The Riverside Energy Park Order 2020

Type Statutory-Instrument
Publication 2020-04-09
Last updated 2023-02-17
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • Work No. 10 infrastructure” means any works or development comprised within Work No. 10 in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 10 on the works plans.(1) Number of plot shown on the land plans(2) Rights etc. which may be acquired02/01, 02/03, 02/10, 02/13, 02/14, 02/15, 02/18, 02/19, 02/25, 02/29, 02/31, 02/32, 02/38For and in connection with the Work No. 6 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 6 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6 infrastructure, or interfere with or obstruct access from and to the Work No. 6 infrastructure, including the right to protect the Work No. 6 infrastructure , the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.02/33, 02/34, 02/45, 02/46, 02/47, 02/50For and in connection with the Work No. 7 infrastructure and Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 7 infrastructure and Work No. 9 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7 infrastructure and Work No. 9 infrastructure, or interfere with or obstruct access from and to the Work No. 7 infrastructure and Work No. 9 infrastructure, including the right to protect the Work No. 7 infrastructure and Work No. 9 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.02/43, 02/44, 02/48, 02/49, 02/51For and in connection with the Work No. 7 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 7 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 7 infrastructure, or interfere with or obstruct access from and to the Work No. 7 infrastructure, including the right to protect the Work No. 7 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.02/33, 02/54, 02/5703/03, 03/04, 03/11, 03/12, 03/1304/01, 04/0205/0106/01, 06/02, 06/03, 06/0407/02, 07/09, 07/1009/0111/01, 11/0312/01, 12/03, 12/04, 12/05, 12/06, 12/06(a), 12/06(b), 12/08, 12/09, 12/11, 12/13, 12/14, 12/15, 12/16, 12/16(a), 12/17, 12/17(a), 12/17(b) 12/18, 12/1913/01, 13/02, 13/03, 13/04, 13/05, 13/06, 13/07, 13/08, 13/09, 13/11, 13/13, 13/14, 13/15, 13/1814/01, 14/02, 14/03, 14/04, 14/04(a), 14/04(b), 14/06, 14/07, 14/08, 14/0915/01, 15/02, 15/03, 15/0516/01, 16/02For and in connection with the Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 9 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9 infrastructure, or interfere with or obstruct access from and to the Work No. 9 infrastructure, including the right to protect the Work No. 9 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.03/06, 03/10For and in connection with the Work No. 8 infrastructure and Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 8 infrastructure and Work No. 9 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 8 infrastructure and Work No. 9 infrastructure, or interfere with or obstruct access from and to the Work No. 8 infrastructure and Work No. 9 infrastructure, including the right to protect the Work No. 8 infrastructure and Work No. 9 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.07/03, 07/04, 07/05At footbridge level only: for and in connection with the Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 9 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9 infrastructure, or interfere with or obstruct access from and to the Work No. 9 infrastructure, including the right to protect the Work No. 9 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.07/06, 07/08At road level only: for and in connection with the Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 9 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9 infrastructure, or interfere with or obstruct access from and to the Work No. 9 infrastructure, including the right to protect the Work No. 9 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.11/02, 12/10, 12/12At road level (and below) only: for and in connection with the Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 9 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9 infrastructure, or interfere with or obstruct access from and to the Work No. 9 infrastructure, including the right to protect the Work No. 9 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.07/03, 07/06, 07/07, 07/08At railway level only: for and in connection with the Work No. 9 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the maintenance of the Work No. 9 infrastructure along with the right to prevent interference with or obstruct access from and to the Work No. 9 infrastructure.16/03For and in connection with the Work No. 9 infrastructure and Work No. 10 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 9 infrastructure and Work No. 10 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9 infrastructure and Work No. 10 infrastructure, or interfere with or obstruct access from and to the Work No. 9 infrastructure and Work No. 10 infrastructure, including the right to protect the Work No. 9 infrastructure and Work No. 10 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.16/04For and in connection with the Work No. 10 infrastructure, the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with the laying, installation, use and maintenance of the Work No. 10 infrastructure, and a right of support for it, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 10 infrastructure, or interfere with or obstruct access from and to the Work No. 10 infrastructure, including the right to protect the Work No. 10 infrastructure, the right to prevent or remove the whole of any building, or fixed or moveable structure, tree, shrub, plant or other thing, and the right to prevent or remove any works or uses which alter the surface level, ground cover or composition of the land.

SCHEDULE 8 — MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS

Compensation enactments

1

The enactments for the time being in force with respect to compensation for the compulsory purchase of land are to apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right or restrictive covenant as they apply as respects compensation on the compulsory purchase of land and interests in land.

2
  • (1) Without limitation on the scope of paragraph 1, the Land Compensation Act 1973 has effect subject to the modifications set out in sub-paragraph (2).
  • (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 5—
  • (a) for “land is acquired or taken from” substitute “ a right or restrictive covenant over land is purchased from or imposed on ”; and
  • (b) for “acquired or taken from him” substitute “ over which the right is exercisable or the restrictive covenant enforceable ”.
3
  • (1) Without limitation on the scope of paragraph 1, the Land Compensation Act 1961 has effect subject to the modification set out in paragraph 2(2).
  • (2) For section 5A(5A) (relevant valuation date) of the 1961 Act, after “if” substitute—

(a) the acquiring authority enters on land for the purpose of exercising a right in pursuance of a notice of entry under section 11(1) of the 1965 Act (as modified by paragraph 5(5) of Schedule 8 to the Riverside Energy Park Order 2020); (b) the acquiring authority is subsequently required by a determination under paragraph 27 of Schedule 2A to the 1965 Act (as substituted by paragraph 5(8) of Schedule 8 to the Riverside Energy Park Order 2020) to acquire an interest in the land; and (c) the acquiring authority enters on and takes possession of that land, the authority is deemed for the purposes of subsection (3)(a) to have entered on that land where it entered on that land for the purpose of exercising that right.

Application of Part 1 of the 1965 Act

4

Part 1 (compulsory purchase under Acquisition of Land Act of 1946) of the 1965 Act, as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and modified by article 29) to the acquisition of land under article 22, applies to the compulsory acquisition of a right by the creation of a new right under article 24—

  • (a) with the modifications specified in paragraph 5; and
  • (b) with such other modifications as may be necessary.
5
  • (1) The modifications referred to in paragraph 4(a) are as follows.
  • (2) References in the 1965 Act to land are, in the appropriate contexts, to be read (according to the requirements of the particular context) as referring to, or as including references to—
  • (a) the right acquired or to be acquired, or the restriction imposed or to be imposed; or
  • (b) the land over which the right is or is to be exercisable, or the restriction is to be enforceable.
  • (3) For section 7 (measure of compensation in case of severance) of the 1965 Act substitute—

(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.

  • (4) The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
  • (a) section 9(4) (refusal to convey, failure to make title etc.);
  • (b) paragraph 10(3) of Schedule 1 (persons without power to sell their interests);
  • (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
  • (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),

are modified to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.

  • (5) Section 11(powers of entry) of the 1965 Act is modified to secure that, where the acquiring authority has served notice to treat in respect of any right or restriction, as well as the notice of entry required by subsection (1) of that section (as it applied to compulsory acquisition under article 22), it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant; and sections 11A (powers of entry: further notices of entry), 11B (counter-notice requiring possession to be taken on specified date), 12 (unauthorised entry) and 13 (refusal to give possession to acquiring authority) of the 1965 Act are modified correspondingly.
  • (6) Section 20 (tenants at will, etc.) of the 1965 Act applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.
  • (7) Section 22 (interests omitted from purchase) of the 1965 Act as modified by article 29(3) is also modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, or enforce the restriction imposed, subject to compliance with that section as respects compensation.
  • (8) For Schedule 2A (counter–notice requiring purchase of land not in notice to treat) to the 1965 Act substitute—

SCHEDULE 2A (1) (1) This Schedule applies where an acquiring authority serve a notice to treat in respect of a right over, or restrictive covenant affecting, the whole or part of a house, building or factory and have not executed a general vesting declaration under section 4 (execution of declaration) of the 1981 Act as applied by article 28 (application of the 1981 Act) of the Riverside Energy Park Order 2020 in respect of the land to which the notice to treat relates. (2) But see article 25 (acquisition of subsoil only) of the Riverside Energy Park Order 2020 which excludes the acquisition of subsoil only from this Schedule. (2) In this Schedule, “house” includes any park or garden belonging to a house. (3) A person who is able to sell the house, building or factory (“the owner”) may serve a counter-notice requiring the authority to purchase the owner's interest in the house, building or factory. (4) A counter-notice under paragraph 3 must be served within the period of twenty-eight days beginning with the day on which the notice to treat was served. (5) On receiving a counter-notice, the acquiring authority must decide whether to— (a) withdraw the notice to treat, (b) accept the counter-notice, or (c) refer the counter-notice to the Upper Tribunal. (6) The authority must serve notice of their decision on the owner within the period of three months beginning with the day on which the counter-notice is served (“the decision period”). (7) If the authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period. (8) If the authority do not serve notice of a decision within the decision period they are to be treated as if they had served notice of a decision to withdraw the notice to treat at the end of that period. (9) If the authority serve notice of a decision to accept the counter-notice, the compulsory purchase order and the notice to treat are to have effect as if they included the owner's interest in the house, building or factory. (10) On a referral under paragraph 7, the Upper Tribunal must determine whether the acquisition of the right or the imposition of the restrictive covenant would— (a) in the case of a house, building or factory, cause material detriment to the house, building or factory, or (b) in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs. (11) In making its determination, the Upper Tribunal must take into account— (a) the effect of the acquisition of the right or the imposition of the covenant, (b) the use to be made of the right or covenant proposed to be acquired or imposed, and (c) if the right or covenant is proposed to be acquired or imposed for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land. (12) If the Upper Tribunal determines that the acquisition of the right or the imposition of the covenant would have either of the consequences described in paragraph 10, it must determine how much of the house, building or factory the authority ought to be required to take. (13) If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the compulsory purchase order and the notice to treat are to have effect as if they included the owner's interest in that land. (14) (1) If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the authority may at any time within the period of six weeks beginning with the day on which the Upper Tribunal makes its determination withdraw the notice to treat in relation to that land. (2) If the acquiring authority withdraws the notice to treat under this paragraph they must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawal of the notice. (3) Any dispute as to the compensation is to be determined by the Upper Tribunal.

SCHEDULE 9 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1) Location (2) Number of plot shown on land plans (3) Purpose for which temporary possession may be taken
In the London Borough of Bexley 2/43, 2/44, 2/48, 2/49, 02/52, 03/05 Temporary use as laydown, construction compound, construction use and accesses for as described in Work No. 8
In the Borough of Dartford 13/12 Temporary use as laydown, construction compound and construction use as described in Work No. 9c

SCHEDULE 10 — PROTECTIVE PROVISIONS

PART 1 — FOR THE PROTECTION OF RRRL

1

For the protection of RRRL as referred to in this part of this Schedule the following provisions have effect unless otherwise agreed in writing between the undertaker and RRRL.

2

In this part of this Schedule

  • access road” means that part of the access road known as Norman Road between points C and D on the access and public rights of way plan;
  • alternative apparatus” means alternative apparatus adequate to enable RRRL to fulfil its functions in a manner no less efficient than previously;
  • apparatus” means any electric cables, electrical plant, drains, mains, sewers, pipes, conduits or any other apparatus belonging to or maintained by RRRL and used for, or for purposes connected with, waste treatment and disposal and the generation, transmission, distribution or supply of electricity and/or heat generated at the RRRL facility and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
  • authorised development” has the same meaning as in article 2 of this Order;
  • functions” includes powers and duties;
  • “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
  • internal street” means any roads that service the RRRL facility and which are located within the RRRL facility perimeter;
  • “plan” or “plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe and assess the works to be executed;
  • RRRL facility” means the energy from waste facility and associated infrastructure at Norman Road, Belvedere, Bexley, Kent;
  • RRRL facility perimeter” means that part of the Order land identified as plots 02/01, 02/03, 02/10, 02/13, 02/14, 02/15, 02/18, 02/19, 02/25, 02/29, 02/31 and 02/32 on the land plans;
  • RRRL land” means that part of the Order land in the freehold ownership of RRRL which, as at the date upon which this Order comes into force pursuant to Article 1, are those plots identified as being in the freehold ownership of RRRL in the book of reference but always excluding plots 02/43, 02/44, 02/47, 02/48, 02/49, and 02/51;
3

Upon the permanent stopping up of the access road pursuant to article 14 (permanent stopping up of streets), the undertaker must afford to RRRL the rights for RRRL and all persons authorised on its behalf to enter and pass and re-pass, on foot and/or with or without vehicles, plant and machinery, for all purposes in connection with its occupation and use of the RRRL facility.

4

The undertaker must not install pipes for the offtake of waste heat from the authorised development without first giving RRRL the option to combine its pipes with any pipes for the offtake of waste heat from the authorised development. The undertaker must have regard to any consultation responses received from RRRL when finalising the location of pipes for the offtake of waste heat from the authorised development.

5

Regardless of the temporary prohibition or restriction of use of streets under the powers conferred by article 13 (temporary prohibition or restriction of use of streets and public rights of way), RRRL is at liberty at all times to take all necessary access across any street used to access the RRRL facility and which has been temporarily stopped up under article 13 and/or any internal street and to execute and do all such works and things in, upon or under any such street used to access the RRRL facility that has been temporarily stopped up under article 13 and/or internal street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the prohibition or restriction is in that street used to access the RRRL facility and has been temporarily stopped up under article 13 or internal street.

6

Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus within the RRRL land otherwise than by agreement.

7
  • (1) If, in the exercise of the powers conferred by this Order, the undertaker:–
  • (a) acquires any interest in the RRRL land in which any apparatus is placed or over which access to any apparatus is enjoyed; or
  • (b) requires that RRRL's apparatus within the RRRL land is relocated, diverted or removed,

any right of RRRL to any part of the RRRL land and/or to maintain that apparatus in that land and to gain access to it must not be extinguished, and that apparatus must not be relocated, diverted or removed, until equivalent rights have been granted to RRRL for alternative apparatus and equivalent alternative apparatus has vested in RRRL and (in relation to apparatus) has been constructed and is in operation, and access to it has been provided. The location of equivalent alternative apparatus and rights for the equivalent alternative apparatus must in each case be agreed between the undertaker and RRRL before any step is taken to extinguish, relocate, divert or remove as aforesaid.

  • (2) If, for the purpose of executing any works in, on or under the RRRL land, the undertaker requires the relocation, diversion or removal of any apparatus placed in the RRRL land, the undertaker must give to RRRL for approval written notice of that requirement, a plan and section of the work proposed and of the proposed position of the alternative apparatus together with a timetable for when the alternative apparatus is to be provided or constructed by the undertaker.
  • (3) The approval of RRRL under sub-paragraph (2) must not be unreasonably withheld and if by the end of the period of 28 days beginning with the date on which the notice, plan, section and timetable have been supplied to RRRL, RRRL has not intimated approval or disapproval of such notice, plan, section and timetable and the grounds of disapproval, RRRL is deemed to have approved the said notice, plan, section and timetable as submitted.
  • (4) When giving its approval under sub-paragraph (2), RRRL may specify such reasonable requirements that are necessary in the provision or construction of the alternative apparatus.
  • (5) In the event that RRRL issues a disapproval to the notice, plan, section and timetable within the 28 day period referred to in sub-paragraph (3), the undertaker may refer the matter to arbitration in accordance with article 42 (procedures in relation to certain approvals etc.).
  • (6) Subject to sub-paragraph (8), any alternative apparatus to be provided or constructed pursuant to this paragraph must be provided or constructed by the undertaker within a timescale, to a standard and in such manner and in such line or situation as is agreed with RRRL or in default of agreement settled by arbitration in accordance with article 42 (procedures in relation to certain approvals etc.).
  • (7) Where the alternative apparatus is to be provided or constructed on land of the undertaker and once the undertaker has provided or constructed the alternative apparatus, the undertaker must grant RRRL the necessary rights to access and maintain the alternative apparatus on that land.
  • (8) If in the approval to the notice, plan, section and timetable under sub-paragraph (2) or by the end of the period of 28 days beginning with the date on which the arbitrator settles the alternative apparatus to be provided or constructed, RRRL gives notice to the undertaker that it desires to provide or construct the alternative apparatus and this is agreed to by the undertaker, (acting reasonably) RRRL, after the grant to RRRL of the rights as are referred to in sub-paragraph (9), must proceed without unnecessary delay to provide and construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this part of this Schedule.
  • (9) Where RRRL is to provide or construct the alternative apparatus, and the alternative apparatus is to be provided or constructed on land of the undertaker, the undertaker must grant RRRL the necessary rights to provide or construct the alternative apparatus on that land and grant RRRL the necessary rights to access and maintain the alternative apparatus on that land.
8
  • (1) Where, in accordance with the provisions of this part of this Schedule, the undertaker affords to RRRL rights in land of the undertaker for the construction and maintenance of alternative apparatus in substitution for apparatus to be removed, those rights must be granted upon such terms and conditions as may be agreed between the undertaker and RRRL or in default of agreement settled by arbitration in accordance with article 42 (procedures in relation to certain approvals etc.).
  • (2) If the rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those rights are to be granted, are in the opinion of the arbitrator materially less favourable on the whole to RRRL than the rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to RRRL as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
9
  • (1) Not less than 28 days before starting the execution of any works in, on or under the RRRL land that may materially affect the operation of the RRRL facility, the undertaker must submit to RRRL for approval a plan, section and description of the works to be executed and a timetable for when such works are to be carried out.
  • (2) The approval of RRRL under sub-paragraph (1) must not be unreasonably withheld and if by the end of the period of 28 days beginning with the date on which the plan, section, description and timetable have been supplied to RRRL, RRRL has not intimated disapproval of such plan, section, description and timetable and the grounds of disapproval, RRRL is deemed to have approved the said plan, section description and timetable as submitted.
  • (3) When giving its approval under sub-paragraph (1), RRRL may specify such reasonable requirements which in RRRL's opinion are necessary in the execution of the works.
  • (4) The works described in sub-paragraph (1) must be executed only in accordance with the plan, section, description and timetable submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be given in accordance with sub-paragraph (3) by RRRL. Where RRRL reasonably requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature) such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to RRRL's reasonable satisfaction prior to the works described in sub-paragraph (1).
  • (5) In the event that RRRL issues a disapproval to the plan, section, description and timetable within the 28 day period referred to in sub-paragraph (1), the undertaker may refer the matter to arbitration in accordance with article 42 (procedures in relation to certain approvals etc.).
  • (6) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
  • (7) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency works (as defined in the 1991 Act) but in that case it must give to RRRL notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraphs (3) and (4) in so far as is reasonably practicable in the circumstances.
10
  • (1) Subject to the following provisions of this paragraph, the undertaker must repay to RRRL the reasonable expenses incurred by RRRL in, or in connection with, the inspection, removal, alteration or protection of any apparatus within the RRRL land or the provision or construction of any alternative apparatus which RRRL elects to carry out itself as referred to in paragraph 7(8).
  • (2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this part of this Schedule, that value being calculated after removal.
  • (3) If in accordance with the provisions of this part of this Schedule:–
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 42 (procedures in relation to certain approvals etc.) to be necessary, then, if such placing involves cost in the construction of works under this part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to RRRL by virtue of sub-paragraph (1) will be reduced by the amount of that excess.

  • (4) For the purposes of sub-paragraph (3):–
  • (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the execution of any such works as are referred to in paragraph 7(2); and
  • (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
  • (5) An amount which apart from this sub-paragraph would be payable to RRRL in respect of works by virtue of sub-paragraph (1) if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on RRRL any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
11

Nothing in this part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and RRRL in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

12

Where in consequence of the proposed construction or maintenance of any part of the authorised development, the undertaker or RRRL requires the removal of apparatus or RRRL makes requirements for the protection or alteration of apparatus, the undertaker shall use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution and maintenance of the authorised development and taking into account the need to ensure the safe and efficient operation of RRRL's undertaking and RRRL shall use its reasonable endeavours to co-operate with the undertaker for that purpose.

13

If in consequence of any agreement reached or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable RRRL to maintain or use the apparatus no less effectively than was possible before such obstruction.

14
  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule or in consequence of the construction, use, maintenance or failure of any part of the authorised development by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, use or maintenance, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised development) or property of RRRL, or there is any interruption in any service provided, or in the supply of any goods, by RRRL, or RRRL becomes liable to pay any amount to any third party, the undertaker will:–
  • (a) bear and pay on demand the cost reasonably incurred by RRRL in making good such damage or restoring the supply; and
  • (b) indemnify RRRL for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from RRRL, by reason or in consequence of any such damage or interruption or RRRL becoming liable to any third party as aforesaid other than arising from any default of RRRL.
  • (2) The fact that any act or thing may have been done by RRRL on behalf of the undertaker or in accordance with a plan approved by RRRL or in accordance with any requirement of RRRL or under its supervision will not (unless sub-paragraph (3) applies), excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless RRRL fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and RRRL.
  • (3) Nothing in sub-paragraph (1) shall impose any liability on the undertaker in respect of:–
  • (a) any damage or interruption to the extent that it is attributable to the neglect or default of RRRL, its officers, servants, contractors or agents; and
  • (b) any part of the authorised development and/or any other works authorised by this Part of this Schedule carried out by RRRL as an assignee, transferee or lessee of a person with the benefit of the Order pursuant to section 156 of the Planning Act 2008 or article 8 (consent to transfer benefit of the Order) subject to the proviso that once such works become apparatus, any part of the authorised development yet to be executed and not falling within this sub-section 3(b) will be subject to the full terms of this Part of this Schedule including this paragraph 14.
  • (4) RRRL must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
  • (5) RRRL must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 14 applies. If requested to do so by the undertaker, RRRL shall provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph 14 for claims reasonably incurred by RRRL.
15
  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of any works carried out by RRRL pursuant to this Part of this Schedule or in consequence of the use, maintenance or failure of any part of the RRRL facility by or on behalf of RRRL or in consequence of any act or default of RRRL (or any person employed or authorised by him) in the course of carrying out such works, use or maintenance, including without limitation works carried out by RRRL under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any part of the authorised development or property of the undertaker, or there is any interruption in any service provided, or in the supply of any goods, by the undertaker, or the undertaker becomes liable to pay any amount to any third party, RRRL will:–
  • (a) bear and pay on demand the cost reasonably incurred by the undertaker in making good such damage or restoring the supply; and
  • (b) indemnify the undertaker for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from the undertaker, by reason or in consequence of any such damage or interruption or the undertaker becoming liable to any third party as aforesaid other than arising from any default of the undertaker.
  • (2) The fact that any act or thing may have been done by the undertaker on behalf of RRRL or in accordance with a plan approved by the undertaker or in accordance with any requirement of the undertaker or under its supervision will not (unless sub-paragraph (3) applies), excuse RRRL from liability under the provisions of this sub-paragraph (1) unless the undertaker fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and RRRL.
  • (3) Nothing in sub-paragraph (1) shall impose any liability on RRRL in respect of any damage or interruption to the extent that it is attributable to the neglect or default of the undertaker, its officers, servants, contractors or agents.
  • (4) The undertaker must give RRRL reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting RRRL and considering their representations.
  • (5) The undertaker must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 15 applies. If requested to do so by RRRL, the undertaker shall provide an explanation of how the claim has been minimised. RRRL shall only be liable under this paragraph 15 for claims reasonably incurred by the undertaker.

PART 2 — FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS

16

The provisions of this Part have effect for the protection of a utility undertaker unless otherwise agreed in writing between the undertaker and the utility undertaker in question.

17

In this Part of this Schedule—

  • alternative apparatus” means alternative apparatus adequate to enable the utility undertaker in question to fulfil its statutory functions in a manner not less efficient than previously;
  • apparatus” means—in the case of a utility undertaker within paragraph (a) of the definition of that term in this paragraph, electric lines or electrical plant (as defined in the Electricity Act 1989 ), belonging to or maintained by the utility undertaker for the purposes of electricity supply;in the case of a utility undertaker within paragraph (b) of the definition of that term, any mains, pipes or other apparatus belonging to or maintained by the utility undertaker for the purposes of gas supply;in the case of a utility undertaker within paragraph (c) of the definition of that term—mains, pipes or other water apparatus belonging to or maintained by the utility undertaker for the purposes of water supply; andmains, pipes or other water apparatus that is the subject of an agreement to adopt made under section 51A (agreements to adopt water main or service pipe at future date) of the Water Industry Act 1991 ; andin the case of a sewerage undertaker within paragraph (d) of the definition of that term—any drain or works vested in the sewerage undertaker under the Water Industry Act 1991; andany sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) (adoption of sewers and disposal works) of that Act or an agreement to adopt made under section 104 (agreements to adopt sewer, drain or sewerage disposal works, at future date) of that Act,

and includes a sludge main, disposal main (within the meaning of section 219 (general interpretation) of that Act) or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any such sewer, drain or works, and in each case includes any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;

  • functions” includes powers and duties;
  • “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land; and
  • utility undertaker” means—any licence holder within the meaning of Part 1 (electricity supply) of the Electricity Act 1989;a gas transporter within the meaning of Part 1 (gas supply) of the Gas Act 1986 ;a water undertaker within the meaning of the Water Industry Act 1991; anda sewerage undertaker within the meaning of the Water Industry Act 1991,

for the area of the authorised development, and in relation to any apparatus, means the utility undertaker to whom it belongs or by whom it is maintained.

18

This Part of this Schedule does not apply to apparatus in respect of which the relations between the undertaker and the utility undertaker are regulated by Part 3 (water supply) of the Water Industry Act 1991.

19

Regardless of the temporary prohibition or restriction of use of streets under the powers conferred by article 13, a utility undertaker is at liberty at all times to take all necessary access across any such street and to execute and do all such works and things in, upon or under any such street as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the prohibition or restriction was in that street.

20

Regardless of any provision in this Order or anything shown on the land plans, the undertaker must not acquire any apparatus otherwise than by agreement.

21
  • (1) If, in the exercise of the powers conferred by this Order, the undertaker acquires any interest in any land in which any apparatus is placed or over which access to any apparatus is enjoyed or requires that the utility undertaker's apparatus is relocated or diverted, that apparatus must not be removed under this Part of this Schedule, and any right of a utility undertaker to maintain that apparatus in that land and to gain access to it must not be extinguished, until alternative apparatus has been constructed and is in operation, and access to it has been provided, to the reasonable satisfaction of the utility undertaker in question in accordance with sub-paragraphs (2) to (7).
  • (2) If, for the purpose of executing any works in, on or under any land purchased, held, appropriated or used under this Order, the undertaker requires the removal of any apparatus placed in that land, the undertaker must give to the utility undertaker in question written notice of that requirement, together with a plan and section of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any of the powers conferred by this Order a utility undertaker reasonably needs to remove any of its apparatus) the undertaker must, subject to sub-paragraph (3), afford to the utility undertaker the necessary facilities and rights for the construction of alternative apparatus in other land of the undertaker and subsequently for the maintenance of that apparatus.
  • (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, the utility undertaker in question must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible use reasonable endeavours to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed.
  • (4) Any alternative apparatus to be constructed in land of the undertaker under this Part of this Schedule must be constructed in such manner and in such line or situation as may be agreed between the utility undertaker in question and the undertaker or in default of agreement settled by arbitration in accordance with article 42(3) (procedures in relation to certain approvals etc.).
  • (5) The utility undertaker in question must, after the alternative apparatus to be provided or constructed has been agreed or settled by arbitration in accordance with article 42(3), and after the grant to the utility undertaker of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay to construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under the provisions of this part of this Schedule.
  • (6) Regardless of anything in sub-paragraph (5), if the undertaker gives notice in writing to the utility undertaker in question that it desires itself to execute any work, or part of any work, in connection with the construction or removal of apparatus in any land controlled by the undertaker, that work, instead of being executed by the utility undertaker, must be executed by the undertaker without unnecessary delay in accordance with plans approved by the utility undertaker (such approval not to be unreasonably withheld or delayed and may be subject to such reasonable conditions as the utility undertaker deems necessary), under the superintendence (if given) of the utility undertaker and to the reasonable satisfaction of the utility undertaker.
22
  • (1) Where, in accordance with the provisions of this Part of this Schedule, the undertaker affords to a utility undertaker facilities and rights for the construction and maintenance in land of the undertaker of alternative apparatus in substitution for apparatus to be removed, those facilities and rights must be granted upon such terms and conditions as may be agreed between the undertaker and the utility undertaker in question or in default of agreement settled by arbitration in accordance with article 42(3).
  • (2) If the facilities and rights to be afforded by the undertaker in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are in the opinion of the arbitrator less favourable on the whole to the utility undertaker in question than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the arbitrator must make such provision for the payment of compensation by the undertaker to that utility undertaker as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.
23
  • (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 21(2) the undertaker must submit to the utility undertaker in question a plan, section and description of the works to be executed.
  • (2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by the utility undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the utility undertaker is entitled to watch and inspect the execution of those works.
  • (3) Any requirements made by a utility undertaker under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.
  • (4) If a utility undertaker in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 16 to 22 apply as if the removal of the apparatus had been required by the undertaker under paragraph 21(2).
  • (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
  • (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the utility undertaker in question notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
24
  • (1) Subject to the following provisions of this paragraph, the undertaker must repay to a utility undertaker the reasonable expenses incurred by that utility undertaker in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 21(2).
  • (2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule, that value being calculated after removal.
  • (3) If in accordance with the provisions of this Part of this Schedule—
  • (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
  • (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,

and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 42(3) to be necessary, then, if such placing involves cost in the construction of works under this part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the utility undertaker in question by virtue of sub-paragraph (1) is to be reduced by the amount of that excess.

  • (4) For the purposes of sub-paragraph (3)—
  • (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the execution of any such works as are referred to in paragraph 21(2); and
  • (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
  • (5) An amount which apart from this sub-paragraph would be payable to a utility undertaker in respect of works by virtue of sub-paragraph (1) if the works include the placing of apparatus provided in substitution for apparatus placed more than seven years and six months earlier so as to confer on the utility undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
25
  • (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the works referred to in paragraph 21(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a utility undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any utility undertaker, the undertaker must—
  • (a) bear and pay the cost reasonably incurred by that utility undertaker in making good such damage or restoring the supply; and
  • (b) make reasonable compensation to that utility undertaker for any other expenses, loss, damages, penalty or costs incurred by the utility undertaker,

by reason or in consequence of any such damage or interruption.

  • (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a utility undertaker, its officers, servants, contractors or agents.
  • (3) A utility undertaker must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
26

Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and a utility undertaking in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

PART 3 — FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS

27
  • (1) For the protection of any operator, the following provisions have effect, unless otherwise agreed in writing between the undertaker and the operator.
  • (2) In this Part of this Schedule—
  • the 2003 Act” means the Communications Act 2003 ;
  • electronic communications apparatus” has the same meaning as in the electronic communications code;
  • the electronic communications code” has the same meaning as in section 106 (application of the electronic communications code) of the 2003 Act;
  • electronic communications code network” means—so much of an electronic communications network or conduit system provided by an electronic communications code operator as is not excluded from the application of the electronic communications code by a direction under section 106 of the 2003 Act; andan electronic communications network which the Secretary of State is providing or proposing to provide;
  • electronic communications code operator” means a person in whose case the electronic communications code is applied by a direction under section 106 of the 2003 Act; and
  • operator” means the operator of an electronic communications code network.
28

The exercise of the powers of article 33 (statutory undertakers) is subject to Part 10 (undertakers' works affecting electronic communications apparatus) of the electronic communications code.

29
  • (1) Subject to sub-paragraphs (2) to (4), if as the result of the authorised development or its construction, or of any subsidence resulting from any of those works—
  • (a) any damage is caused to any electronic communications apparatus belonging to an operator (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works), or other property of an operator; or
  • (b) there is any interruption in the supply of the service provided by an operator,

the undertaker must bear and pay the cost reasonably incurred by the operator in making good such damage or restoring the supply and make reasonable compensation to that operator for any other expenses, loss, damages, penalty or costs incurred by it, by reason, or in consequence of, any such damage or interruption.

  • (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of an operator, its officers, servants, contractors or agents.
  • (3) The operator must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise of the claim or demand is to be made without the consent of the undertaker which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
  • (4) Any difference arising between the undertaker and the operator under this part of this Schedule must be referred to and settled by arbitration under article 42(3) (procedures in relation to certain approvals etc.).
30

This Part of this Schedule does not apply to—

  • (a) any apparatus in respect of which the relations between the undertaker and an operator are regulated by the provisions of Part 3 (street works in England and Wales) of the 1991 Act; or
  • (b) any damage, or any interruption, caused by electro-magnetic interference arising from the construction or use of the authorised development.
31

Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and an operator in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

PART 4 — FOR THE PROTECTION OF THE ENVIRONMENT AGENCY

32
  • (1) The following provisions shall apply for the protection of the Agency unless otherwise agreed in writing between the undertaker and the Agency.
  • (2) In this Part of this Schedule—
  • the Agency” means the Environment Agency;
  • building” includes any structure or erection or any part of a building, structure or erection;
  • construction” includes execution, placing, altering, replacing, relaying and removal and excavation and “construct” and “constructed” shall be construed accordingly;
  • damage” includes (but is not limited to) scouring, erosion, loss of structural integrity and environmental damage to any drainage work or any flora or fauna dependent on the aquatic environment, and “damaged” is to be construed accordingly;
  • drainage work” means any main river and includes any land which provides or is expected to provide flood storage capacity for any main river and any bank, wall, embankment or other structure, or any appliance, constructed or used for flood defence or tidal monitoring;
  • main river” means all watercourses shown as such on the statutory main river maps held by the Agency and the Department for Environment Food and Rural Affairs including any structure or appliance for controlling or regulating the flow of water in or out of the channel;
  • non–tidal main river” means any part of a main river that is not a tidal main river;
  • tidal main river” means that part of a main river downstream of the normal tidal limit;
  • plans” includes sections, drawings, specifications, calculations and method statements;
  • specified work” means so much of any work or operation authorised by this Order as is in, on, under, over or within 16 metres of a drainage work on a Tidal Main River, 8 metres of a drainage work on a non–tidal main rivers or is otherwise likely to—affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work;affect the flow, purity or quality in any main river;affect the conservation, distribution or use of water resources; oraffect the conservation value of the main river and habitats in its immediate vicinity; and
  • watercourse” includes all rivers, streams, ditches, drains, cuts, culverts, dykes, sluices, basins, sewers and passages through which water flows except a public sewer.
33

The provisions within this Part shall not apply where a matter would fall within the remit of the Lead Local Flood Authority under the Land Drainage Act 1991 .

34
  • (1) Before beginning to construct any specified work, the undertaker must submit to the Agency for its approval plans of the specified work together with the details of the positioning of any structure within the main river and such further particulars available to it as the Agency may within 28 days of the receipt of the plans reasonably require.
  • (2) Any submission made by the undertaker under sub–paragraph (1), and any approval given by the Agency under this sub–paragraph, may be in respect of all or part of a specified work.
  • (3) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency under sub–paragraph (1) or settled in accordance with paragraph 43 where applicable, and in accordance with any reasonable conditions or requirements specified under this paragraph.
  • (4) Any approval of the Agency required under this paragraph—
  • (a) must not be unreasonably withheld or delayed;
  • (b) is deemed to have been refused if it is neither given nor refused within two months of the submission of the plans or receipt of further particulars if such particulars have been requested by the Agency for approval; and
  • (c) may be given subject to such reasonable requirements as the Agency may have for the protection of any drainage work or for the protection of water resources, or for the prevention of flooding or pollution or in the discharge of its environmental duties.
  • (5) The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (4)(b).
35

Without limiting paragraph 34, the requirements which the Agency may have under that paragraph include conditions requiring the undertaker, at its own expense, to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—

  • (a) to safeguard any drainage work against damage; or
  • (b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,

by reason of any specified work.

36

No buildings will be erected within the area defined by the red dotted line annotated as ‘16m FRAP Line’ on the FRAPA drawings and no material will be stored, within the area defined by the red dotted line annotated as ‘16m FRAP Line’ on the FRAPA drawings, which could create a risk of damage to the integrity of the flood defence structure within this area.

37
  • (1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 35, must be constructed—
  • (a) without unreasonable delay in accordance with the plans approved under this Part of this Schedule; and
  • (b) to the reasonable satisfaction of the Agency,

and the Agency is entitled by its officer to watch and inspect the construction of such works.

  • (2) The undertaker must give to the Agency not less than 14 days' notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is completed.
  • (3) If the Agency reasonably requires, the undertaker must construct all or part of the protective works so that they are in place prior to the construction of any specified work.
  • (4) If any part of a specified work or any protective work required by the Agency is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Agency may by notice in writing require the undertaker at the undertaker's own expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
  • (5) Subject to sub-paragraph (6) and paragraph 41, if, within a reasonable period, being not less than 28 days beginning with the date when a notice under sub-paragraph (4) is served upon the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any expenditure reasonably incurred by the Agency in so doing is recoverable from the undertaker.
  • (6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency must not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined in accordance with paragraph 43.
38
  • (1) Subject to sub–paragraph (6), the undertaker must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation and on land held by the undertaker for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
  • (2) If any such drainage work which the undertaker is liable to maintain is not maintained to the reasonable satisfaction of the Agency, the Agency may by notice in writing require the undertaker to repair and restore the work, or any part of such work, or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work and restore the site to its former condition, to such extent and within such limits as the Agency reasonably requires.
  • (3) Subject to sub–paragraph (5) and paragraph 41, if, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) is received by the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may do what is necessary for such compliance and any expenditure reasonably incurred by the Agency in so doing is recoverable from the undertaker.
  • (4) If there is any failure by the undertaker to obtain a necessary consent or comply with conditions imposed by the Agency in accordance with this Part of this Schedule the Agency may serve written notice requiring the undertaker to cease all or part of the specified works and the undertaker must upon receipt of the notice cease the specified works or part thereof until it has obtained the necessary consent or complied with the condition unless the cessation of the specified works or part thereof would cause greater damage than compliance with the written notice.
  • (5) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2), the Agency must not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined in accordance with paragraph 43.
  • (6) This paragraph does not apply to drainage works which are vested in the Agency, or which the Agency or another person is liable to maintain and is not proscribed by the powers of the Order from doing so.
39

Subject to paragraph 41, if by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work is otherwise damaged, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Agency and if the undertaker fails to do so, the Agency may make good the impairment or damage and recover any expenditure reasonably incurred by the Agency in so doing from the undertaker.

40

If by reason of construction of the specified work the Agency's access to flood defences or equipment maintained for flood defence purposes is materially obstructed, the undertaker must provide such alternative means of access that will allow the Agency to maintain the flood defence or use the equipment no less effectively than was possible before the obstruction within three days of the undertaker becoming aware of such obstruction, unless otherwise agreed with the Agency.

41

The undertaker must indemnify the Agency in respect of all costs, charges and expenses which the Agency may reasonably incur—

  • (a) in the examination or approval of plans under this Part of this Schedule;
  • (b) in the inspection of the construction of the specified works or any protective works required by the Agency under this Part of this Schedule; and
  • (c) in the carrying out of any surveys or tests by the Agency which are reasonably required in connection with the construction of the specified works.
42
  • (1) The undertaker is responsible for and must indemnify the Agency against all costs and losses not otherwise provided for in this Part of this Schedule which may be incurred or suffered by the Agency by reason of—
  • (a) the construction, operation or maintenance of any specified works comprised within the authorised works or the failure of any such works comprised within them; or
  • (b) any act or omission of the undertaker, its employees, contractors or agents or others whilst engaged upon the construction, operation or maintenance of the authorised works or dealing with any failure of the authorised works.
  • (2) For the avoidance of doubt, in sub–paragraph (1)—
  • costs” includes—expenses and charges;staff costs and overheads; andlegal costs;
  • losses” includes physical damage.
  • (3) The undertaker must indemnify the Agency against all liabilities, claims and demands arising out of or in connection with the authorised works or otherwise out of the matters referred to in sub–paragraphs (1)(a) and (1)(b).
  • (4) For the avoidance of doubt, in sub–paragraph (3)—
  • “claims” and “demands” include as applicable—costs (within the meaning of sub–paragraph (2)) incurred in connection with any claim or demand; andany interest element of sums claimed or demanded;
  • liabilities” includes—contractual liabilities;tortious liabilities (including liabilities for negligence or nuisance);liabilities to pay statutory compensation or for breach of statutory duty; andliabilities to pay statutory penalties imposed on the basis of strict liability (but does not include liabilities to pay other statutory penalties).
  • (5) The Agency must give to the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without the agreement of the undertaker, such agreement not to be unreasonably withheld or delayed.
  • (6) The fact that any work or thing has been executed or done by the undertaker in accordance with a plan approved by the Agency, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the undertaker from any liability under the provisions of this Part of this Schedule.
43

Any dispute arising between the undertaker and the Agency under this Part of this Schedule must, if the parties agree, be determined by arbitration under article 42(3) (arbitration) of this Order, but otherwise must be determined by the Secretary of State for Environment, Food and Rural Affairs or its successor on a reference to them by the undertaker or the Agency, after notice in writing by one to the other.

PART 5 — FOR THE PROTECTION OF RAILWAY INTERESTS

44

The following provisions of this Part of this Schedule have effect, unless otherwise agreed in writing between the undertaker and Network Rail and, in the case of paragraph 58, any other person on whom rights or obligations are conferred by that paragraph.

45

In this Part of this Schedule—

  • construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
  • the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
  • network licence” means the network licence, as the same is amended from time to time, granted to Network Rail Infrastructure Limited by the Secretary of State in exercise of his powers under section 8 (licenses) of the Railways Act l993 ;
  • Network Rail” means Network Rail Infrastructure Limited (company number 0204587, whose registered office is at 1 Eversholt Street, London, NW1 2DN) and any associated company of Network Rail Infrastructure Limited which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 (meaning of “subsidiary” etc) of the Companies Act 2006 ) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited;
  • plans” includes sections, designs, design data, software, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
  • protective works” means any works specified by the engineer under paragraph 48(4);
  • railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
  • railway property” means any railway belonging to Network Rail and—any station, land, works, apparatus and equipment belonging to Network Rail or connected with any such railway; andany easement or other property interest held or used by Network Rail for or connected with the purposes of such railway or works, apparatus or equipment; and
  • specified work” means so much of any of the authorised development as is or is to be situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property.
46
  • (1) Where under this Part of this Schedule Network Rail is required to give its consent or approval in respect of any matter, that consent or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
  • (2) In so far as any specified work or the acquisition or use of railway property or rights over railway property is or may be subject to railway operational procedures, Network Rail must—
  • (a) co-operate with the undertaker with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
  • (b) use its reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised development under this Order.
47
  • (1) The undertaker must not exercise the powers conferred by—
  • (a) articles 3 (development consent granted by the Order), 4 (maintenance of authorised development), 13 (temporary prohibition or restriction of use of streets and public rights of way), 14 (permanent stopping up of streets), 15 (access to works), 17 (traffic regulation measures), 18 (discharge of water), 19 (authority to survey and investigate land), 20 (protective works to buildings), 21 (felling or lopping of trees), 22 (compulsory acquisition of land), 24 (compulsory acquisition of rights), 25 (acquisition of subsoil only), 26 (private rights), 27 (power to override easements and other rights), 30 (rights under or over streets), 31 (temporary use of land for carrying out the authorised development), 32 (temporary use of land for maintaining the authorised development), 33 (statutory undertakers), 34 (apparatus and rights of statutory undertakers in stopped up streets), 35 (recovery of costs of new connections); or
  • (b) section 11(3) (powers of entry) of the 1965 Act or the 1981 Act as applied by this Order,

in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.

  • (2) The undertaker must not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
  • (3) The undertaker must not exercise the powers conferred by sections 271 (extinguishment of rights of statutory undertakers: preliminary notices) or 272 (extinguishment of rights of electronic communications code network operators: preliminary notices) of the 1990 Act or article 33 (statutory undertakers) of this Order in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail.
  • (4) The undertaker must not under the powers of this Order acquire or use or acquire new rights over any railway property except with the consent of Network Rail.
  • (5) Where Network Rail is asked to give its consent under this paragraph, such consent must not be unreasonably withheld but may be given subject to reasonable conditions.
48
  • (1) The undertaker must before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration.
  • (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not intimated disapproval of those plans and the grounds of disapproval, the undertaker may serve upon the engineer written notice requiring the engineer to intimate the engineer's approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by the expiry of the further 28 days the engineer has not intimated approval or disapproval, the engineer is to be deemed to have approved the plans as submitted.
  • (3) If by the end of the period of 28 days beginning with the date on which written notice was served upon the engineer under sub-paragraph (2) Network Rail gives notice to the undertaker that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker desires such part of the specified work to be constructed, Network Rail must construct it without unnecessary delay on behalf of and to the reasonable satisfaction of the undertaker in accordance with the plans approved or deemed to be approved or settled under this paragraph, and under the supervision (where appropriate and if given) of the undertaker.
  • (4) When signifying approval of the plans, the engineer may specify any protective works (whether temporary or permanent) which in the engineer's opinion must be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using those railways (including any relocation, decommissioning and removal of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes must be constructed by Network Rail or by the undertaker, if Network Rail so desires, and such protective works must be carried out at the expense of the undertaker in either case without unnecessary delay and the undertaker must not commence the construction of the specified works until the engineer has notified the undertaker that the protective works have been completed to the engineer's reasonable satisfaction.
49
  • (1) Any specified work and any protective works to be constructed by virtue of paragraph 48(4) must, when commenced, be constructed—
  • (a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 48;
  • (b) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
  • (c) in such manner as to cause as little damage as is possible to railway property; and
  • (d) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic on it and the use by passengers of railway property.
  • (2) If any damage to railway property or any such interference or obstruction is caused by the carrying out of, or in consequence of the construction of a specified work or a protective work, the undertaker must, regardless of any such approval, make good such damage and must pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
  • (3) Nothing in this Part of this Schedule imposes any liability on the undertaker with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents or any liability on Network Rail with respect of any damage, costs, expenses or loss attributable to the negligence of the undertaker or its servants, contractors or agents.
50

The undertaker must—

  • (a) at all times afford reasonable facilities to the engineer for access to a specified work or a protective work during its construction; and
  • (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or a protective work or the method of constructing it.
51

Network Rail must at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Part of this Schedule during their construction and must supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.

52
  • (1) If any permanent or temporary alterations or additions to railway property are reasonably necessary in consequence of the construction of a specified work or a protective work, or during a period of 24 months after the completion of that work in order to ensure the safety of railway property or the continued safe operation of the railway of Network Rail, such alterations and additions may be carried out by Network Rail and if Network Rail gives to the undertaker reasonable notice of its intention to carry out such alterations or additions (which must be specified in the notice), the undertaker must pay to Network Rail the reasonable cost of those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
  • (2) If during the construction of a specified work or a protective work by the undertaker, Network Rail gives notice to the undertaker that Network Rail desires itself to construct that part of the specified work or the protective work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the undertaker decides that part of the specified work or protective work is to be constructed, Network Rail must assume construction of that part of the specified work or the protective work and the undertaker must, regardless of any such approval of a specified work or the protective work under paragraph 48(2) pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work or protective work.
  • (3) The engineer must, in respect of the capitalised sums referred to in this paragraph and paragraph 53(a) provide such details of the formula by which those sums have been calculated as the undertaker may reasonably require.
  • (4) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving must be set off against any sum payable by the undertaker to Network Rail under this paragraph.
53

The undertaker must repay to Network Rail all reasonable fees, costs, charges and expenses reasonably incurred by Network Rail—

  • (a) in constructing any part of a specified work on behalf of the undertaker as provided by paragraph 48(4) or in constructing any protective works under the provisions of paragraph 48(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.