisions of this Order have effect solely for the benefit of the undertaker.
  • (2) The undertaker may—
  • (a) transfer to another person (the “transferee”) any or all of the benefit of the provisions of this Order (including the deemed marine licences) and such related statutory rights as may be agreed between the undertaker and the transferee; or
  • (b) grant to another person (the “lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order (including the deemed marine licences) and such related statutory rights as may be agreed between the undertaker and the lessee.
  • (3) The consent of the Secretary of State is required for a transfer or grant under paragraph (2), except for—
  • (a) a transfer or grant of the benefit of any of the provisions (and any related statutory rights) relating to Work No. 1A or 1B from one undertaker to the other; or
  • (b) a transfer or grant of any of the provisions (and any related statutory rights) relating to Work Nos. 2A, 2B, 3A, 3B, 4A, 4B, 5A, 5B, 6A, 6B, 7A, 7B, 8A, 8B, 9A, 9B or 10 to a person who holds a licence under section 6 of the 1989 Act.
  • (4) Where the consent of the Secretary of State is required for a transfer or grant under paragraph (1), the Secretary of State must consult the MMO before giving consent if the proposed transfer or grant is relevant to the exercise of functions within the MMO’s jurisdiction.
  • (5) Where there is a transfer or grant under paragraph (2)—
  • (a) the exercise by the transferee or, as the case may be, by the lessee of any benefit or right conferred by the transfer or grant (the “transferred benefit”) is subject to the same restrictions, liabilities and obligations as would apply under this Order if the benefit or right were exercised by the undertaker; and
  • (b) the transferred benefit resides exclusively with the transferee or lessee, and any breach of a restriction or an obligation with respect to the transferred benefit is not ... enforceable against the person making the transfer or grant, except for a breach occurring before the date of transfer.
  • (6) At least 5 days before a transfer or grant under paragraph (2) takes effect, the undertaker must give notice in writing—
  • (a) to the Secretary of State; and
  • (b) if the transfer or grant is relevant to the exercise of functions within the MMO’s or the local planning authority’s jurisdiction, to the MMO or the local planning authority (or to both).
  • (7) The notice must—
  • (a) state—
  • (i) the name and contact details of the transferee or lessee;
  • (ii) the date on which the transfer or grant takes effect;
  • (iii) the provisions transferred or granted; and
  • (iv) the restrictions, liabilities and obligations that, in accordance with paragraph (5)(a), apply to the transferee or lessee;
  • (b) be accompanied by—
  • (i) where relevant, a plan showing the Works or areas to which the transfer or grant relates;
  • (ii) where the Secretary of State’s consent is needed for the transfer or grant, a copy of the consent; and
  • (iii) a copy of the document effecting the transfer or grant signed by the person making the transfer or grant and the transferee or lessee; and
  • (c) be signed by the person making the transfer or grant and the transferee or lessee.
  • (8) Where there is a transfer or grant under paragraph (2), references in this Order to the undertaker, except in paragraph (5), include references to the transferee or lessee.

Deemed marine licences under Marine and Coastal Access Act 2009

36

The marine licences set out in Schedules 8 to 11 are deemed to have been issued under Part 4 of the 2009 Act (marine licensing) for the licensed activities set out in Part 1, and subject to the Conditions set out in Part 2, of each licence.

Saving for Trinity House

37

Nothing in this Order prejudices or derogates from any of the rights, duties or privileges of Trinity House.

Crown rights

38

  • (1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and, in particular, nothing in this Order authorises the undertaker or any licensee to take, use, enter on or in any manner interfere with any land or rights of any description (including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary)—
  • (a) belonging to Her Majesty in right of the Crown and forming part of the Crown Estate without the consent in writing of the Crown Estate Commissioners;
  • (b) belonging to Her Majesty in right of the Crown and not forming part of the Crown Estate without the consent in writing of the government department having the management of that land; or
  • (c) belonging to a government department or held in trust for Her Majesty for the purposes of a government department without the consent in writing of that government department.
  • (2) Paragraph (1) does not apply to the exercise of any right under this Order compulsorily to acquire an interest in any land that is Crown land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown.
  • (3) A consent under paragraph (1)—
  • (a) may be given unconditionally or subject to terms and conditions;
  • (b) is deemed to have been given in writing where it is sent electronically.

Protective provisions

39

Schedule 12 (protective provisions) has effect.

Certification of plans, etc.

40

  • (1) The undertaker must, as soon as practicable after this Order is made, submit to the Secretary of State copies of the documents listed in Schedule 13 (documents to be certified) for certification that they are true copies of the documents referred to in this Order.
  • (2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.

Arbitration

41

Any difference under any provision of this Order, unless otherwise provided for, must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.

SCHEDULE 1 — Authorised project

PART 1 — Authorised development

1

The authorised development includes—

  • (a) the nationally significant infrastructure project (as defined in sections 14 and 15 of the 2008 Act) described in paragraph 2; and
  • (b) the associated development (within the meaning of section 115(2) of the 2008 Act) described in paragraphs 3 and 4.

2

  • (1) The nationally significant infrastructure project comprises up to 2 offshore wind generating stations with a combined gross electrical output capacity of up to 1,800 megawatts as follows—

3

  • (1) The associated development includes the following Works—

4

The associated development includes such further development as may be necessary or expedient in connection with each of the Works within the Order limits and is within the scope of the environmental impact assessment recorded in the environmental statement including—

  • (a) scour protection around the foundations of the offshore structures;
  • (b) dredging;
  • (c) cable protection measures such as rock placement and the placement of concrete mattresses and frond mattresses;
  • (d) the disposal of seabed sediments produced during construction drilling and seabed preparation for the installation of the foundations of the offshore structures or during seabed preparation for cable laying;
  • (e) works to alter the position of apparatus, including mains, sewers, drains and cables;
  • (f) works to alter the course of, or otherwise interfere with, non-navigable rivers, streams or watercourses;
  • (g) landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised project;
  • (h) works for the benefit or protection of land affected by the authorised project;
  • (i) working sites in connection with the construction of the authorised project;
  • (j) compensation compounds;
  • (k) works to secure means of access;
  • (l) works to construct surface water drainage systems;
  • (m) in connection with Work Nos. 8A and 8B, private roads and hardstanding for parking;
  • (n) link or earthing boxes associated with Work Nos. 6A and 6B;
  • (o) jointing pits (including link or earthing boxes) associated with Work Nos. 7A and 7B;
  • (p) a temporary haul road and temporary access track, both alongside and used for the purpose of constructing Work Nos. 7A and 7B;
  • (q) works to enable utility services to be run from Chase Hill Road to Work Nos. 8A and 8B; and
  • (r) such other works and apparatus, plant and machinery of whatever nature as may be necessary or expedient for the purposes of or in connection with the construction of the authorised project.

PART 2 — Ancillary works

Works and operations within the Order limits comprising—

  • (a) temporary anchorage of vessels; and
  • (b) buoys, beacons, fenders and other navigational warning or ship impact protection works.

PART 3 — Requirements

Time limits

1

The authorised development must be commenced on or before 6th September 2021.

Detailed design parameters

2

  • (1) No wind turbine generator forming part of Work No. 1A or 1B may—
  • (a) be more than 151 metres from LAT to the turbine hub;
  • (b) exceed a height of 276 metres from LAT to the upper tip of the vertical blade;
  • (c) exceed a rotor diameter of 241.03 metres;
  • (d) be less than 34.97 metres from LAT to the lowest point of the rotating blade;
  • (e) be less than 810 metres from the nearest wind turbine generator in all directions.
  • (2) In this Requirement, references to the location of a wind turbine generator are references to the centre point of the turbine.
  • (3) No offshore accommodation platform forming part of Work No. 1A or 1B may—
  • (a) exceed 64 metres in height above LAT;
  • (b) have a platform that at its greatest extent exceeds 3,600 square metres in area or 60 metres in width.
  • (4) No offshore HVAC collector substation forming part of Work No. 2A or 2B may—
  • (a) exceed 64 metres in height above LAT;
  • (b) have a platform that at its greatest extent exceeds 6,300 square metres in area or 90 metres in width.
  • (5) No offshore HVDC converter substation forming part of Work No. 2A or 2B may—
  • (a) exceed 110 metres in height above LAT;
  • (b) have a platform that at its greatest extent exceeds 16,200 square metres in area or 180 metres in width.
  • (6) No offshore reactive compensation substation comprised in Work No. 3A or 3B may—
  • (a) exceed 64 metres in height above LAT; or
  • (b) have a platform that at its greatest extent exceeds 3,600 square metres in area or 60 metres in width.
  • (7) The diameter of the electrical cables comprising the electrical circuits must not exceed—
  • (a) within Work Nos. 1A and 1B, 170 millimetres;
  • (b) within Work Nos. 2A and 2B, 300 millimetres;
  • (c) within Work Nos. 4A, 4B, 5A and 5B—
  • (i) 190 millimetres, where the mode of transmission is HVDC; and
  • (ii) 300 millimetres, where the mode of transmission is HVAC.
  • (8) The combined total length of the connections in the form of electrical circuits between the structures comprised in Work Nos. 1A and 1B must not exceed 685 kilometres.
  • (9) The combined total length of the connections in the form of electrical circuits between the structures comprised in Work Nos. 2A and 2B must not exceed 300 kilometres.
  • (10) The combined total length of the electrical circuits comprised in Work Nos. 4A, 4B, 5A and 5B seaward of MHWS must not exceed 1,200 kilometres.
  • (11) The combined total area of cable protection for the electrical circuits comprising Work Nos. 1A and 1B must not exceed 1,246,700 square metres.
  • (12) The combined total area of cable protection for the electrical circuits comprising Work Nos. 2A and 2B must not exceed 546,000 square metres.
  • (13) The combined total area of cable protection for the electrical circuits comprising Work Nos. 4A and 4B located outside the Humber Estuary Special Area of Conservation must not exceed 2,055,200 square metres.
  • (14) The combined total area of cable protection for the electrical circuits comprising Work Nos. 4A and 4B located within the Humber Estuary Special Area of Conservation must not exceed 44,800 square metres.
  • (15) The combined total volume of cable protection for the electrical circuits comprising Work Nos. 1A and 1B must not exceed 712,400 cubic metres.
  • (16) The combined total volume of cable protection for the electrical circuits comprising Work Nos. 2A and 2B must not exceed 312,000 cubic metres.
  • (17) The combined total volume of cable protection for the electrical circuits comprising Work Nos. 4A and 4B located outside the Humber Estuary Special Area of Conservation must not exceed 1,174,400 cubic metres.
  • (18) The combined total volume of cable protection for the electrical circuits comprising Work Nos. 4A and 4B located within the Humber Estuary Special Area of Conservation must not exceed 25,600 cubic metres.
  • (19) The electrical circuits comprised in Work Nos. 1A, 1B, 2A, 2B, 4A and 4B must be installed by use of, or a combination of, ploughing, trenching, jetting, rock-cutting, dredging, surface laying with post-lay burial and, where ground conditions make burial impracticable, by surface laying.
  • (20) The electrical circuits comprised in Work Nos. 5A and 5B must be installed by use of, or a combination of, a trenchless technique, ploughing, trenching and jetting, with the exception that, where the electrical circuits comprised in Work Nos. 5A and 5B cross under the existing sea wall, they must be installed using a trenchless technique.
  • (21) The combined total area in which the underground electrical circuit transition joint bays comprised in Work Nos. 6A and 6B may be contained must not exceed 2,000 square metres, and no underground electrical circuit transition joint bay within that area may individually exceed 25 metres in length or 10 metres in width.
  • (22) The diameter of the cables within Work Nos. 7A, 7B, 9A and 9B must not exceed 180 millimetres.
  • (23) No main building forming part of Work No. 8A or 8B may—
  • (a) where the mode of transmission is HVDC, exceed—
  • (i) 40 metres in height;
  • (ii) 69.5 metres in width;
  • (iii) 135 metres in length; or
  • (b) where the mode of transmission is HVAC, exceed—
  • (i) 15 metres in height;
  • (ii) 18.5 metres in width;
  • (iii) 82.5 metres in length.
  • (24) The combined total area of the site of Work Nos. 8A and 8B must not exceed 49,326 square metres, excluding any area of land required for landscaping and mitigation.
  • (25) The electrical circuits comprised in Work Nos. 7A and 7B must be installed by use of a trenchless technique where crossing under a main river.
  • (26) The width of the corridor occupied by the connection comprised in Work Nos. 7A and 7B following completion of construction of those works must not exceed 30 metres, except where those works overlap with Work No. 5A, 5B, 6A or 6B in which case the width of the corridor occupied by the connection comprising Work Nos. 7A and 7B must not exceed 150 metres.

Colour and lighting

3

Except as otherwise required by Trinity House under Condition 4 of each of the deemed marine licences, the undertaker must exhibit such lights, with such shape, colour and character as required by the Air Navigation Order 200942 or as otherwise directed by the Civil Aviation Authority or the Secretary of State for Defence.

Foundation methods

4

  • (1) The undertaker must in fixing to the seabed any structures comprised in Work Nos. 1A, 1B, 2A, 2B, 3A and 3B use one of the following methods—
  • (a) monopile foundations;
  • (b) jacket foundations supported by piles; or
  • (c) gravity base foundations.
  • (2) The undertaker must not use the monopile foundation method or any other method that includes braced monopiles to fix to the seabed any offshore HVDC converter substation.
  • (3) The following parameters apply in respect of the foundation methods used to fix wind turbine generators to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 2,827 square metres;
  • (ii) the number of piles per jacket must not exceed 12;
  • (iii) the diameter of each pile must not exceed 6 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and scour protection for each individual structure must not exceed 12,596 square metres;
  • (ii) the number of piles per jacket must not exceed 4;
  • (iii) the diameter of each pile must not exceed 21.1 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 7,543 square metres;
  • (ii) the seabed levelling diameter must not exceed 78 metres;
  • (iii) the cone diameter must not exceed 58 metres at its base.
  • (4) The following parameters apply in respect of the foundation methods used to fix offshore accommodation platforms to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,414 square metres;
  • (ii) the number of piles must not exceed 8;
  • (iii) the diameter of each pile must not exceed 3 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the number of piles per jacket must not exceed 4;
  • (iii) the diameter of each pile must not exceed 15 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the seabed levelling diameter must not exceed 70 metres;
  • (iii) the cone diameter must not exceed 50 metres at its base.
  • (5) The following parameters apply in respect of the foundation methods used to fix offshore HVAC collector substations to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,924 square metres;
  • (ii) the number of piles per jacket must not exceed 8;
  • (iii) the diameter of each pile must not exceed 3.5 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 12,723 square metres;
  • (ii) the number of piles per jacket must not exceed 8;
  • (iii) the diameter of each pile must not exceed 15 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the seabed levelling diameter must not exceed 70 metres;
  • (iii) the cone diameter must not exceed 50 metres at its base.
  • (6) The following parameters apply in respect of the foundation methods used to fix offshore HVDC converter substations to the seabed—
  • (a) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 17,318 square metres;
  • (ii) the number of jacket foundations per topside must not exceed 4;
  • (iii) the number of piles per topside must not exceed 72;
  • (iv) the number of piles per jacket must not exceed 18;
  • (v) the diameter of each pile must not exceed 3.5 metres;
  • (b) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 50,894 square metres;
  • (ii) the number of jacket foundations per topside must not exceed 4;
  • (iii) the number of piles per topside must not exceed 32;
  • (iv) the number of piles per jacket must not exceed 8;
  • (v) the diameter of each pile must not exceed 15 metres;
  • (c) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 27,300 square metres;
  • (ii) the number of pontoons for each individual structure must not exceed 3;
  • (iii) the pontoons must not exceed 170 metres in length or 35 metres in width.
  • (7) The following parameters apply in respect of the foundation methods used to fix the offshore reactive compensation substation to the seabed—
  • (a) where monopile foundations are used—
  • (i) the area occupied by the foundations and the scour protection must not exceed 1,963 square metres;
  • (ii) the diameter of each foundation must not exceed 10 metres;
  • (b) where jacket foundations (driven/drilled piles) are used—
  • (i) the area occupied by the foundations and the scour protection must not exceed 1,414 square metres;
  • (ii) the number of piles per jacket must not exceed 8;
  • (iii) the diameter of each pile must not exceed 3 metres;
  • (c) where jacket foundations (suction piles) are used—
  • (i) the area occupied by the foundations and the scour protection must not exceed 6,362 square metres;
  • (ii) the number of piles per jacket must not exceed 4;
  • (iii) the diameter of each pile must not exceed 15 metres;
  • (d) where gravity base foundations are used—
  • (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 square metres;
  • (ii) the seabed levelling diameter must not exceed 70 metres;
  • (iii) the cone diameter must not exceed 50 metres at its base.
  • (8) The combined total volume of scour protection for the wind turbine generators and the offshore accommodation platforms forming part of the authorised development must not exceed 4,761,555 cubic metres.

Archaeology landward of mean low water springs

5

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until a written scheme for the investigation of areas of archaeological interest landward of MLWS has been submitted to and approved by the local planning authority.
  • (2) The scheme must identify areas where field work or a watching brief (or both) are required and the measures to be taken to evaluate, protect, record or preserve any significant archaeological remains that may be found.
  • (3) Any archaeological works or watching brief must be carried out—
  • (a) in accordance with the approved scheme;
  • (b) by a suitably qualified person or body approved by the local planning authority.
  • (4) Staged reports of the measures taken to evaluate, protect, record or preserve any significant archaeological remains that are found must be submitted to and approved by the local planning authority before the commencement of any works that would affect those remains.

Ecological management plan landward of mean low water springs

6

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until an ecological management plan relating to the land landward of MLWS based on the outline ecological management plan and reflecting the survey results and ecological mitigation measures included in the environmental statement has been submitted to and approved by the local planning authority in consultation with Natural England, the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.
  • (2) The ecological management plan must include an implementation timetable and must be carried out as approved.
  • (3) The ecological management plan must be submitted for approval at least 4 months before the intended start of construction unless otherwise agreed by the local planning authority in consultation with Natural England.

Code of construction practice

7

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until a code of construction practice relating to the Works landward of MLWS based on the outline code of construction practice has been submitted to and approved by the local planning authority.
  • (2) Before giving approval in the case of a construction traffic management plan referred to in sub-paragraph (3)(e) and a travel plan referred to in sub-paragraph (3)(l), the local planning authority must consult the highway authority and Highways England.
  • (3) The code of construction practice must include—
  • (a) an external lighting scheme for the construction phase;
  • (b) construction noise and vibration monitoring and management measures;
  • (c) air quality and dust monitoring and management measures during construction;
  • (d) a site waste management plan detailing sustainable site waste management measures;
  • (e) a construction traffic management plan;
  • (f) measures to prevent and control spillage of oil, chemicals and other potentially harmful liquids;
  • (g) details of the storage of materials during construction;
  • (h) measures for the protection of surface and ground water during construction;
  • (i) a communication plan;
  • (j) a health and safety plan, including details of how health and safety risks are to be identified and managed during construction;
  • (k) details of screening and fencing to be installed during construction; and
  • (l) a travel plan for the construction workforce to include details of—
  • (i) expected means of travel to and from the construction sites;
  • (ii) numbers of construction staff, working hours and modal split;
  • (iii) details of the number of car parking spaces to be provided on sites and if appropriate a car park management plan;
  • (iv) specification of measures to encourage sustainable travel to and from the construction site for construction staff;
  • (v) responsibility and timescales for implementing proposed measures;
  • (vi) targets for vehicle trips and modal splits;
  • (vii) formal monitoring regime for those targets; and
  • (viii) details of mess or canteen facilities for staff.
  • (4) All construction works must be undertaken in accordance with the approved code.

Landscape scheme

8

  • (1) No part of the authorised development landward of MLWS may be commenced within the area of a local planning authority until a landscape scheme has been submitted to and approved by the local planning authority.
  • (2) The landscape scheme must include the provisions of the outline landscape scheme and management plan, subject to any variation approved by the local planning authority, and, in addition details of—
  • (a) cultivation, importing of materials and other operations to ensure plant establishment;
  • (b) proposed finished ground levels;
  • (c) hard surfacing materials; and
  • (d) minor structures, refuse or other storage units, signs and lighting.

Implementation and maintenance of landscaping

9

  • (1) Landscape works must be carried out in accordance with the relevant landscape scheme approved under Requirement 8.
  • (2) Any tree or shrub planted as part of an approved landscape scheme that within a period of 5 years after planting, is removed, dies or becomes, in the opinion of the local planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless alternative timing or a different specimen is otherwise approved by the local planning authority.

Offshore decommissioning

10

No part of the authorised development seaward of MLWS may be commenced until a decommissioning programme in compliance with any notice served on the undertaker by the Secretary of State under section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval in relation to that part.

Highway accesses

11

  • (1) No permanent or temporary means of access to a highway to be used by vehicular traffic or any alteration to an existing means of access to a highway used by vehicular traffic may be commenced until details of the design and layout of such works have been submitted to and approved by the local planning authority in consultation with the highway authority.
  • (2) The highway accesses must be constructed in accordance with the approved details.

Contaminated land and groundwater scheme

12

  • (1) No part of the authorised development within the area of a local planning authority may be commenced until a scheme to deal with the contamination of any land (including groundwater) within the Order limits that is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to, and approved by, the local planning authority in consultation with the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.
  • (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the local planning authority, to identify the extent of any contamination and the remedial measures to be taken for that stage to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
  • (3) No remedial work constituting a material operation (as defined in section 155 of the 2008 Act) in respect of contamination of any land (including groundwater) within the Order limits may be carried out until the scheme has been approved.
  • (4) In carrying out the works for the authorised development, the undertaker must not conduct trenchless technique operations unless the scheme includes a hydrogeological risk assessment demonstrating that such operations are unlikely to cause an unacceptable risk to groundwater quality.
  • (5) Remediation must be carried out in accordance with the approved scheme.
  • (6) In this Requirement, “controlled waters” has the meaning given in Part 3 of the Water Resources Act 199143.

Surface water drainage scheme

13

  • (1) No part of any electrical transmission station may be commenced until a detailed surface water drainage scheme based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the electrical transmission station has been submitted to and approved by the local planning authority, in consultation with the drainage board concerned within the meaning of section 23 of the Land Drainage Act 1991.
  • (2) Construction of the electrical transmission station must be carried out in accordance with the approved scheme.

Colour and detailed design approval: electrical transmission stations

14

  • (1) Unless otherwise agreed by the local planning authority, the electrical transmission stations must be coloured using one or more of the following colours—
  • (a) bluebell (RAL Code 270 50 30);
  • (b) lilac (RAL Code 270 60 25);
  • (c) chalk blue (RAL Code 270 70 20);
  • (d) Baltic blue (RAL Code 270 80 15);
  • (e) white lilac (RAL Code 270 85 10);
  • (f) blue white (RAL Code 270 90 05).
  • (2) Despite sub-paragraph (1), construction of Work No. 8A must not commence until details of the layout, scale and external appearance of that Work have been submitted to and approved by the local planning authority.
  • (3) Despite sub-paragraph (1), construction of Work No. 8B must not commence until details of the layout, scale and external appearance of that work have been submitted to and approved by the local planning authority.
  • (4) The construction of Work Nos. 8A and 8B must be carried out in accordance with the approved details.

Access road within plots 45 to 49

15

  • (1) The undertaker must not use the access road along the crest of the sea defences within the plots numbered 45 to 49 on the land plans during the construction of Work Nos. 4A, 4B, 5A, 5B, 6A and 6B.
  • (2) Except in an emergency, the access road along the sea defences within the plots numbered 45 to 49 on the land plans must not be used by the undertaker following the construction of Work Nos. 4A, 4B, 5A, 5B, 6A and 6B until a scheme for the protection of the sea defences from use of the access road by the undertaker during the operation and maintenance of the authorised development has been submitted to and approved by the Environment Agency, such approval not to be unreasonably withheld or delayed.
  • (3) If the Environment Agency fails to notify the undertaker of its decision on whether to give approval within 2 months of receiving the scheme for approval, the Environment Agency is deemed to have given approval.
  • (4) The use of the access road must be in accordance with the approved scheme.

Port traffic management plan

16

  • (1) No part of the authorised development seaward of MLWS (excluding ducting and related works which are an integral part of works landward of MLWS) may be commenced until—
  • (a) a traffic management plan for the onshore port-related traffic to and from the selected base port or ports for construction or operation (or both) of that part of the authorised development has been submitted to and approved by the relevant planning authority in consultation with the relevant highway authority; or
  • (b) the relevant planning authority has confirmed, after consultation with the relevant highway authority, that no traffic management plan is required for that part of the authorised development.
  • (2) All traffic management plans must be implemented as approved at all times specified within the relevant traffic management plan during the construction and operation of the authorised development.
  • (3) In this Requirement—
  • “relevant highway authority” means the highway authority in whose area the selected base port is located;
  • “relevant planning authority” means the local planning authority in whose area the selected base port is located;
  • “selected base port” means a port situated in England and/or Wales and used by management personnel for the construction or ongoing operational management of the authorised development (or both).

Employment and skills plan

17

  • (1) No part of the authorised development may be commenced until an employment and skills plan based on the outline employment and skills plan has been submitted to and approved by North Lincolnshire Council in consultation with North East Lincolnshire Council, East Lindsey District Council and the Humber Local Enterprise Partnership.
  • (2) The plan must include—
  • (a) proposals for the provision of information to the Humber Local Enterprise Partnership on the employment and supply chain opportunities associated with the construction, operation and maintenance of the authorised development including details of the core qualifications and skillsets required to access those opportunities;
  • (b) proposals for local advertising of employment and supply chain opportunities during the construction of the authorised development;
  • (c) proposals for the undertaker to provide outreach employment presentations during the period of construction of the authorised development at appropriate times and locations; and
  • (d) proposals for local advertising of employment and supply chain opportunities during the operation of the authorised development.
  • (3) The approved employment and skills plan must be implemented and maintained during the construction and operation of the authorised development.
  • (4) In this Requirement, “Humber Local Enterprise Partnership” means the local enterprise partnership established in June 2011 with the objective of promoting and developing the natural economic area surrounding the Humber estuary.

Offshore co-operation

18

  • (1) Before submitting the pre-construction plans and documentation required to be submitted to the MMO for approval under Condition 8 of each of the deemed marine licences, the undertaker in respect of the relevant licence must provide a copy of the plans and documentation to the other undertaker under this Order.
  • (2) The other undertaker must provide any comments on the plans and documentation to the first undertaker within 14 days of receipt.
  • (3) Each undertaker must participate in liaison meetings with the other undertaker as requested from time to time by the MMO in writing in advance; and the meetings must be chaired by the MMO and must consider such matters as are determined by the MMO relating to the efficient operation of a deemed marine licence where it has an impact on the efficient operation of any other deemed marine licence.

Compensation compounds

19

  • (1) The undertaker may exercise the powers conferred by this Order in relation to the compensation compounds shown coloured green on the compensation compounds plan only where—
  • (a) the undertaker exercises, or intends to exercise, the powers conferred by this Order in relation to the Order land shown hatched green on the compensation compounds plan; and
  • (b) sub-paragraph (4) applies.
  • (2) The undertaker may exercise the powers conferred by this Order only in relation to the compensation compound access coloured pink and labelled 14-A1c on the compensation compounds plan only where the undertaker exercises, or intends to exercise, the powers conferred by this Order in relation to the compensation compound shown coloured green and labelled 14-C3 on the compensation compounds plan in accordance with sub-paragraph (1).
  • (3) Where the undertaker exercises the powers conferred by this Order in relation to—
  • (a) the compensation compounds shown coloured green on the compensation compounds plan in accordance with sub-paragraph (1); or
  • (b) the compensation compound access coloured pink and labelled 14-A1c on the compensation compounds plan in accordance with sub-paragraph (2),

those powers may be exercised only for the benefit of the Hornsea Project One undertaker in connection with the carrying out of works authorised by the Hornsea One Offshore Wind Farm Order 2014.

  • (4) This sub-paragraph applies where—
  • (a) the carrying out of works authorised by this Order in the Order land shown hatched green on the compensation compounds plan would overlap temporally with the carrying out of works authorised by the Hornsea One Offshore Wind Farm Order 2014 in that land; or
  • (b) works authorised by this Order in the Order land shown hatched green on the compensation compounds plan are carried out and completed before the works authorised by the Hornsea One Offshore Wind Farm Order 2014 in that land commence.

Onshore decommissioning plan

20

  • (1) Within 3 months of the cessation of commercial operation of the connection works, an onshore decommissioning plan must be submitted to the local planning authority for its approval.
  • (2) The decommissioning plan must be implemented as approved.

North Coates airfield

21

No part of the authorised development may be commenced within half a mile of the perimeter of the North Coates airfield until a plan to secure its safe operation during the construction and operation of the authorised development has been submitted to and approved by the Secretary of State following consultation with the operator of North Coates airfield and the Civil Aviation Authority.

Control of noise during operational phase

22

  • (1) The combined rating level (LAr,Tr) of the noise emitted during normal operation from the electrical transmission station, converter and associated plant, must not exceed 35 decibels at any residential property that has planning permission on 1st December 2014.
  • (2) The assessment must be carried out in accordance with BS 4142:2014 “Methods for rating and assessing industrial and commercial sound”44.

Onshore co-operation

23

  • (1) Before submitting any plan or document required to be submitted for approval under the Requirements, the undertaker in respect of the works to which the plan or document relates must provide a copy of the plan or document to the other undertaker under this Order.
  • (2) The other undertaker must provide any comments on the plan or document to the first undertaker within 14 days of receipt.
  • (3) On submission of any plan or document referred to in sub-paragraph (1) for approval, the undertaker in respect of the works to which the plan or document relates must also submit any comments received from the other undertaker under sub-paragraph (2) or a statement confirming that no such comments were received.
  • (4) Each undertaker must participate in liaison meetings with the other undertaker as requested from time to time by the local planning authority in writing in advance; and the meetings must be chaired by the local planning authority and must consider such matters as are determined by the local planning authority relating to the efficient construction and operation of the Project A works and the shared works above MLWS where they have an impact on the efficient construction and operation of the Project B works and the shared works above MLWS (and vice versa).

Intertidal access management plan

24

  • (1) No part of the authorised development within the intertidal area may be commenced until an intertidal access management plan setting out details of the access routes to the intertidal area, the methods for accessing the intertidal area, the expected number of vehicles that will be accessing the intertidal area and the expected number of vehicle trips to the intertidal area required in relation to that part of the authorised development has been submitted to and approved by the local planning authority in consultation with Natural England.
  • (2) The undertaker must not exercise the power to maintain under article 7 (maintenance of authorised project) in the intertidal area until an intertidal access management plan setting out details of the access routes to the intertidal area, the methods for accessing the intertidal area, the expected number of vehicles that will be accessing the intertidal area and the expected number of vehicle trips to the intertidal area required for such maintenance activities has been submitted to and approved by the local planning authority in consultation with Natural England.
  • (3) If the local planning authority fails to notify the undertaker of its decision on whether to give approval within 2 months of receiving an intertidal access management plan for approval, the local planning authority is deemed to have given approval.
  • (4) The intertidal access management plan must be implemented as approved, unless otherwise agreed by the local planning authority.

25

  • (1) No construction of any wind turbine generator forming part of the authorised development may commence until the Secretary of State, having consulted with the operator, is satisfied that appropriate mitigation will be implemented and maintained for the life of the authorised development.
  • (2) In this Requirement—
  • “appropriate mitigation” means measures to mitigate any adverse impacts which the operation of the authorised development will have on the ability of the operator’s radar early warning system to ensure the safety of its Saturn, Mimas and Tethys offshore platforms during the life of the authorised development;
  • “operator” means ConocoPhillips (U.K.) Limited (company number 00524868) or successor operator of any of the Saturn, Mimas or Tethys offshore platforms;
  • “radar early warning system” means the radar early warning system used to monitor and track vessels proximate to the operator’s offshore facilities via radio and network links (which is comprised primarily of radars fitted on a number of operator’s offshore platforms and provides a multi-site, multi-sensor integrated marine surveillance system with logistic and emergency response co-ordination facilities).
  • (3) The undertaker must comply with all obligations contained within the appropriate mitigation for the life of the authorised development.

Requirement for written approval

26

Where the approval, agreement or confirmation of the Secretary of State, the local planning authority or another person is required under a Requirement, that approval, agreement or confirmation must be given in writing.

Amendments to approved plans, etc.

27

  • (1) Where a Requirement requires the authorised development to be carried out in accordance with a plan, scheme, code or details approved by the local planning authority or any other person (the “approved plan”), the approved plan must be taken to include any amendments that may subsequently be approved by the local planning authority or other person.
  • (2) Any amendments to the approved plan must be in accordance with the principles and assessments set out in the environmental statement; and approval for such amendments may be given only where it has been demonstrated to the satisfaction of the local planning authority or other person that the amendments are unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
  • (3) Where the approved plan is required to be approved after consultation with another person, any amendments may be approved only after consultation with that person.

SCHEDULE 2 — Streets subject to street works

(1) Area (2) Streets subject to street works
District of East Lindsey Permissive footpath along sea wall
District of East Lindsey Sheep Marsh Lane
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north
District of East Lindsey Sea Lane
District of East Lindsey Tetn/19/1 (public footpath)
District of East Lindsey North Coates Road
District of East Lindsey Tetn/343/1 (public footpath)
District of East Lindsey Tetn/12/5 (public footpath)
District of East Lindsey Tetn/13/5 (public footpath)
District of East Lindsey Unnamed highway east of New Delights access
District of East Lindsey Tetney Lock Road
District of East Lindsey Humberston Road (A1031)
District of East Lindsey Tetn/14/4 (public footpath)
District of East Lindsey Holton Road
District of East Lindsey HoLC/5/4 (public footpath)
District of East Lindsey Station Road, Tetney
District of East Lindsey HoLC/4/1 (public footpath)
District of East Lindsey Louth Road (A16)
District of East Lindsey High Street, North Thoresby (B1201)
District of East Lindsey Station Road, North Thoresby (B1201)
District of East Lindsey HoLC/10/1 (public footpath)
North East Lincolnshire Brigsley FP84 (public footpath)
North East Lincolnshire Brigsley FP83 (public footpath)
North East Lincolnshire Waithe Lane
North East Lincolnshire Brigsley BW75 (public bridleway)
North East Lincolnshire Waltham Road, Brigsley (B1203)
North East Lincolnshire Waltham Road, Barnoldby le Beck (C148)
North East Lincolnshire Bradley FP95 (public footpath)
North East Lincolnshire Bradley Road
North East Lincolnshire Bradley BW93 (public bridleway)
North East Lincolnshire Laceby FP95 (public footpath)
North East Lincolnshire Laceby BW97 (public bridleway)
North East Lincolnshire Laceby FP96 (public footpath)
North East Lincolnshire Grimsby Road (A46)
North East Lincolnshire Aylesby FP103 (public footpath)
North East Lincolnshire Aylesby FP110 (public footpath)
North East Lincolnshire Aylesby Road
North East Lincolnshire Aylesby BW108 (public bridleway)
North East Lincolnshire Beech Holt Lane
North East Lincolnshire Nooking Lane
West Lindsey District Wells Road
North East Lincolnshire Riby Road (A1173)
North East Lincolnshire Stallingborough FP26 (public footpath)
North East Lincolnshire Stallingborough FP24 (public footpath)
North East Lincolnshire Keelby Road
North East Lincolnshire Habrough FP4 (public footpath)
North East Lincolnshire Roxton Road south of A180 between Keelby and Immingham
North East Lincolnshire A180(T)
North East Lincolnshire Station Road, Habrough (B1210)
North East Lincolnshire Immingham Road (B1210)
North East Lincolnshire Habrough FP8 (public footpath)
North East Lincolnshire Habrough FP7 (public footpath)
North East Lincolnshire Killingholme Road/ Habrough Road
North Lincolnshire Council South Killingholme 94 (public footpath) FP/SKIL/94
North Lincolnshire Council Habrough Road/Faulding Lane
North Lincolnshire Council South Killingholme 87 (public footpath) FP/SKIL/87
North Lincolnshire Council Habrough Road
North Lincolnshire Council South Killingholme 88 (public footpath) FP/SKIL/88
North Lincolnshire Council Proposed A160 upgrade/realignment (HA Improvement Scheme)
North Lincolnshire Council Ulceby Road (A160)
North Lincolnshire Council Ulceby Road access to houses
North Lincolnshire Council Top Road
North Lincolnshire Council Currently unconstructed road on route of proposed cable route (part of the A160 improvement works) north of the A160 and west of Top Road (area hatched between points 119 and 120 on the onshore works plan 24)
North Lincolnshire Council South Killingholme 87 (public footpath) FP/SKIL/87
North Lincolnshire Council South Killingholme 85 (public footpath) FP/SKIL/85
North Lincolnshire Council Church Lane/ Nicholson Road
North Lincolnshire Council Chase Hill Road
North Lincolnshire Council Eastfield Road
North Lincolnshire Council Brick Lane/Dean Street
North Lincolnshire Council North Killingholme 86 (public footpath) FP/NKIL/86
North Lincolnshire Council North Killingholme 79 (public footpath) FP/NKIL/79

SCHEDULE 3 — Streets to be temporarily stopped up

(1) Area (2) Street to be temporarily stopped up (3) Extent of temporary stopping up
District of East Lindsey Permissive footpath Between points F1 and F2 as shown in a dotted black line on sheet 1 of the onshore works plans
District of East Lindsey Permissive footpath Between points F3 and F4 as shown in a dotted black line on sheet 1 of the onshore works plans
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north Between points 1 and 2 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north Between points 3 and 4 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north Between points 5 and 6 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Sea Lane Between points 7 and 8 as shown hatched on sheet 2 of the onshore works plans
District of East Lindsey Footpath Tetn/19/1 Between points F5 and F6 as shown in a dotted black line on sheet 3 of the onshore works plans
District of East Lindsey Footpath Tetn/19/1 Between points F7 and F8 as shown in a dotted black line on sheet 3 of the onshore works plans
District of East Lindsey North Coates Road Between points 9 and 10 as shown hatched on sheet 4 of the onshore works plans
District of East Lindsey Footpath Tetn/13/5 Between points F9 and F10 as shown in a dotted black line on sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 11 and 12 as shown hatched on sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 13 and 14 as shown hatched on sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 15 and 16 as shown hatched on Sheet 4 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 17 and 18 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Unnamed highway east of New Delights access Between points 19 and 20 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Tetney Lock Road Between points 21 and 22 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Tetney Lock Road Between points 23 and 24 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Humberston Road Between points 25 and 26 as shown hatched on sheet 5 of the onshore works plans
District of East Lindsey Footpath Tetn/14/4 Between points F11 and F12 as shown in a dotted black line on sheet 6 of the onshore works plans
District of East Lindsey Holton Road Between points 27 and 28 as shown hatched on sheet 6 of the onshore works plans
District of East Lindsey Holton Road Between points 121 and 122 as shown hatched on sheet 6 of the onshore works plans
District of East Lindsey Holton Road Between points 123 and 124 as shown hatched on sheet 6 of the onshore works plans
District of East Lindsey Footpath HoLC/5/4 Between points F13 and F14 as shown in a dotted black line on sheet 7 of the onshore works plans
District of East Lindsey Footpath HoLC/5/4 Between points F14 and F15 as shown in a dotted black line on sheet 7 of the onshore works plans
District of East Lindsey Station Road, Tetney Between points 29 and 30 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Station Road, Tetney Between points 31 and 32 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Station Road, Tetney Between points 33 and 34 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Footpath HoLC/4/1 Between points F16 and F17 as shown in a dotted black line on sheet 7 of the onshore works plans
District of East Lindsey Louth Road (A16) Between points 35 and 36 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Louth Road (A16) Between points 36 and 37 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Louth Road (A16) Between points 38 and 39 as shown hatched on sheet 7 of the onshore works plans
District of East Lindsey Footpath HoLC/10/1 Between points F18 and F19 as shown in a dotted black line on sheet 8 of the onshore works plans
North East Lincolnshire Footpath FP84 Between points F18 and F21 as shown in a dotted black line on sheet 8 of the onshore works plans
North East Lincolnshire Footpath FP83 Between points F20 and F20.1 as shown in a dotted black line on sheet 8 of the onshore works plans
North East Lincolnshire Waithe Lane Between points 40 and 41 as shown hatched on sheet 8 of the onshore works plans
North East Lincolnshire Waithe Lane Between points 127 and 128 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waithe Lane Between points 42 and 43 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Bridleway BW75 Between points F22 and F23 as shown in a dotted black line on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (B1203) Between points 44 and 45 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (B1203) Between points 46 and 47 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (B1203) Between points 48 and 49 as shown hatched on sheet 9 of the onshore works plans
North East Lincolnshire Waltham Road (C148) Between points 50 and 51 as shown hatched on sheet 10 of the onshore works plans
North East Lincolnshire Bradley Road Between points 52 and 53 as shown hatched on sheet 11 of the onshore works plans
North East Lincolnshire Footpath FP95 Between points F24 and F25 as shown in a dotted black line on sheet 12 of the onshore works plans
North East Lincolnshire Footpath FP95 Between points F26 and F27 as shown in a dotted black line on sheet 12 of the onshore works plans
North East Lincolnshire Bradley Road Between points 54 and 55 as shown hatched on sheet 12 of the onshore works plans
North East Lincolnshire Bradley Road Between points 56 and 57 as shown hatched on sheet 12 of the onshore works plans
North East Lincolnshire Bridleway BW93 Between points F28 and F29 as shown in a dotted black line on sheet 12 of the onshore works plans
North East Lincolnshire Footpath FP95 Between points F30 and F31 as shown in a dotted black line on sheet 13 of the onshore works plans
North East Lincolnshire Bridleway BW97 Between points F32 and F33 as shown in a dotted black line on sheet 14 of the onshore works plans
North East Lincolnshire Footpath FP96 Between points F34 and F35 as shown in a dotted black line on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 58 and 59 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 60 and 61 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 62 and 63 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 64 and 65 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 60 and 65 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Grimsby Road (A46) Between points 58 and 62 as shown hatched on sheet 14 of the onshore works plans
North East Lincolnshire Footpath FP103 Between points F36 and F37 as shown in a dotted black line on sheet 15 of the onshore works plans
North East Lincolnshire Footpath FP110 Between points F38 and F39 as shown in a dotted black line on sheet 15 of the onshore works plans
North East Lincolnshire Aylesby Road Between points 66 and 67 as shown hatched on sheet 15 of the onshore works plans
North East Lincolnshire Bridleway BW108 Between points F40 and F41 as shown in a dotted black line on sheet 15 of the onshore works plans
North East Lincolnshire Beech Holt Lane/Nooking Lane Between points 68 and 69 as shown hatched on sheet 16 of the onshore works plans
West Lindsey District Wells Road Between points 70 and 71 as shown hatched on sheet 17 of the onshore works plans
North East Lincolnshire Riby Road (A1173) Between points 72 and 73 as shown hatched on sheet 18 of the onshore works plans
North East Lincolnshire Riby Road (A1173) Between points 74 and 75 as shown hatched on sheet 18 of the onshore works plans
North East Lincolnshire Footpath FP26 Between points F42 and F43 as shown in a dotted black line on sheet 19 of the onshore works plans
North East Lincolnshire Keelby Road Between points 76 and 77 as shown hatched on sheet 19 of the onshore works plans
North East Lincolnshire Keelby Road Between points 78 and 79 as shown hatched on sheet 19 of the onshore works plans
North East Lincolnshire Roxton Road Between points 80 and 81 as shown hatched on sheet 20 of the onshore works plans
North East Lincolnshire Roxton Road Between points 82 and 83 as shown hatched on sheet 20 of the onshore works plans
North East Lincolnshire Station Road (B1210) Between points 92 and 93 as shown hatched on sheet 22 of the onshore works plans
North East Lincolnshire Immingham Road (B1210) Between points 94 and 95 as shown hatched on sheet 23 of the onshore works plans
North East Lincolnshire Immingham Road (B1210) Between points 96 and 97 as shown hatched on sheet 23 of the onshore works plans
North East Lincolnshire Footpath FP8 Between points F44 and F45 as shown in a dotted black line on sheet 23 of the onshore works plans
North East Lincolnshire Footpath FP7 Between points F46 and F47 as shown in a dotted black line on sheet 23 of the onshore works plans
North East Lincolnshire Killingholme Road/ Habrough Road Between points 98 and 99 as shown hatched on sheet 23 of the onshore works plans
North Lincolnshire Council Footpath 94 Between points F48 and F49 as shown in a dotted black line on sheet 24 of the onshore works plans
North Lincolnshire Council Faulding Lane Between points 100 and 101 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council Footpath 87 Between points F50 and F51 as shown in a dotted black line on sheet 24 of the onshore works plans
North Lincolnshire Council Footpath 88 Between points F52 and F53 as shown in a dotted black line on sheet 24 of the onshore works plans
North Lincolnshire Council Habrough Road Between points 102 and 103 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council Ulceby Road (A160) Between points 104 and 105 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council On cable route – potential future road Between points 119 and 120 as shown hatched on sheet 24 of the onshore works plans
North Lincolnshire Council Top Road Between points 106 and 107 as shown hatched on sheet 25 of the onshore works plans
North Lincolnshire Council Footpath 87 Between points F54 and F55 as shown in a dotted black line on sheet 25 of the onshore works plans
North Lincolnshire Council Footpath 87 Between points F56 and F57 as shown in a dotted black line on sheet 25 of the onshore works plans
North Lincolnshire Council Church Lane Between points 108 and 109 as shown hatched on sheet 25 of the onshore works plans
North Lincolnshire Council Church Lane Between points 109 and 111 as shown hatched on sheet 25 of the onshore works plans
North Lincolnshire Council Chase Hill Road Between points 112 and 113 as shown hatched on sheet 26 of the onshore works plans
North Lincolnshire Council Chase Hill Road Between points 114 and 115 as shown hatched on sheet 26 of the onshore works plans
North Lincolnshire Council Brick Lane Between points 115 and 116 as shown hatched on sheet 26 and 27 of the onshore works plans
North Lincolnshire Council Footpath 86 Between points F58 and F59 as shown in a dotted black line on sheet 27 of the onshore works plans
North Lincolnshire Council Footpath 79 Between points F60 and F61 as shown in a dotted black line on sheet 27 of the onshore works plans
North Lincolnshire Council Footpath 86 Between points F62 and F65 as shown in a dotted black line on sheet 27 of the onshore works plans
North Lincolnshire Council Footpath 86 Between points F65 and F64 as shown in a dotted red line on sheet 27 of the onshore works plans
North Lincolnshire Council Chase Hill Road Between points 117 and 118 as shown hatched on sheet 27 of the onshore works plans

SCHEDULE 4 — Access to works

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.