The South Humber Bank Energy Centre Order 2021
Made: 10th November 2021
Coming into force: 2nd December 2021
Accordingly, the Secretary of State, in exercise of the powers conferred by sections 114, 115 and 120 of the 2008 Act, makes the following Order—
PART 1 — PRELIMINARY
Citation and commencement
1
This Order may be cited as the South Humber Bank Energy Centre Order 2021 and comes into force on 2nd December 2021.
Interpretation
2
- (1) In this Order—
- “the 1961 Act” means the Land Compensation Act 1961[^f00004];
- “the 1980 Act” means the Highways Act 1980[^f00005];
- “the 1990 Act” means the Town and Country Planning Act 1990[^f00006];
- “the 1991 Act” means the New Roads and Street Works Act 1991[^f00007];
- “the 2008 Act” means the Planning Act 2008[^f00008];
- “the 2009 Regulations” means the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009[^f00009];
- “access and rights of way plan” means the plan submitted under regulation 5(2)(k) of the 2009 Regulations and certified as such by the Secretary of State for the purposes of this Order;
- “address” includes any number or address used for the purposes of electronic transmission;
- “Anglian Water” means Anglian Water Services Limited (company number 2366656) whose registered address is Lancaster House Lancaster Way, Ermine Business Park, Huntingdon, Cambridge, United Kingdom PE29 6XU;
- “AOD” means above ordnance datum;
- “apparatus” has the same meaning as in Part 3 of the 1991 Act (street works in England and Wales) save that “apparatus” further includes pipelines (and parts of them), aerial markers, cathodic protection test posts, field boundary markers, transformer rectifier kiosks, electricity cables, telecommunications equipment and electricity cabinets;
- “authorised development” means the development and associated development described in Schedule 1 (authorised development) to this Order, which is development within the meaning of section 32 of the 2008 Act (meaning of “development”);
- “biodiversity strategy” means the biodiversity strategy dated April 2021 and certified as such by the Secretary of State for the purposes of this Order;
- “the book of reference” means the book of reference submitted under regulation 5(2)(d) of the 2009 Regulations and certified as such by the Secretary of State for the purposes of this Order;
- “building” includes any structure or erection or any part of a building, structure or erection;
- “carriageway” has the same meaning as in the 1980 Act;
- “the charge” means the charge held by Lloyds Bank plc registered at HM Land Registry against title number HS239444 dated 18 December 2018;
- “commence” means the carrying out of a material operation comprised in or carried out for the purposes of the authorised development and the words “commencement” and “commenced” and cognate expressions are to be construed accordingly;
- “electronic transmission” means a communication transmitted— by means of an electronic communications network; or by other means but while in electronic form;
- “the environmental statement” means the environmental statement submitted under regulation 5(2)(a) of the 2009 Regulations and certified as such by the Secretary of State for the purposes of this Order;
- “EP Waste Management Limited” means EP Waste Management Limited (Company No. 12144128) whose registered office is Paradigm Building, 3175 Century Way, Thorpe Park, Leeds, United Kingdom LS15 8ZB;
- “EP SHB Limited” means EP SHB Limited (Company No. 02571241) whose registered office is Berger House, 36-38 Berkeley Square, London, United Kingdom W1J 5AE;
- “footpath” and “footway” have the same meaning as given in section 329(1) of the 1980 Act;
- “framework construction traffic management plan” means the plan dated December 2020 included as annex 28 of appendix 9A of the environmental statement;
- “highway” and “highway authority” have the same meaning as in the 1980 Act;
- “the indicative landscape strategy” means the indicative landscape strategy submitted under regulation 5(2)(q) of the 2009 Regulations and certified as such by the Secretary of State for the purposes of this Order;
- “the indicative lighting strategy” means the indicative lighting strategy submitted under regulation 5(2)(q) of the 2009 Regulations and certified as such by the Secretary of State for the purposes of this Order;
- “the land plans” means the land plans submitted under regulation 5(2)(i) of the 2009 Regulations and certified as such by the Secretary of State for the purposes of this Order;
- “Lloyds Bank plc” means Lloyds Bank plc (Company No. 00002065) whose registered office is 25 Gresham Street, London, EC2V 7HN;
- “maintain” includes (i) inspect, repair, adjust, alter, refurbish or improve the authorised development and (ii) in relation to any part (but not the whole of the authorised development) remove, reconstruct or replace that part provided those works do not give rise to materially new or materially different environmental effects; and “maintenance” and “maintaining” are to be construed accordingly;
- “material operation” has the same meaning as in section 155 of the 2008 Act;
- “National Grid” means National Grid Electricity Transmission plc or National Grid Gas plc as the context requires;
- “National Grid Electricity Transmission plc” means National Grid Electricity Transmission plc (Company No. 2366977) whose registered office is at 1-3 Strand, London WC2N 5EH;
- “National Grid Gas plc” means National Grid Gas plc (Company No. 2006000) whose registered office is at 1-3 Strand, London WC2N 5EH;
- “Network Rail” means Network Rail Infrastructure Limited (Company No. 02904587) whose registered office is at 1 Eversholt Street, London NW1 2DN;
- “the Order limits” means the limits shown on the works plans within which the authorised development may be carried out;
- “owner”, in relation to land, has the same meaning as in section 7 of the Acquisition of Land Act 1981 (interpretation)[^f00010];
- “public sewer or drain” means a sewer or drain which belongs to Homes England, the Environment Agency, a harbour authority within the meaning of section 57 of the Harbours Act 1964 (interpretation)[^f00011], an internal drainage board, a joint planning board, a local authority, a National Park Authority, a sewerage undertaker or an urban development corporation;
- “relevant planning authority” means the planning authority for the area in which the land to which the provisions of this Order apply is situated;
- “requirements” means those matters set out in Schedule 2 (requirements) to this Order;
- “requirements discharge schedule” means a document setting out the following information— the submissions and approvals that have been made in relation to each condition attached to the SHBEC planning permission; the submissions and approvals that the undertaker anticipates are required pursuant to each requirement; details of any outstanding applications for discharge of conditions attached to the SHBEC planning permission and which will be subject to article 5(2)(b)(iii); and any steps to which paragraph 36 of Schedule 2 applies;
- “section 106 agreement” means the agreement made pursuant to section 106 of the 1990 Act between North East Lincolnshire Borough Council and EP SHB Limited dated 11 April 2019 as varied by a deed of variation made between the same parties dated 19 April 2021;
- “SHBEC planning permission” means the planning permission for an energy from waste generating station of up to 49.9MW gross generation, granted by North East Lincolnshire Council on 12 April 2019 with reference DM/1070/18/FUL and including any variation and amendment to it;
- “statutory undertaker” means any person falling within section 127(8) of the 2008 Act (statutory undertakers’ land);
- “street” means a street within the meaning of section 48 of the 1991 Act (streets, street works and undertakers), together with land on the verge of a street or between two carriageways, and includes any footpath and “street” includes any part of a street;
- “street authority”, in relation to a street, has the same meaning as in Part 3 of the 1991 Act;
- “street works” means the works listed in article 10(1);
- “swept path analysis plan” means the site entrance swept path analysis and visibility splay drawings dated January 2021 or such other alternative plan as the highway authority may approve;
- “undertaker” means EP Waste Management Limited or a person who has the benefit of this Order in accordance with articles 8 and 9;
- “varied condition” means a condition of the SHBEC planning permission— that is imposed at any time under a new planning permission pursuant to section 73 of the 1990 Act (determination of applications to develop land without compliance with conditions previously attached) and which is in variance with the conditions under the original SHBEC planning permission as issued on 12 April 2019; which has at any time been varied pursuant to section 96A of the 1990 Act (power to make non-material changes to planning permission or permission in principle); or where the numbering of the condition has changed compared to the numbering as originally issued on 12 April 2019;
- “watercourse” includes all rivers, streams, ditches, drains, canals, cuts, culverts, dykes, sluices, sewers and passages through which water flows except a public sewer or drain;
- “working day” means any day other than a Saturday, Sunday or English bank or other public holiday; and
- “the works plans” means the works plans submitted under regulation 5(2)(j) of the 2009 Regulations and certified as the works plans by the Secretary of State for the purposes of this Order.
- (2) All distances, directions, measurements and lengths referred to in this Order are approximate, except the measurements and lengths set out in requirement 3.
- (3) All areas described in square metres in the book of reference are approximate.
- (4) References in this Order to “numbered works” or “Work No” are references to the works comprising the authorised development as numbered in Schedule 1 (authorised development) and shown on the works plans.
- (5) The expression “includes” is to be construed without limitation.
Electronic Communications
3
- (1) In this Order, subject to Article 26—
- (a) references to documents, plans, drawings, certificates, or to copies, include references to them in electronic form; and
- (b) references to a form of communication being “in writing” include references to an electronic communication that satisfies the conditions in paragraph (3); and “written” and cognate expressions are to be construed accordingly.
- (2) If an electronic communication is received outside the recipient’s business hours, it is to be taken to have been received on the next working day.
- (3) The conditions are that the communication is—
- (a) capable of being accessed by the recipient;
- (b) legible in all material respects; and
- (c) sufficiently permanent to be used for subsequent reference.
- (4) For the purposes of paragraph (3) (b), a communication is legible in all material respects if the information contained in it is available to the recipient to no lesser extent than it would be if transmitted by means of a document in printed form.
- (5) In this article “electronic communication” has the meaning given in section 15(1) of the Electronic Communications Act 2000 (general interpretation)[^f00012].
PART 2 — PRINCIPAL POWERS
Development consent etc. granted by the Order
4
- (1) Subject to the provisions of this Order the undertaker is granted development consent for the authorised development to be carried out within the Order limits.
- (2) Each numbered work must be situated within the corresponding numbered area shown on the works plans and within the limits of deviation.
- (3) In paragraph (2), “limits of deviation” means the limits of deviation shown for each work number on the works plans.
Effect of the Order on the SHBEC planning permission
5
- (1) The undertaker must not commence any part of the authorised development pursuant to this Order until notice has been served on the relevant planning authority.
- (2) If the undertaker serves a notice under this article—
- (a) there must be no further development under the SHBEC planning permission; and
- (b) from the date of the undertaker’s notice—
- (i) the conditions of the SHBEC planning permission will cease to have effect within the Order limits;
- (ii) the requirements apply to development that has taken place or is to take place within the Order limits and which is comprised in the authorised development; and
- (iii) any application for discharge of a condition listed in column (1) of Schedule 3 (deemed approval of matters referred to in requirements) which was outstanding at the date of the undertaker’s notice will be treated as an application for discharge of the corresponding requirement listed in column (2) of Schedule 3.
- (3) Despite paragraph (1), the undertaker may exercise any other powers under this Order in respect of any part of the authorised development prior to, or following service of, notice under paragraph (2).
- (4) Without prejudice to the generality of paragraph (3), the undertaker may seek an approval under or take any other action in relation to any requirement prior to or following the service of notice under paragraph (1).
- (5) Subject to paragraph (6), where details, plans or any other matters have been approved or agreed by the relevant planning authority under a condition of the SHBEC planning permission in column (1) of Schedule 3 prior to the date on which the undertaker serves notice under paragraph (1) they are deemed to have been approved for the purpose of the corresponding requirement in column (2) of Schedule 3 from the date of the undertaker’s notice.
- (6) Paragraph (5) does not apply to a varied condition unless the relevant planning authority issues a notice pursuant to paragraph (7).
- (7) The relevant planning authority may issue a notice to the undertaker confirming—
- (a) that the discharge of details, plans or other matters in paragraph (5) applies to a varied condition; and
- (b) the number of the relevant condition and requirement to which the deemed discharge applies in cases where the numbering of the conditions of the SHBEC planning permission has changed compared to those as originally issued on 12 April 2019.
- (8) Where paragraph (7)(b) applies, the numbering of the corresponding condition and requirement in Schedule 3 does not apply.
- (9) The relevant planning authority may only issue a notice pursuant to paragraph (7) where it has been demonstrated to the satisfaction of that authority that the application of paragraph (5) will not give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
- (10) The undertaker must issue a requirements discharge schedule with a notice served under paragraph (2).
- (11) The relevant planning authority must, within three weeks of receipt of the requirements discharge schedule, notify the undertaker that the details set out in the requirements discharge schedule—
- (a) are agreed; or
- (b) are not agreed.
- (12) Where paragraph (11)(b) applies, the relevant planning authority must provide details of the parts which it considers are not correct.
- (13) The relevant planning authority must include a copy of a notice served by the undertaker under paragraph (2) and a copy of the relevant planning authority’s notice under paragraph (11) in the planning register.
- (14) In this article, “planning register” means the register which the relevant planning authority is required to maintain pursuant to section 69 of the 1990 Act (register of applications etc.)[^f00013].
Maintenance of authorised development
6
- (1) The undertaker is authorised to, and may at any time, maintain the authorised development subject to any provision in this Order, including the requirements, or to an agreement made under this Order.
- (2) This article only authorises the carrying out of maintenance works within the Order limits.
Operation of authorised development
7
- (1) The undertaker is authorised to use and operate the generating station comprised in the authorised development.
- (2) This article does not relieve the undertaker of any requirement to obtain any permit or licence or any obligation under any legislation that may be required to authorise the operation of a generating station.
Benefit of the Order
8
- (1) Subject to paragraph (2) and article 9 (consent to transfer benefit of Order), the provisions of this Order have effect solely for the benefit of the undertaker.
- (2) Paragraph (1) does not apply to Work No. 2(e) in respect of which the Order is for the benefit of the undertaker and EP SHB Limited.
Consent to transfer benefit of the Order
9
- (1) Subject to paragraph (4) the undertaker may—
- (a) transfer to another person (“the transferee”) any or all of the benefit of the provisions of this Order (including any of the numbered works) and such related statutory rights as may be agreed in writing between the undertaker and the transferee; or
- (b) grant to another person (“the lessee”) for a period agreed between the undertaker and the lessee any or all of the benefit of the provisions of this Order (including any of the numbered works) and such related statutory rights as may be agreed in writing between the undertaker and the lessee.
- (2) Where an agreement has been made in accordance with paragraph (1) references in this Order to the undertaker, except in paragraph (3), include references to the transferee or the lessee.
- (3) The exercise by a person of any benefits or rights conferred in accordance with any transfer or grant under paragraph (1) is subject to the same restrictions, liabilities and obligations as would apply under this Order if those benefits or rights were exercised by the undertaker.
- (4) The consent of the Secretary of State is required for the exercise of the powers in paragraph (1) except where the transferee or lessee is—
- (a) the holder of a licence under section 6 of the Electricity Act 1989 (licences authorising supply, etc.)[^f00014];
- (b) in relation to a transfer or lease of utility or other infrastructure connection works, the relevant statutory undertaker or licence holder; or
- (c) in relation to a transfer or lease of any works within a highway, a highway authority responsible for the relevant highway.
- (5) Where the consent of the Secretary of State is not required under paragraph (4) the undertaker must notify the Secretary of State in writing before transferring or granting a benefit referred to in paragraph (1).
- (6) The notification referred to in paragraph (5) must state—
- (a) the name and contact details of the person to whom the benefit of the powers are to be transferred or granted;
- (b) subject to paragraph (7), the date on which the transfer is proposed to take effect;
- (c) the powers to be transferred or granted;
- (d) the restrictions, liabilities and obligations that are to apply to the person exercising the powers transferred or granted under paragraph (3); and
- (e) where relevant, a plan showing the works or areas to which the transfer or grant relates.
- (7) The date specified under paragraph (6)(b) must not be earlier than the expiry of five working days from the date of the receipt of the notice.
- (8) The notice given under paragraph (6) must be signed by the undertaker and the person to whom the benefit of the powers are to be transferred or granted as specified in that notice.
- (9) In this article “relevant statutory undertaker” or “licence holder” means a body—
- (a) who falls within section 127(8) of the 2008 Act (statutory undertakers’ land), is a holder of a licence granted under a statute or other regulatory framework; and
- (b) whose duties under the licence include owning, operating or maintaining utilities and or infrastructure and their connections.
PART 3 — STREETS
Street works
10
- (1) The undertaker may, for the purposes of the authorised development, enter the streets specified in Schedule 4 (streets subject to street works) and may—
- (a) break up or open the street, or any sewer, drain or tunnel under it;
- (b) tunnel or bore under the street;
- (c) place apparatus in the street;
- (d) maintain apparatus in the street, change its position or remove it; and
- (e) execute any works required for or incidental to any works referred to in sub-paragraphs (a) to (d).
- (2) The authority given by paragraph (1) is a statutory right for the purposes of sections 48(3) (streets, street works and undertakers) and 51(1) (prohibition of unauthorised street works) of the 1991 Act.
- (3) Where the person carrying out any works under paragraph (1) is not the street authority the provisions of sections 54 (advance notice of certain works) to 106 (index of defined expressions) of the 1991 Act apply to any such works.
Power to alter layout, etc., of streets
11
- (1) The undertaker may for the purposes of the authorised development alter the layout of, or carry out any works in, the street specified in column (2) of Schedule 5 (streets subject to permanent alteration of layout) in the manner specified in column (3).
- (2) Without prejudice to the specific powers conferred by paragraph (1), but subject to paragraphs (3) and (4), the undertaker may for the purposes of constructing and maintaining the authorised development alter the layout of any street or construct any works in the street and, without limitation on the scope of this paragraph—
- (a) alter the level or increase the width of any kerb, footway, cycle track or verge; and
- (b) make and maintain passing places.
- (3) The undertaker must restore any street that has been temporarily altered under this article to the reasonable satisfaction of the street authority.
- (4) The powers conferred by paragraph (2) may not be exercised without the consent of the street authority.
- (5) Paragraphs (3) and (4) do not apply where the undertaker is the street authority for a street in which the works are being constructed.
Construction and maintenance of new or altered means of access
12
- (1) The means of access specified in Part 1 (those parts of the access to be maintained at the public expense) of Schedule 6 (access) to be constructed under this Order must be completed to the reasonable satisfaction of the highway authority and, unless otherwise agreed by the highway authority, must be maintained by and at the expense of the undertaker for a period of 12 months from their completion and from the expiry of that period by and at the expense of the highway authority.
- (2) Those parts of each means of access specified in Part 2 (those parts of the access to be maintained by the street authority) of Schedule 6 (access) to be constructed under this Order and which are not intended to be a public highway must be completed to the reasonable satisfaction of the street authority and must be maintained by and at the expense of the undertaker for a period of 12 months from their completion and from the expiry of that period by and at the expense of the street authority.
- (3) In any action against the undertaker in respect of loss or damage resulting from any failure by it to maintain a street under this article, it is a defence (without prejudice to any other defence or the application of the law relating to contributory negligence) to prove that the undertaker had taken such care as in all the circumstances was reasonably required to secure that the part of the street to which the action relates was not dangerous to traffic.
- (4) For the purposes of a defence under paragraph (3), a court must in particular have regard to the following matters—
- (a) the character of the street including the traffic which was reasonably to be expected to use it;
- (b) the standard of maintenance appropriate for a street of that character and used by such traffic;
- (c) the state of repair in which a reasonable person would have expected to find the street;
- (d) whether the undertaker knew, or could reasonably have been expected to know, that the condition of the part of the street to which the action relates was likely to cause danger to users of the street; and
- (e) where the undertaker could not reasonably have been expected to repair that part of the street before the cause of action arose, what warning notices of its condition had been displayed,
but for the purposes of such a defence it is not relevant that the undertaker had arranged for a competent person to carry out or supervise the maintenance of that part of the street to which the action relates unless it is also proved that the undertaker had given that person proper instructions with regard to the maintenance of the street and that those instructions had been carried out.
- (5) Nothing in this article—
- (a) prejudices the operation of section 87 of the 1991 Act (prospectively maintainable highways); and the undertaker is not by reason of any duty under that section to maintain a street to be taken to be a street authority in relating to that street for the purposes of Part 3 of that Act (street works in England and Wales); or
- (b) has effect in relation to the street works with regard to which the provisions of Part 3 of the 1991 Act apply.
- (6) Paragraphs (1) and (2) do not apply to any works which are carried out under an agreement made with the street authority pursuant to the 1980 Act.
Temporary stopping up of streets and public rights of way
13
- (1) The undertaker may, during and for the purposes of carrying out and maintaining the authorised development, temporarily stop up, alter or divert any street or public right of way and may for any reasonable time—
- (a) divert the traffic or a class of traffic from the street or public right of way; and
- (b) subject to paragraph (2), prevent all persons from passing along the street or public right of way.
- (2) The undertaker must provide reasonable access for pedestrians going to or from premises abutting a street or public right of way affected by the temporary stopping up, alteration or diversion of a street or public right of way under this article if there would otherwise be no such access.
- (3) Without prejudice to the generality of paragraph (1), the undertaker may temporarily stop up, alter or divert the streets specified in column (2) of Schedule 7 (streets to be temporarily stopped up) to the extent specified in column (3) of that Schedule.
- (4) The undertaker may not temporarily stop up, alter or divert—
- (a) any street or public right of way specified in paragraph (3) without first consulting the highway authority; and
- (b) any other street or public right of way without the consent of the highway authority and the highway authority may attach reasonable conditions to any such consent.
- (5) Any person who suffers loss by the suspension of any private right of way under this article is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act (determination of questions of disputed compensation).
- (6) Without prejudice to the scope of paragraph (1), the undertaker may use any street or public right of way which has been temporarily stopped up under the powers conferred by this article and within the Order limits as a temporary working site.
Agreements with street authorities
14
- (1) A street authority and the undertaker may enter into agreements with respect to—
- (a) the construction of any new street including any structure carrying the street over or under any part of the authorised development;
- (b) the strengthening, improvement, repair or reconstruction of any street under the powers conferred by this Order;
- (c) the maintenance of the structure of any bridge or tunnel carrying a street;
- (d) any stopping up, alteration or diversion of a street authorised by this Order;
- (e) the undertaking in the street of any of the works referred to in article 12(1) (construction and maintenance of new or altered means of access); or
- (f) the adoption, by a street authority which is the highway authority, of works—
- (i) undertaken on a street which is a publicly maintainable highway; and
- (ii) which the undertaker and highway authority agree are to be adopted as a publicly maintainable highway.
- (2) If such an agreement provides that the street authority must undertake works on behalf of the undertaker the agreement may, without prejudice to the generality of paragraph (1)—
- (a) make provision for the street authority to carry out any function under this Order which relates to the street in question;
- (b) specify a reasonable time for the completion of the works; and
- (c) contain such terms as to payment and otherwise as the parties consider appropriate.
PART 4 — SUPPLEMENTAL POWERS
Discharge of water
15
- (1) The undertaker may use any watercourse or any public sewer or drain for the drainage of water in connection with the carrying out or maintenance of the authorised development and for that purpose may lay down, take up and alter pipes and may, on any land within the Order limits, make openings into, and connections with, the watercourse, public sewer or drain.
- (2) Any dispute arising from the making of connections to or the use of a public sewer or drain by the undertaker under paragraph (1) is to be determined as if it were a dispute under section 106 of the Water Industry Act 1991 (right to communicate with public sewers)[^f00015].
- (3) The undertaker must not discharge any water into any watercourse, public sewer or drain except with the consent of the person to whom it belongs; and such consent may be given subject to such terms and conditions as that person may reasonably impose.
- (4) The undertaker must not make any opening into any public sewer or drain except—
- (a) in accordance with plans approved by the person to whom the sewer or drain belongs; and
- (b) where that person has been given the opportunity to supervise the making of the opening.
- (5) Except as authorised under this Order, the undertaker must not, in constructing or maintaining works, damage or interfere with the bed or banks of any watercourse forming part of a main river.
- (6) The undertaker must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain under this article is as free as may be practicable from gravel, soil or other solid substance, oil or matter in suspension.
- (7) This article does not authorise the entry into controlled waters of any matter whose entry or discharge into controlled waters requires a licence under the Environmental Permitting (England and Wales) Regulations 2016[^f00016].
- (8) In this article expressions, excluding “public sewer or drain” and “watercourse”, used both in this article and in the Water Resources Act 1991[^f00017], have the same meaning as in that Act.
Authority to survey and investigate the land
16
- (1) The undertaker may for the purposes of this Order enter on any land shown within the Order limits or which may be affected by the authorised development and—
- (a) survey or investigate the land;
- (b) without prejudice to the generality of sub-paragraph (a), make trial holes in such positions on the land as the undertaker thinks fit to investigate the nature of the surface layer and subsoil and remove soil samples;
- (c) without prejudice to the generality of sub-paragraph (a), carry out ecological or archaeological investigations on such land; and
- (d) place on, leave on and remove from the land apparatus for use in connection with the survey and investigation of land and making of trial holes.
- (2) No land may be entered or equipment placed or left on or removed from the land under paragraph (1) unless at least 14 days’ notice has been served on every owner and occupier of the land.
- (3) Any person entering land under this article on behalf of the undertaker—
- (a) must, if so required, produce written evidence of their authority to do so; and
- (b) may take with them such vehicles and equipment as are necessary to carry out the survey or investigation or to make the trial holes.
- (4) No trial holes are to be made under this article—
- (a) in land located within the highway boundary without the consent of the highway authority; or
- (b) in a private street without the consent of the street authority.
- (5) The undertaker must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the authority conferred by this article, such compensation to be determined, in case of dispute, under Part 1 of the 1961 Act (determination of questions of disputed compensation).
PART 5 — OPERATIONS
Felling or lopping of trees
17
- (1) The undertaker may fell or lop any tree or shrub near any part of the authorised development, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—
- (a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or
- (b) from constituting a danger to persons using the authorised development.
- (2) In carrying out any activity authorised by paragraph (1), the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.
- (3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined under Part 1 of the 1961 Act (determination of questions of disputed compensation).
- (4) The undertaker may not pursuant to paragraph (1) fell or lop a tree within the extent of the highway maintainable at the public expense without the consent of the highway authority.
- (5) Save in the case of emergency, the undertaker must not enter any land under paragraph (1) without serving notice of the intended entry on the owners and occupiers of that land and, where the land is a highway maintainable at the public expense, on the highway authority.
- (6) The notice under paragraph (5) must be served not less than 14 days before entering the land.
- (7) In carrying out any activity authorised by paragraph (1) the duty contained in section 206(1) of the 1990 Act[^f00018] (replacement of trees) does not apply.
PART 6 — MISCELLANEOUS AND GENERAL
Protective provisions
18
Schedule 8 (protective provisions) has effect.
Statutory undertakers
19
Subject to the provisions of Schedule 8 (protective provisions), the undertaker may reposition the apparatus belonging to statutory undertakers.
Apparatus and rights of statutory undertakers in stopped up streets
20
Where a street is temporarily altered or diverted or its use is temporarily stopped up under article 12 (construction and maintenance of new or altered means of access) or article 13 (temporary stopping up of streets and public rights of way) any statutory utility whose apparatus is under, in, on, along or across the street is to have the same powers and rights in respect of that apparatus, subject to Schedule 8 (protective provisions), as if this Order had not been made.
Recovery of costs of new connections
21
- (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 20 (apparatus and rights of statutory undertakers in stopped up streets) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
- (2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 20 (apparatus and rights of statutory undertakers in stopped up streets), any person who is—
- (a) the owner or occupier of premises the drains of which communicated with that sewer; or
- (b) the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
- (3) This article does not have effect in relation to apparatus to which article 20 (apparatus and rights of statutory undertakers in stopped up streets) or Part 3 of the 1991 Act (street works in England and Wales) applies.
- (4) In this article—
- (a) “public communications provider” has the same meaning as in section 151(1) of the Communications Act 2003[^f00019] (interpretation of chapter 1); and
- (b) “public utility undertaker” has the same meaning as in the 1980 Act.
Application of landlord and tenant law
22
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
- (3) Accordingly, no such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for purposes of the 1990 Act
23
Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being operational land).
Defence to proceedings in respect of statutory nuisance
24
- (1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 1990 (summary proceedings by persons aggrieved by statutory nuisances)[^f00020] in relation to a nuisance falling within section 79(1)(g) of that Act (statutory nuisances and inspections therefor) no order is to be made, and no fine may be imposed, under section 82(2) of that Act if—
- (a) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the construction of the authorised development in accordance with a notice served under section 60 (control of noise on construction sites), or a consent given under section 61 (prior consent for work on construction sites) or 65 (noise exceeding registered level), of the Control of Pollution Act 1974[^f00021]; or
- (ii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or
- (b) the defendant shows that the nuisance is a consequence of the use of the authorised development and that it cannot reasonably be avoided.
- (2) Section 61(9) of the Control of Pollution Act 1974 (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990), does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.
Certification of plans, etc.
25
- (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
- (a) the access and rights of way plan;
- (b) the book of reference;
- (c) the environmental statement;
- (d) the land plans;
- (e) the works plans;
- (f) the indicative lighting strategy;
- (g) the biodiversity strategy;
- (h) the framework construction traffic management plan;
- (i) the swept path analysis plan; and
- (j) the indicative landscape strategy;
for certification that they are true copies of the documents referred to in this Order.
- (2) A plan or document so certified is admissible in any proceedings as evidence of the contents of the document of which it is a copy.
Service of notices
26
- (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
- (a) by post;
- (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
- (c) with the consent of the recipient and subject to paragraphs (6) to (8), by electronic transmission.
- (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
- (3) For the purposes of section 7 of the Interpretation Act 1978 (references to service by post)[^f00022] as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address and otherwise—
- (a) in the case of the secretary or clerk of that body corporate, the registered or principal office of that body; and
- (b) in any other case, the last known address of that person at that time of service.
- (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
- (a) addressing it to that person by the description of “owner”, or as the case may be “occupier” of the land (describing it); and
- (b) either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
- (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
- (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
- (b) the notice or document is capable of being accessed by the recipient;
- (c) the notice or document is legible in all material respects; and
- (d) in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.
- (9) This article does not exclude the employment of any method of service not expressly provided for by it.
Procedure in relation to certain approvals, etc.
27
- (1) Where an application is made to, or a request is made of, the relevant planning authority, a highway authority, a street authority, or the owner of a watercourse, sewer or drain for any consent, agreement or approval required or contemplated by any of the provisions of the Order, not including the requirements, such consent, agreement or approval must be given in writing and must not be unreasonably withheld or delayed.
- (2) Save for applications made in relation to requirements, if, within eight weeks after the application or request has been submitted to an authority or an owner as referred to in paragraph (1) of this article (or such longer period as may be agreed in writing with the undertaker) it has not notified the undertaker of its decision (and if it is a disapproval the grounds of disapproval), it is deemed to have approved the application or request.
Requirements, appeals etc.
28
- (1) Where an application is made to the relevant planning authority for any consent, agreement or approval required by a requirement the undertaker may appeal, in the event that—
- (a) the relevant planning authority refuses that consent, agreement or approval or grants it subject to conditions;
- (b) the relevant planning authority does not give notice of its decision to the undertaker within eight weeks after the application has been made to the relevant planning authority or such other period that has been agreed by the undertaker and the relevant planning authority;
- (c) on receipt of a request for any further information, the undertaker considers that either the whole or part of the specific information requested by the relevant authority is not necessary for consideration of the application; or
- (d) on receipt of any further information requested, the relevant planning authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The appeal process is to be as follows—
- (a) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the relevant planning authority and any consultee required to be consulted pursuant to the requirement which is the subject of the appeal (together with the undertaker, these are the “appeal parties”);
- (b) as soon as is practicable after receiving the appeal documentation, the Secretary of State must appoint a person (“the appointed person”) to determine the appeal and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for their attention should be sent, the date of such notification being the “start date” for the purposes of this paragraph (2);
- (c) the relevant planning authority and any consultee required to be consulted pursuant to the requirement which is the subject of the appeal must submit written representations to the appointed person in respect of the appeal within ten working days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (d) the appeal parties must make any counter-submissions to the appointed person within ten working days of receipt of written representations pursuant to sub-paragraph (c); and
- (e) the appointed person must make their decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable and in any event within thirty working days of the deadline for the receipt of counter-submissions pursuant to sub-paragraph (d).
- (3) The appointment of the person pursuant to paragraph (2)(b) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (4) In the event that the appointed person considers that further information is necessary to consider the appeal, the appointed person must notify the appeal parties in writing specifying the further information required and the date by which the information is to be submitted and the appointed person must make any notification and set the date for the receipt of such further information having regard to the timescales in paragraph (2).
- (5) Any further information required under paragraph (4) must be provided by the appeal party from whom the further information was requested to the appointed person and the other appeal parties on the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within ten working days of the specified date but otherwise is to be in accordance with the process and time limits set out in paragraphs (2)(c) to (2)(e).
- (6) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the relevant planning authority (whether the appeal relates to that part of it or not).
- (7) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the relevant time limits.
- (8) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case and may deal with the application as if it had been made to the appointed person in the first instance.
- (9) The decision of the appointed person on an appeal is to be final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (10) If an approval is given by the appointed person pursuant to this article, it is to be deemed to be an approval for the purpose of Schedule 2 as if it had been given by the relevant planning authority. The relevant planning authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person’s determination.
- (11) Save where a direction is given pursuant to paragraph (12) requiring the costs of the appointed person to be paid by the relevant planning authority, the reasonable costs of the appointed person must be met by the undertaker.
- (12) On application by the relevant planning authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Planning Practice Guidance: Appeals (March 2014) or any circular or guidance which may from time to time replace it.
Arbitration
29
- (1) Any difference under any provision of this Order, unless otherwise provided for, is to be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.
- (2) This article does not apply where any difference under any provision of this Order is between any person and the Secretary of State.
SCHEDULE 1 — AUTHORISED DEVELOPMENT
In the Borough of North East Lincolnshire a nationally significant infrastructure project as defined in sections 14(1)(a) (nationally significant infrastructure projects: general) and 15 (generating stations) of the 2008 Act and associated development within the meaning of section 115(2) (development for which development consent may be granted), comprising—
- Work No. 1— an electricity generating station located on land at the South Humber Bank Power Station Site, South Marsh Road, near Stallingborough, Lincolnshire, fuelled by refuse derived fuels, with a capacity to process up to 753,500 tonnes of refuse derived fuel per annum, with a gross generation capacity of up to 95 megawatts at ISO conditions comprising the following works—fuel reception and storage facilities, consisting of vehicle ramps, a tipping hall, shredder, fuel storage bunker and cranes;a combustion system housed within a boiler hall, consisting of two combustion lines and associated boilers;a steam turbine and generator housed within a turbine hall with a cooling system comprising fin fan coolers;a bottom ash handling system, including ash storage;a flue gas treatment system, including residue and reagent silos;a silo or tank for the storage of ammonia or urea based reagents;an air-cooled condenser;a compressed air system;a process effluent storage tank;a demineralised water treatment plant and demineralised water storage tanks; andindoor storage tanks for boiler water treatment chemicals.
- Work No. 1A— two emissions stacks and associated emissions monitoring systems.
- Work No. 1B— administration block, including control room, workshops, stores and welfare facilities.In connection with and in addition to Work No.s 1, 1A and 1B—an electrical switchyard, including generator transformers;auxiliary diesel generators and diesel storage tanks;pipe racks, pipe runs and cabling;fire water pump house and fire water tank;internal vehicle access roads, crossings and pedestrian and cycle facilities and routes;security gatehouse, barriers and enclosures;weighbridges;car parking;heavy goods vehicle holding area and driver welfare facilities;a surface water drainage system, including oil-water separators and attenuation pond; andconnections between parts of Work No. 1 and each connection comprised in Work No. 2.
- Work No. 2comprising associated development—an underground or overground electrical connection from Work No. 1;an underground gas supply pipeline to Work No. 1;towns water connection;telecommunications connections;steam connection; andother utility connections.
- Work No. 3— associated development being landscaping and biodiversity works, comprising soft landscaping including planting and biodiversity mitigation and enhancement measures.
- Work No. 4— associated development comprising a new site access on to South Marsh Road and works to an existing access on to South Marsh Road.
- Work No. 5— associated development comprising temporary construction and laydown areas comprising hard standing; laydown and open storage areas, including materials and plant storage; contractor compounds and construction staff office and welfare facilities; generators; concrete batching facilities; vehicle and cycle parking facilities; pedestrian and cycle routes and facilities; security fencing and gates; external lighting; roadways and haul routes; wheel wash facilities and signage.In connection with and in addition to Work No.s 1, 1A, 1B, 2, 3, 4 and 5, further associated development including—external lighting, including lighting columns;security fencing, gates, boundary treatment and other means of enclosure;closed circuit television cameras and columns and other security measures;surface and foul water drainage systems, oil-water separators, including channelling, culverting, crossings and works to existing drainage ditches and systems;electric, gas, water, telecommunication and other infrastructure connections and works, and works to alter such services and utilities connections;hard and soft landscaping;biodiversity mitigation and enhancement measures;site establishment and preparation works, including site clearance (including vegetation removal); earthworks (including soil stripping and storage and site levelling) and excavations; temporary fencing; the creation of temporary construction access points; and the temporary alteration of the position of services and utilities apparatus and connections;temporary construction laydown areas and contractor facilities, including materials and plant storage and laydown areas; generators; concrete batching facilities; vehicle and cycle parking facilities; pedestrian and cycle routes and facilities; offices and staff welfare facilities; security fencing and gates; external lighting; roadways and haul routes; wheel wash facilities; and signage; andvehicle access roads, crossings, parking, and pedestrian and cycle facilities and routes,and, to the extent that it does not form part of such works, further associated development comprising such other works (i) as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised development and (ii) which fall within the scope of the works assessed in the environmental statement.
SCHEDULE 2 — REQUIREMENTS
Interpretation
1
In this Schedule—
- “arboricultural survey report” means the report dated April 2020 included as appendix 2 of the indicative landscape strategy;
- “biodiversity protection plan” means the detail set out in part 6 of the biodiversity strategy;
- “coming into operation” or “come into operation” mean the date on which the authorised development first receives commercial deliveries of fuel after commissioning;
- “commissioning” means the process of assuring that all systems and components of the authorised development are tested, to verify that they function and are operable in accordance with the design objectives, specifications and operational requirements of the undertaker, prior to the authorised development coming into operation;
- “indicative biodiversity mitigation and enhancement plan” means the detail set out in part 8 of the biodiversity strategy;
- “the outline drainage strategy” means the outline drainage strategy included as appendix 14B of the environmental statement;
- “the permitted preliminary works” means—within the area of Work No. 1 works consisting of the removal of existing structures, and site clearance works; andwithin the areas of Work No.s 1, 2, 3, 4 and 5 works consisting of biodiversity management, mitigation and enhancement works, providing these are in accordance with the biodiversity protection plan or any details approved pursuant to requirement 11, wheel cleaning facilities, the installation and diversion of utility services, surveys, and temporary contractors’ facilities; andreferences to “Work No. 1” in this Schedule include Work No. 1A and Work No. 1B;
- “Royal Mail” means Royal Mail plc (Company No. 08680755) whose registered office is at 100 Victoria Embankment, London EC4Y 0HQ; and
- “SCANNER” means Surface Condition Assessment for the National Network of Roads.
Commencement of the authorised development and notices
2
- (1) The authorised development must not be commenced after the expiration of five years from the date this Order comes into force.
- (2) Unless such event has already occurred prior to the date of the undertaker’s notice under article 5, the undertaker must notify the relevant planning authority within seven days of each of the following events occurring—
- (a) the start of commissioning of the authorised development; and
- (b) the coming into operation of the authorised development.
Approved details and amendments to them
3
- (1) All relevant details submitted for the approval of the relevant planning authority pursuant to these requirements must be in accordance with the following dimensions—
- (a) maximum main building height – 59 metres AOD (including 2 metre parapet wall on boiler house);
- (b) maximum main building footprint – 210 metres x 110 metres;
- (c) stack height – 102 metres AOD;
- (d) maximum stack diameter – 3 metres per combustion stream; and
- (e) bunker base maximum depth – -8 metres AOD.
- (2) Where a requirement requires the authorised development to be constructed in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments subsequently approved by the relevant planning authority.
Requirement for written approval
4
Where under any of the requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.
Detailed design (position and scale)
5
- (1) In relation to any part of the authorised development comprised in Work No. 1 no development of that part may commence, save for the permitted preliminary works, until details of the final position, finished floor levels, elevations and floor plans of all new permanent buildings and structures have been submitted to and approved by the relevant planning authority. The authorised development must be carried out in accordance with the approved details.
- (2) No part of the authorised development may have more than three occupied storeys save for Work No. 1B.
Detailed design (appearance)
6
In relation to any part of the authorised development comprised in Work No. 1 no development of that part may commence, save for the permitted preliminary works, until details of the external appearance, including the colour, materials and surface finishes, of all new permanent buildings and structures have been submitted to and approved by the relevant planning authority. The authorised development must be carried out in accordance with the approved details.
Retained trees
7
- (1) All trees located within Work No. 3 must be retained throughout the construction and operation of the authorised development unless replaced under sub-paragraph (2) or otherwise agreed with the relevant planning authority.
- (2) Any tree within Work No. 3 that is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, during the construction or operation of the development must be replaced in the first available planting season with a specimen of the same species unless otherwise agreed with the relevant planning authority.
Means of enclosure and hard landscaping
8
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until the details and position of means of enclosure, circulation areas, hardstandings and all other hard landscaping for that part have been submitted and approved by the relevant planning authority.
- (2) The details submitted under sub-paragraph (1) in respect of Work No. 1 must include details of a 2.5 metre high close board fence along the southern and eastern boundary of Work No. 1, as set out in section 7 and illustrated in figure 1 of the biodiversity strategy.
- (3) The details submitted under sub-paragraph (1) in respect of Work No. 5 must include details of a 2.5 metre high close board fence along the eastern boundary of Work No. 5 to the extent that it is coincidental with the Order limits.
- (4) The details approved under this requirement must be implemented during the construction of the authorised development and then maintained throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority.
- (5) In this requirement, “means of enclosure” means fencing, walls or other means of boundary treatment and enclosure.
Lighting scheme
9
- (1) The authorised development may not come into operation until a scheme for all permanent external lighting to be installed (with the exception of any aviation warning lighting required under requirement 30) has been submitted to and approved by the relevant planning authority.
- (2) The scheme submitted and approved under sub-paragraph (1) must be in accordance with the principles of the indicative lighting strategy and include measures to minimise and otherwise mitigate any artificial light emissions during the operation of the authorised development.
- (3) The scheme must be implemented as approved prior to the coming into operation of the authorised development and maintained throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority.
Soft landscaping
10
- (1) The permitted preliminary works may start but the authorised development may not come into operation until a scheme of soft landscaping and planting has been submitted to, and approved by, the relevant planning authority.
- (2) The scheme submitted and approved under sub-paragraph (1) must include details of—
- (a) materials, and the number, species, sizes and planting positions of any planting;
- (b) measures to protect any existing shrub and tree planting that is to be retained;
- (c) an implementation plan; and
- (d) a future maintenance plan.
- (3) The scheme must be implemented within a period of 12 months beginning with the coming into operation of the authorised development and maintained as approved during the operation of the authorised development, unless otherwise agreed with the relevant planning authority.
Biodiversity protection
11
- (1) The biodiversity protection plan must be implemented during the construction of the authorised development, unless otherwise agreed by the relevant planning authority.
- (2) No later than 18 months from the commencement of the authorised development a report by a qualified ecologist verifying the implementation of the relevant parts of the biodiversity protection plan and setting out implementation measures for the remaining parts of the biodiversity protection plan must be submitted to the relevant planning authority for approval, unless otherwise agreed by the relevant planning authority. The implementation measures for the remaining parts of the biodiversity protection plan must be implemented as approved, unless otherwise agreed by the relevant planning authority.
Biodiversity mitigation and enhancement
12
- (1) No later than 12 months from submission of the details under requirement 11(2) a biodiversity mitigation and enhancement plan must be submitted to the relevant planning authority for approval.
- (2) The plan submitted and approved under sub-paragraph (1) must be in accordance with the principles set out in the indicative biodiversity mitigation and enhancement plan, and must include an implementation timetable, including monitoring and maintenance activities.
- (3) The plan approved under sub-paragraph (1) must be implemented in full by the end of the second planting season after the plan is approved and maintained during the operation of the authorised development unless otherwise agreed by the relevant planning authority.
Surface water drainage
13
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until the undertaker has consulted with Anglian Water on details of the permanent surface water drainage systems, including a future maintenance plan, the undertaker has then submitted the details to the relevant planning authority and the relevant planning authority has approved those details.
- (2) The details submitted and approved under sub-paragraph (1) must be in accordance with the principles set out in sections 2, 4 and 6 of the outline drainage strategy.
- (3) The scheme approved under sub-paragraph (1) must be implemented as approved prior to the development coming into operation and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.
Foul water drainage
14
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until details of the permanent foul water drainage systems, including a future maintenance plan, have been submitted to and, after consultation with Anglian Water and the Environment Agency, approved by the relevant planning authority.
- (2) The details submitted and approved under sub-paragraph (1) must be in accordance with the principles set out in sections 2 and 5 of the outline drainage strategy.
- (3) The scheme approved under sub-paragraph (1) must be implemented as approved prior to the development coming into operation and maintained as approved throughout the operation of the authorised development unless otherwise agreed by the relevant planning authority.
Construction environmental management plan
15
- (1) No part of the authorised development may commence until a construction environmental management plan for that part has been submitted to and approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with appendix 5A of the environmental statement and the biodiversity protection plan and incorporate—
- (a) visitor and contractor parking areas;
- (b) a materials management plan;
- (c) materials storage areas;
- (d) wheel cleaning facilities;
- (e) noise, vibration and dust mitigation measures;
- (f) lighting details;
- (g) fence installation (including a timetable for installation) and its retention throughout construction in accordance with paragraph 7.1.1 of the biodiversity strategy;
- (h) tree protection measures throughout construction in accordance with sections 6.6 to 6.8 of the arboricultural survey report;
- (i) waste management in accordance with chapter 16 of the environmental statement; and
- (j) pollution control.
- (3) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan unless otherwise agreed with the relevant planning authority.
Construction traffic management and travel planning
16
- (1) No part of the authorised development may commence until the undertaker has consulted with Network Rail on a construction traffic management plan for that part, submitted the plan to the relevant planning authority, and the relevant planning authority has approved the plan.
- (2) The plan submitted and approved under sub-paragraph (1) must be in accordance with the framework construction traffic management plan.
- (3) The plan submitted and approved under sub-paragraph (1) for Work No. 1 must include—
- (a) details of the routes to be used for the delivery of abnormal indivisible loads and procedures for the notification of these to the local highway authority, Royal Mail and, if the route includes railway assets, Network Rail; and
- (b) a construction worker travel plan (which must be in accordance with the framework construction worker travel plan included as annex 27 of appendix 9A of the environmental statement).
- (4) The plan must be implemented as approved throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
Piling
17
- (1) No part of the authorised development comprised within Work No. 1 may commence, save for the permitted preliminary works, until the undertaker has consulted the Environment Agency on a written specification of the type of piling to be used to support the building and structures, the undertaker has submitted that specification to the relevant planning authority, and the relevant planning authority has approved that specification.
- (2) The written specification submitted and approved under sub-paragraph (1) must include a scheme to mitigate the effects of the piling with regard to noise to ecological receptors (which must include seasonal piling restrictions and/or the use of continuous flight auger piling as each of those are described in section 7 of the biodiversity strategy) and a scheme to mitigate the effects of the piling with regard to groundwater resources (which must be in accordance with the results of the site investigation carried out, and any remediation strategy submitted, pursuant to requirement 19).
- (3) All piling works must be carried out in accordance with the approved written specification unless otherwise agreed with the relevant planning authority.
Temporary halting of development on finding unexpected contamination
18
If at any point during construction contamination is found that is not expected in the scheme submitted and approved under sub-paragraph (1) of requirement 19, development must be halted on that part of the site affected by the unexpected contamination to the extent specified by the relevant planning authority in writing until requirement 21 has been complied with in relation to the unexpected contamination.
Investigation and remediation of contamination
19
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until the undertaker has consulted with the Environment Agency on a scheme for an investigation of the nature and extent of any contamination on the site, whether or not it originates on the site, the undertaker has submitted this scheme to the relevant planning authority, and the relevant planning authority has approved the scheme.
- (2) The scheme submitted and approved under sub-paragraph (1) must be in accordance with the principles set out in chapter 12 and appendix 12A of the environmental statement and must be undertaken by competent persons.
- (3) The scheme submitted and approved under sub-paragraph (1) must include—
- (a) a survey of the extent, scale and nature of contamination;
- (b) a risk assessment taking into account—
- (i) human health;
- (ii) property (existing or proposed) including buildings, crops, livestock, pets, woodland and service lines and pipes;
- (iii) adjoining land;
- (iv) groundwaters and surface waters;
- (v) ecological systems; and
- (vi) archaeological sites and ancient monuments (if applicable); and
- (c) an appraisal of the need for remediation to bring the site to a condition suitable for the intended use by removing unacceptable risks to human health, buildings and other property and the natural and (if applicable) historical environment.
- (4) If the appraisal under sub-paragraph (3) (c) identifies the need for remediation then a remediation scheme must be submitted together with the scheme submitted pursuant to sub-paragraph (1).
- (5) Any scheme submitted under sub-paragraph (4) must contain an appraisal of the remedial options available and a description of the proposed remediation works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works and site management procedures. The remediation scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
- (6) The schemes submitted under sub-paragraphs (1) and (4) (in the event a remediation scheme under sub-paragraph (4) is required) and approved under sub-paragraph (1) must be conducted in accordance with DEFRA and the Environment Agency’s ‘Model Procedures for the Management of Land Contamination, CLR 11’.
Implementation of remediation scheme
20
- (1) In the event that a remediation scheme under requirement 19(4) is required, the relevant part of the authorised development must not commence, save for the permitted preliminary works, until any scheme approved under requirement 19(4) has been implemented as approved, unless otherwise agreed by the relevant planning authority.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.