The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022
- (2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by Northern Powergrid for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and Northern Powergrid is entitled to watch and inspect the execution of those works.
- (3) Any requirements made by Northern Powergrid under sub-paragraph (2) must be made within a period of 42 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.
- (4) If Northern Powergrid in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 93 to 98 apply as if the removal of the apparatus had been required by the undertaker under paragraph (2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 35 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to Northern Powergrid notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
100
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to Northern Powergrid all reasonable and proper expenses costs or charges incurred by Northern Powergrid—
- (a) in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 97(2) including without limitation:
- (i) any costs reasonably incurred or compensation properly paid in connection with the acquisition of rights or the exercise of statutory powers for such apparatus including without limitation in the event that it is agreed Northern Powergrid elects to use compulsory purchase powers to acquire any necessary rights under paragraph 97(3) all costs reasonably incurred as a result of such action;
- (ii) in connection with the cost of the carrying out of any diversion work or the provision of any alternative apparatus;
- (iii) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (iv) the approval of plans;
- (v) the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;
- (vi) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to in this Part of this Schedule); and
- (b) in assessing and preparing a design for its apparatus to address and accommodate the proposals of the undertaker whether or not the undertaker proceeds to implement those proposals or alternative or none at all,
provided that if it so prefers Northern Powergrid may abandon apparatus that the undertaker does not seek to remove in accordance with paragraph 97(1) having first decommissioned such apparatus.
- (2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this Part of this Schedule, that value being calculated after removal and for the avoidance of doubt, if the apparatus removed under the provisions of this Part of this Schedule has nil value, no sum will be deducted from the amount payable under sub-paragraph (1) if in accordance with the provisions of this Part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 44 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to Northern Powergrid by virtue of sub-paragraph (1) is to be reduced by the amount of that excess save where it is not possible on account of project time limits and/or supply issues to obtain the existing type of operations, capacity, dimensions or place at the existing depth in which case full costs shall be borne by the undertaker.
- (3) For the purposes of sub-paragraph (2)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the execution of any such works as are referred to in paragraph 97(2); and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
101
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the works referred to in in paragraph 97(2), or in consequence of the, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by it) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Schedule or any subsidence resulting from any of these works any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Northern Powergrid, or there is any interruption in any service provided by Northern Powergrid, or Northern Powergrid becomes liable to pay any amount to a third party as a consequence of any default, negligence or omission by the undertaker in carrying out the authorised works, the undertaker must—
- (a) bear and pay the cost reasonably incurred by Northern Powergrid in making good such damage or restoring the supply; and
- (b) indemnify Northern Powergrid for any other expenses, loss, damages, penalty, proceedings, claims or costs incurred by or recovered from Northern Powergrid,
by reason or in consequence of any such damage or interruption or Northern Powergrid becoming liable to any third party.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of Northern Powergrid, its officers, employees, servants, contractors or agents.
- (3) Northern Powergrid must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
- (4) Northern Powergrid must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 101 applies. If requested to do so by the undertaker, Northern Powergrid must provide an explanation of how the claim has been minimised or details to substantiate any cost or compensation claimed pursuant to sub-paragraph (1). The undertaker shall only be liable under this paragraph 101 for claims reasonably incurred by Northern Powergrid.
102
Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and Northern Powergrid in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
103
Where in consequence of the proposed construction of any of the authorised development, the undertaker or Northern Powergrid requires the removal of apparatus under paragraph 97 or otherwise or Northern Powergrid makes requirements for the protection or alteration of apparatus under paragraph 99, the undertaker shall use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the need to ensure the safe and efficient operation of Northern Powergrid’s undertaking taking into account the undertaker’s desire for the efficient and economic execution of the authorised development and the undertaker and Northern Powergrid shall use reasonable endeavours to co-operate with each other for those purposes.
104
If in consequence of an agreement reached in accordance with paragraph 96 or the powers granted under this Order the access to any apparatus or alternative apparatus is materially obstructed, the undertaker shall provide such alternative means of access to such apparatus or alternative apparatus as will enable Northern Powergrid to maintain or use the said apparatus no less effectively than was possible before such obstruction.
105
The plans submitted to Northern Powergrid by the undertaker pursuant to this Part of this Schedule must be sent to Northern Powergrid at property@northernpowergrid.com or such other address as Northern Powergrid may from time to time appoint instead for that purpose and notify to the undertaker in writing
SCHEDULE 11 — DESIGN PARAMETERS
1
Maximum parameters for buildings and structures are set out at table 6.
2
The finished ground level in respect of Work No. 1A, Work No. 1C and Work No. 1E may be higher than 2.8 metres above ordinance datum (AOD) but in all cases the maximum heights measured AOD shall not exceed the measurement in column 5 of table 6.
3
Maximum parameters of the A18 Gatehouse building (Work No. 8B) are set out in table 7.
4
Maximum parameters for length (m), width (m) or diameter (m) exclude external support structures such as (but not limited to) ladders, platforms, external piping and structural supports.
| (1) Component | (2) Length (m) | (3) Width (m) or diameter (m) | (4) Height (m) above ground level (AGL) (in the case that the finished ground level is 2.8m AOD) | (5) Height (M) AOD (in all cases) |
|---|---|---|---|---|
| Gas Turbine Hall (Work No. 1A) | 22 | 50 | 31.8 | 34.6 |
| Steam Turbine Hall (Work No. 1A) | 50 | 40 | 34.8 | 37.6 |
| HRSG Building (Work No. 1A) | 28 | 50 | 55.8 | 58.6 |
| Absorber (Work No. 1C) (in the case that a single absorber is developed) | 16 (Note 4) | 43 (Note 4) | 98.8 | 101.6 |
| Absorber Stack (Work No. 1C) (in the case that a single absorber is developed) | - | 6.7 | 104.8 | 107.6 |
| Twin Absorbers (Work No. 1C) (in the case that two absorbers are developed) | - | 19.0 (Note 4) | 80 | 82.8 |
| Twin Absorber Stacks (Work No. 1C) (in the case that two absorbers are developed) | - | 6.7 | 95.5 | 98.3 |
| HRSG Stack (Work No. 1A) | - | 8.0 | 84.8 | 87.6 |
| Carbon Dioxide stripper (Work No. 1C) | - | 15.0 (Note 4) | 63 | 65.8 |
| (1) Component | (2) Length (m) | (3) Width (m) | (4) Height (m) above ground level (AGL) | (5) Height (m) AOD |
| --- | --- | --- | --- | --- |
| A18 Gatehouse (Work No. 8B) | 6 | 7 | 4 | 5.5 |
SCHEDULE 12 — DOCUMENTS AND PLANS TO BE CERTIFIED
| (1) Document Name | (2) Document Reference |
|---|---|
| Access and rights of way plans | 4.4 |
| Book of reference | 3.1 |
| Land plans | 4.2 |
| Works plans | 4.3 |
| Combined heat and power assessment | 5.7 |
| Environmental statement | 6.0, 10.6-10.9 |
| Design principles statement (appendix 1 of the design and access statement) | 5.6 (appendix 1) |
| Flood risk assessment | 6.3.20 |
| Outline written scheme of investigation | 7.4 |
| Indicative landscape and biodiversity plan | 4.15 |
| Landscaping and Biodiversity Management and Enhancement plan | 5.10 |
| Indicative surface water drainage plan | 4.13 |
| Framework construction environmental management plan | 7.1 |
| Framework construction traffic management plan | 7.2 |
| Framework construction workers travel plan | 7.3 |
| Indicative lighting strategy | 5.11 |
| Haul road plans | 4.19 |
| Pilfrey laydown plans | 4.20 |
| Application guide | 1.2 |
SCHEDULE 13 — DEEMED MARINE LICENCE UNDER PART 4 (MARINE LICENSING) OF THE MARINE AND COASTAL ACCESS ACT 2009 / DEEMED MMO LICENCE PROVISIONS
PART 1 — INTRODUCTION
1
- (1) In this licence the definitions in article 2 must apply save where amended—
- “2009 Act” means the Marine and Coastal Access Act 2009.
- “ABP Humber” means Associated British Ports, Humber Estuary Services located at Port Office, Cleethorpe Road, Grimsby, North East Lincolnshire.
- “authorised deposits” means the substances specified in paragraph 2(4)of Part 2 of this licence.
- “the authorised development” has the meaning given in paragraph 2(4) of Part 2 of this licence.
- “business day” means a day other than a Saturday or Sunday, which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 1971.
- “Cefas” means the Centre for Environment, Fisheries and Aquaculture Science or any successor body to its function.
- “CEMP” means the construction and environmental management plan.
- “commence” for the purposes of this Schedule means the first carrying out of any licensed activities, save for pre-construction surveys approved under this licence and “commenced” and “commencement” shall be construed accordingly.
- “condition” means a condition under Part 3 of this licence.
- “enforcement officer” means a person authorised to carry out enforcement duties under Chapter 3 of the 2009 Act.
- “licensed activities” means the activities specified in Part 2 of this licence.
- “licensable marine activities” means any activity licensable under section 66 of the 2009 Act.
- “local enforcement office” means the Marine Management Office (Local Enforcement Office) as further detailed in paragraph 5(b) below.
- “maintain” includes inspect, repair, alter, refurbish, reconstruct, replace and improve any part of, but not remove, reconstruct or replace the whole of an existing structure or asset wholly within its existing three dimensional boundaries and “maintenance” and “maintaining” are to be construed accordingly.
- “marine area” has the meaning given to ‘UK marine area’ in section 42 of the 2009 Act.
- “Marine Management Organisation” means the body created under the 2009 Act which is responsible for the regulation of this licence or any successor of that function and “MMO” shall be construed accordingly.
- “MCA” means the Maritime and Coastguard Agency, the executive agency of the Department for Transport.
- “mean high water springs” or “MHWS” means the average of high water heights occurring at the time of spring tides.
- “office hours” means the period from 0900 until 1700 on any business day.
- “Order limits” means the limits shown on the works plans within which the authorised development may be carried out, whose grid co-ordinates seaward of MHWS are set out in paragraph 6 of Part 2 of this licence.
- “river” means the River Trent.
- “TH” means the corporation of Trinity House of Deptford Strond.
- “undertaker” means the undertaker Keadby Generation Limited (company registration number 02729513), and any agent, contractor or sub-contractor acting on its behalf or any person who has the benefit of this Order in accordance with article 6 (Benefit of Order) and 7 (Consent to transfer benefit of Order).
- “vessel” means every description of vessel, however propelled or moved, and includes a non-displacement craft, a personal watercraft, a seaplane on the surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any other thing constructed or adapted for movement through, in, on, under or over water and which is at the time in, on, under or over water, whether or not self-propelled.
- (2) A reference to any statue, order, regulation or similar instrument is to be construed as reference to a statute, order, regulation or similar instrument as amended by any subsequent statute, order, regulation or instrument or as contained in any subsequent re-enactment.
- (3) Unless otherwise indicated—
- (a) all times are taken to be Greenwich Mean Time (GMT);
- (b) all co-ordinates are taken to be latitude and longitude degrees minutes and seconds to three decimal places.
- (4) Unless otherwise advised in writing by the MMO, the address for electronic communication with the MMO for the purpose of this licence is marine.consents@marinemanagement.org.uk or where contact to the local MMO office is required is beverley@marinemanagement.org.uk.
- (5) Unless otherwise stated or agreed with the MMO, all notifications that must be sent by the undertaker to the MMO must be sent using the MMO’s Marine Casement Management System (MCMS) web portal. Except where otherwise notified in writing by the relevant organisation, the addresses for postal correspondence for the purposes of this Schedule are—
- (a) Marine Management Organisation (Marine Licensing Team)
Lancaster House,
Hampshire Court,
Newcastle Business Park,
Newcastle Upon Tyne,
NE4 7YH,
Tel: 0300 123 1032;
- (b) Marine Management Organisation (Local Enforcement Office)
Beverley office,
Room 13, Ground Floor,
Crosskill House,
Mill Lane,
Beverley,
HU17 9JB,
Tel: 0208 026 0519;
- (c) Trinity House
Tower Hill,
London,
EC3N 4DH,
Tel: 020 7481 6900;
- (d) The United Kingdom Hydrographic Office
Admiralty Way,
Somerset,
TA1 2DN,
Tel: 01823 337 900;
- (e) Maritime and Coastguard Agency (Navigation Safety Branch)
Bay 2/20, Spring Place,
105 Commercial Road,
Southampton,
SO15 1EG,
Tel: 020 3817 2418;
- (f) Natural England
Sterling House,
Dix’s Field,
Exeter,
EX1 1QA,
Tel: 0300 060 39000;
- (g) Historic England
Cannon Bridge House,
25 Dowgate Hill,
London,
EC4R 2YA,
Tel: 020 7973 370;
- (h) Centre for Environment, Fisheries and Aquaculture Science (‘Cefas’)
Pakefield Road,
Lowestoft,
Suffolk,
NR33 0HT,
Tel: 01502 562 244.
PART 2 — DETAILS OF LICENSED MARINE ACTIVITIES
2
Subject to the conditions, this licence authorises the undertaker to carry out any licensable marine activities under section 66(1) of the 2009 Act which—
- (a) form part of, or are related to, the authorised development; and
- (b) are not exempt from requiring a marine licence by virtue of any provision made under section 74 of the 2009 Act.
3
Licensed activities are authorised in relation to the construction, maintenance and operation of—
- (a) Work No. 4B – River Water Abstraction Option—
Works to the existing cooling water supply pipelines running from Work No. 1E to the existing intake structures within the River Trent, including, as necessary, a temporary cofferdam structure, new, upgraded or replacement pipelines, plant, buildings, enclosures, structures and cable;
- (b) Work No. 5 – Water Discharge Corridor—
Works to discharge used cooling water and treated wastewater comprising works to the existing cooling water discharge pipeline(s) running from Work No. 1B to the existing outfall structures within the River Trent, including, as necessary, new, upgraded or replacement pipelines, plant, enclosures, outfall structure, screens and other structures, and cable; and
- (c) any such work, further associated development listed in Schedule 1 ancillary to Work Nos. 4B and 5.
4
The substances or articles authorised for deposit associated with the completion of the construction, maintenance and operational activities described in item 3, sub paragraph (1) (a) and (b) above include—
- (a) Silt, algal growth and biota;
- (b) Stone, rock and concrete;
- (c) Grout and sealant material; and
- (d) any other material of substance to the extent its effects have been considered within the environmental statement.
5
The undertaker may engage in the licensed activities in the area bounded by the coordinates set out in Table 9 in this paragraph to the extent that they fall below MHWS at the time the licensed activities are carried out.
6
The coordinates in Table 9 are defined in accordance with reference system WGS84 - World Geodetic System 1984.
| Works No. | Description | Longitude | Latitude |
|---|---|---|---|
| Works No. 4B | River Water | -0.73879 | 53.59523 |
| Abstraction Option | -0.73893 | 53.5941 | |
| – Intake Works | -0.73952 | 53.59412 | |
| -0.73936 | 53.59525 | ||
| -0.73891 | 53.59432 | ||
| -0.73886 | 53.59492 | ||
| -0.73891 | 53.59457 | ||
| Works No. 5 | Water Discharge Corridor – Existing Outfall Option | -0.73769 | 53.59966 |
| -0.73732 | 53.60015 | ||
| -0.73702 | 53.60006 | ||
| -0.73709 | 53.6 | ||
| -0.73736 | 53.59997 | ||
| -0.73742 | 53.59989 | ||
| -0.73735 | 53.59978 | ||
| -0.73739 | 53.59973 | ||
| -0.73731 | 53.59968 | ||
| -0.73731 | 53.59964 | ||
| -0.73737 | 53.59957 | ||
PART 3 — CONDITIONS
General
7
Any oil, fuel or chemical spill within the marine environment must be reported to the MMO Marine Pollution Response Team within 12 hours of being identified in accordance with the following—
- (a) within office hours: 0300 200 2024;
- (b) outside office hours: 07770 977 825; or
- (c) at all times if other numbers are unavailable: 0845 051 8486 or dispersants@marinemanagement.org.uk.
Notifications and Inspections
8
- (1) The undertaker must ensure that—
- (a) a copy of this licence (issued as part of the grant of the Order) and any subsequent amendments or revisions to it is provided to—
- (i) all agents and contractors notified to the MMO in accordance with condition 12 and
- (ii) the masters responsible for the vessels notified to the MMO in accordance with condition 13.
- (2) Only those persons and vessels notified to the MMO in accordance with condition 12 and 13 are permitted to carry out the licensed activities.
- (3) Copies of this licence must also be available for inspection at the following locations—
- (a) the undertaker’s registered address;
- (b) any site office located at or adjacent to the construction site and used by the licence holder or its agents and contractors responsible for the loading, transportation or deposit of the authorised deposits; and
- (c) on board each vessel or at the office with responsibility for vessels from which authorised deposits or removals are to be made.
- (4) The documents referred to in sub-paragraph (1)(a) must be available for inspection by an enforcement officer at the locations set out in sub-paragraph (3)(b) above.
- (5) The undertaker must provide access, and if necessary appropriate transportation, to the offshore construction site or any other associated works or vessels to facilitate any inspection that the MMO considers necessary to inspect the works during construction and operation of the authorised development.
- (6) A notice to mariners must be issued at least 14 days prior to the commencement of the licensed activities or any part of them advising of the start date of those activities and the expected vessel routes from the construction ports to the relevant location. Copies of all notices must be provided to the MMO, TH, MCA and United Kingdom Hydrographic Office within 24 hours of issue.
- (7) The undertaker must notify the United Kingdom Hydrographic Office of the commencement (within ten days), progress and completion of construction (within ten days) of the licensed activities in order that all necessary amendments to nautical charts are made and the undertaker must send a copy of such notifications to the MMO within 24 hours of issue.
Pre-construction
9
Not later than 8 weeks prior to the proposed commencement of licences activities the undertaker must submit to the MCA and the MMO for review and approval in writing by the MMO the CEMP covering the period of construction to include details of—
- (a) a marine pollution contingency plan to address the risks, methods and procedures to deal with any spills and collision incidents of the authorised development in relation to all activities to be carried out;
- (b) a biosecurity plan detailing how risk of the introduction and spread of invasive non-native species will be minimised; and
- (c) waste management and disposal arrangements.
10
- (1) The undertaker must submit a marine method statement (MMS) to the MMO no later than 8 weeks prior to the proposed commencement of the licensed activities for its written approval. The MMS is to include details of—
- (a) any proposed refurbishment and/or construction activities;
- (b) if a cofferdam is proposed to be constructed as part of Work No. 4B, the cofferdam installation technique and piling methodology;
- (c) any construction works at the intake, including the level or refurbishment or replacement works required;
- (d) an indicative programme for the completion of the licensed activities; and
- (e) the details of engagement undertaken with ABP Humber, as the appropriate navigational authority. This must include the design of the cofferdam and any measures which will be installed around the toe of the cofferdam to manage risk of shoaling, if necessary. It must also include details of any specification demarcation or lighting requests, as directed by ABP Humber.
- (2) The licensed activities must not commence until written approval of the MMS is provided by the MMO.
- (3) All licensed activities must be undertaken in accordance with the approved MMS.
- (4) The MMS may be amended from time to time subject to the approval in writing of the MMO.
11
The undertaker must complete pre-works bathymetry of the areas specified in Part 2, paragraph 5, before the commencement of works. The results of pre-works bathymetry must be shared with ABP Humber, as the appropriate navigational authority and the MMO.
12
The undertaker must notify the MMO in writing of any agents, contractors or subcontractors that will carry on any licensed activity listed in this licence on behalf of the undertaker this must include the name, address, company number (if applicable) and role. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity and any change to a notified agent, contractor or subcontractors must be updated and notified to the MMO accordingly.
13
The undertaker must notify the MMO in writing of any vessel being used to carry on any licensed activity listed in this licence on behalf of the undertaker. Such notification must be received by the MMO no less than 24 hours before the commencement of the licensed activity. Notification must include the master’s name, vessel type, vessel IMO number and vessel owner or operating company.
During Construction, Operation and Maintenance
14
The undertaker must ensure that any coatings and treatments used are suitable for use in the marine area and are used in accordance with either guidelines approved by the Health and Safety Executive or the Environment Agency Pollution prevention for businesses guidelines.
15
The storage, handling, transport and use of fuels, lubricants, chemicals and other substances must be undertaken so as to prevent releases into the marine environment including bunding of 110% of the total volume of all reservoirs and containers.
16
The undertaker must not discharge waste concrete slurry or wash water from concrete or cement into the river. The undertaker must site concrete and cement mixing and washing areas at least 10 metres from the river or surface water drain to minimise the risk of run off entering the river. If concrete is to be sprayed, suitable protective sheeting must be provided to prevent rebounded or windblown concrete from entering the marine environment. Rebounded material must be cleared away before the sheeting is removed.
17
During licensed activities all wastes must be stored in designated areas that are isolated from surface water drains, open water and bunded to contain any spillage.
18
- (1) Vibratory piling must be used as standard, with percussive piling only used if required to drive a pile to its design depth and where drill or vibratory piling has been unsuccessful. If percussive piling is necessary, soft-start procedures must be used to ensure incremental increase in pile power over a set time period until full operational power is achieved.
- (2) The soft-start duration must be a period of not less than twenty minutes.
- (3) Should piling cease for a period greater than ten minutes, then the soft start procedure must be repeated.
19
Piling must not be undertaken between 01 September and 31 November, inclusive, in order to minimize any potential effects on the upstream migration of adult Salmon during their most sensitive migratory period and on wintering birds. Piling will be restricted between 0700 and 1900 hours.
20
The undertaker must comply with the lighting, hazard marking and demarcation requirements of ABP Humber, as the appropriate navigational authority.
21
The undertaker must ensure any rock material used in the construction of the authorised development is from a recognised source, free from contaminants and containing minimal fines.
22
In the event that any rock or stone material is misplaced or lost below MHWS, the undertaker must report the loss to the Local Enforcement Office within 48 hours of becoming aware and if the MMO reasonably considers such material to constitute a navigation or environmental hazard (dependent on the size and nature of the material) the MMO must notify the undertaker and the undertaker must use reasonable endeavours to locate the material and recover it. In that event, the undertaker must demonstrate to the MMO that reasonable attempts have been made to locate, remove or move any such material.
23
- (1) The undertaker must report all dropped objects to the MMO using the Marine Licence Dropped Incident Report (MLDIR) as soon as reasonably practicable and in any event within 24 hours of becoming aware of an incident.
- (2) On receipt of the MLDIR, the MMO may require, acting reasonably, the undertaker to carry out relevant surveys directly related to such MLDIR and where there is a need to remedy any effect related to the MLDIR. The undertaker must carry out surveys at its own expense in accordance with the MMO’s reasonable requirements and must report the results of such survey results to the MMO.
- (3) On receipt of such survey results the MMO may, acting reasonably, require the undertaker to remove specific obstructions from the riverbed. The undertaker must carry out removal of specific obstructions from the riverbed in accordance with the MMO’s reasonable requirements and at its own expense.
Post Construction
24
The undertaker must ensure that any equipment, temporary structures, waste and debris 2associated with the licensed activities are removed within six weeks of completion of the licensed activity.
25
The undertaker must ensure that the MMO Local Enforcement Office is notified of the completion of the licensed activities and operations within ten days following the completion of the works.
26
The undertaker must complete post-works bathymetry of the areas specified in paragraph 5 of Part 2 of this licence, following the completion of the licensed activities. The results of post-works bathymetry must be shared with ABP Humber, as the appropriate navigational authority and with the MMO.
Conditions Discharge
27
The MMO must determine an application for discharge of a condition as soon as 2reasonably practicable and in any event within a period of three months commencing on the date the application is received by the MMO, unless otherwise agreed in writing with the undertaker.
Signed
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
David Wagstaff — Deputy Director Energy Infrastructure Planning — Department for Business, Energy and Industrial Strategy — 7th December 2022
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises the undertaker (referred to in this Order as the undertaker) to construct, operate and maintain a power generating station and carbon capture and compression plant. The Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose.
The Order also grants a deemed marine licence under Part 4 of the Marine and Coast Access Act 2009.
A copy of the Order plans and the book of referenced mentioned in this Order and certified in accordance with Article 41 (certification of plans, etc.) may be inspected free of charge during working hours at Crowle Library, The Market Hall, Market Place, Crowle, North Lincolnshire, DN17 4LA.
Footnotes
[^f00001]: 2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20). Part 7 was amended by S.I. 2017/16.
[^f00002]: S.I. 2009/2264, as amended by S.I. 2012/635 and S.I. 2013/522. There are other amendments to the Regulations which are not relevant to this Order.
[^f00003]: S.I. 2010/103 amended by S.I. 2012/635.
[^f00004]: S.I. 2017/572 amended by S.I. 2018/695, S.I. 2018/942.
[^f00005]: Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act 2011 (c. 20).
[^f00006]: 1961 c. 33.
[^f00007]: 1965 c. 56.
[^f00008]: 1980 c. 66.
[^f00009]: 1981 c. 66.
[^f00010]: 1990 c. 8.
[^f00011]: 1991 c. 22.
[^f00012]: 2008 c. 29.
[^f00013]: 2009 c. 23.
[^f00014]: 1989 c. 29.
[^f00015]: 1981 c. 67. Section 7 was amended by the Planning and Compulsory Purchase Act 1991 (c. 34).
[^f00016]: 1947 c. 51. This Act was repealed by the Planning (Consequential Provision) Act 1990 (c. 11).
[^f00017]: 1962 c. 38. This Act was repealed by the Planning (Consequential Provision) Act 1990.
[^f00018]: 1971 c. 78. This Act was repealed by the Planning (Consequential Provision) Act 1990.
[^f00019]: 1989 c. 29. Section 6 was amended by section 30 of the Utilities Act 2000 (c. 27), sections 89, 136, 145 of, and Schedules 19 and 23 to, the Energy Act 2004 (c. 29), paragraph 2 of Schedule 8 to the Climate Change Act 2008 (c. 27), regulation 19 of S.I. 2011/2704 and articles 6 and 21 of S.I. 2012/2400.
[^f00020]: 1986 c. 44 (as amended).
[^f00021]: 2017 c. 20.
[^f00022]: 1991 c. 56. This Section was amended by sections 35 and 43(2) of, and paragraph 1 of Schedule 2 to, the Competition and Service (Utilities) Act 1992 (c. 43), sections 36 and 99 of the Water Act 2003 (c. 37) and paragraph 16 of Schedule 3 to the Flood and Water Management Act 2010 (c. 29).
[^f00023]: S.I. 2016/1154.
[^f00024]: 1964 c. 40.
[^f00025]: 1991 c. 57.
[^f00026]: Inserted by section 202(1) of the Housing and Planning Act 2016 (c. 22).
[^f00027]: Inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
[^f00028]: 2003 c. 21.
[^f00029]: S.I. 1997/1160.
[^f00030]: 1990 c. 43. This section was amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c. 16).
[^f00031]: 1974 c. 40. Words in this section were repealed by section 133(2) of, and Schedule 7 to, the Building Act 1984 (c. 55) and by section 120(3) of, and paragraph 1 of Schedule 24 to, the Environment Act 1995 (c. 25) and inserted by section 162(1) of, and paragraph 15(3) of Schedule 15 to, that Act.
[^f00032]: 1978 c. 30.
[^f00033]: S.I. 2009/3344.
[^f00034]: 1973 c. 26.
[^f00035]: Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
[^f00036]: Section 11B was inserted by section 187(2) of the above Act.
[^f00037]: 1971 c. 80.
[^f00038]: S.I. 2012/2920.
[^f00039]: 1991 c. 22.
[^f00040]: 1995 c. i.
[^f00041]: 1968 c. 73. Sections 105(1) and (2) were amended by paragraph 39 of Schedule 2 to S.I. 2012/1659.
[^f00042]: 1989 c. 29.
[^f00043]: 1991 c. 56.
[^f00044]: 1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c. 45) and was further amended by the Utilities Act 2000 (c. 27).
[^f00045]: 2003 c. 21 as amended by the Digital Economy Act 2017 (c. 30).
[^f00046]: Added by Schedule 1 of the Digital Economy Act 2017 (c. 30).
[^f00047]: 1991 c. 22.
[^f00048]: 2006 c. 46.
[^f00049]: 1991 c. 22.
Editorial notes
[^key-668df929e54bc4c77e139e9e180e388e]: Art. 1 in force at 29.12.2022, see art. 1
[^key-4f4634605e02e8194f3cda843c146f1c]: Art. 2 in force at 29.12.2022, see art. 1
[^key-e377e25fce0f44ca2287c58e4dcdf02c]: Art. 3 in force at 29.12.2022, see art. 1
[^key-7bae7af0d17d200246d08216e9fb9531]: Art. 4 in force at 29.12.2022, see art. 1
[^key-034ac9b3de620b8e2304bd7415f5ed84]: Art. 5 in force at 29.12.2022, see art. 1
[^key-b08a8410a15342d67cf5e7dff1a10a97]: Art. 6 in force at 29.12.2022, see art. 1
[^key-13bb3e9d9311d6ae1bc0513a14dc3c96]: Art. 7 in force at 29.12.2022, see art. 1
[^key-fa11df409c9543c8515def030384096a]: Art. 8 in force at 29.12.2022, see art. 1
[^key-de2a1aba76242f788bfc5bf3a1b9220b]: Art. 9 in force at 29.12.2022, see art. 1
[^key-cf03b5cd5b23b733945d3153c9b91c65]: Art. 10 in force at 29.12.2022, see art. 1
[^key-c33ca0cb15f75ebd5ce093885340c989]: Art. 11 in force at 29.12.2022, see art. 1
[^key-808464dfea030ba9bbe49fef47366af1]: Art. 12 in force at 29.12.2022, see art. 1
[^key-93a3c72f8d3947dd24148091f27bd17f]: Art. 13 in force at 29.12.2022, see art. 1
[^key-62177fd8242fefa21d08b6d8bf337b28]: Art. 14 in force at 29.12.2022, see art. 1
[^key-9646e5763e32ca737546bf3babeeca27]: Art. 15 in force at 29.12.2022, see art. 1
[^key-6e6aeabc1fa9e3d439096ccdc3a5ee86]: Art. 16 in force at 29.12.2022, see art. 1
[^key-4112abc115e31fd2abd9e0d66894f422]: Art. 17 in force at 29.12.2022, see art. 1
[^key-392c35b5e3d0278ae73669349735e4a4]: Art. 18 in force at 29.12.2022, see art. 1
[^key-183c3dd81d6838cc2586fe62ef639698]: Art. 19 in force at 29.12.2022, see art. 1
[^key-ad88ffa87be258f8accae961a8f4cfea]: Art. 20 in force at 29.12.2022, see art. 1
[^key-218545ca4aad56485fb212333457dcac]: Art. 21 in force at 29.12.2022, see art. 1
[^key-6a0cb1174a5976cab6710702bb32dcba]: Art. 22 in force at 29.12.2022, see art. 1
[^key-eb6acee0ca30d3eb06daff60ac1c0dc3]: Art. 23 in force at 29.12.2022, see art. 1
[^key-6e4cc1fff29dfed928f65e3adfe0c34a]: Art. 24 in force at 29.12.2022, see art. 1
[^key-3708096144d68ef0cb93384902ebc0e8]: Art. 25 in force at 29.12.2022, see art. 1
[^key-25981b5762c5222c52c7c009934e775e]: Art. 26 in force at 29.12.2022, see art. 1
[^key-7de724f21f30de2cacff4a8d47c48678]: Art. 27 in force at 29.12.2022, see art. 1
[^key-138098138ca48c72b60829c09e5824c8]: Art. 28 in force at 29.12.2022, see art. 1
[^key-ff34ad955a845e5f0329c0e9300bc67a]: Art. 29 in force at 29.12.2022, see art. 1
[^key-6998f2a6ed23c83908ae053aa8ba8a03]: Art. 30 in force at 29.12.2022, see art. 1
[^key-d64925cc01c02bd5b8da8071d0d1e0b7]: Art. 31 in force at 29.12.2022, see art. 1
[^key-8c24fcbc8f4144bbb0fd900b9f608834]: Art. 32 in force at 29.12.2022, see art. 1
[^key-ed7835b2e34d4a94722df986eeb5057b]: Art. 33 in force at 29.12.2022, see art. 1
[^key-728af10de1c62f3bdd7ca7a0bbf61eac]: Art. 34 in force at 29.12.2022, see art. 1
[^key-fbd030571a1a9f46cc91947e398745de]: Art. 35 in force at 29.12.2022, see art. 1
[^key-391f345d812711a4b40a8cf8b2848259]: Art. 36 in force at 29.12.2022, see art. 1
[^key-2701d1c16f60637404ee478144416c5e]: Art. 37 in force at 29.12.2022, see art. 1
[^key-724fcba6b1dbac5dcb3e43d1a719b33b]: Art. 38 in force at 29.12.2022, see art. 1
[^key-18242491c5a704f277f453337063708e]: Art. 39 in force at 29.12.2022, see art. 1
[^key-1e0d5ee89fb7153cb35e231d5ed905cb]: Art. 40 in force at 29.12.2022, see art. 1
[^key-c36e2773e2ec6a3595160498f0893470]: Art. 41 in force at 29.12.2022, see art. 1
[^key-da3fd367d6f74ae1e1ae3469eb9badee]: Art. 42 in force at 29.12.2022, see art. 1
[^key-47cb08a9281f2198f304b771eee68750]: Art. 43 in force at 29.12.2022, see art. 1
[^key-a40b2ee40aeed0aff6bb2dd9e4befea2]: Art. 44 in force at 29.12.2022, see art. 1
[^key-d4cc1cf1e4b29cf01e34ed31d0b3f3e2]: Art. 45 in force at 29.12.2022, see art. 1
[^key-bf9e8d3df69048457e1adfae53827503]: Sch. 2 para. 1 in force at 29.12.2022, see art. 1
[^key-31397f960c5d5e1be8540f3d3974048c]: Sch. 2 para. 2 in force at 29.12.2022, see art. 1
[^key-c7dc0ec67f0a75c9447a834715434b0c]: Sch. 2 para. 3 in force at 29.12.2022, see art. 1
[^key-879f6808a2b8de2ac0c2df789566b7c1]: Sch. 2 para. 4 in force at 29.12.2022, see art. 1
[^key-235b4871560f2cfb04a7c54fcbeac147]: Sch. 2 para. 5 in force at 29.12.2022, see art. 1
[^key-4b1e63162f69c8a698b3b077d4073b34]: Sch. 2 para. 6 in force at 29.12.2022, see art. 1
[^key-af0d90eeae4e73c1b82a18ab4ae249b8]: Sch. 2 para. 7 in force at 29.12.2022, see art. 1
[^key-ce2ecd32c3805a53d1b77b57cb425c20]: Sch. 2 para. 8 in force at 29.12.2022, see art. 1
[^key-11b1f88ae9e92a92352016c8f0ebb52b]: Sch. 2 para. 9 in force at 29.12.2022, see art. 1
[^key-2ec87ddd4111c516388338389ebf3339]: Sch. 2 para. 10 in force at 29.12.2022, see art. 1
[^key-716de8917379e596c8a6333e37cb8ffe]: Sch. 2 para. 11 in force at 29.12.2022, see art. 1
[^key-f0cd5a7b5c4b4a6797a765af8b960a32]: Sch. 2 para. 12 in force at 29.12.2022, see art. 1
[^key-eba861db78973c363404f322817fc1b1]: Sch. 2 para. 13 in force at 29.12.2022, see art. 1
[^key-3fe12b20e9a458c3b6b253006d2d2aaf]: Sch. 2 para. 14 in force at 29.12.2022, see art. 1
[^key-50201afeadf1e42ad1e7e0b69bc8b58c]: Sch. 2 para. 15 in force at 29.12.2022, see art. 1
[^key-4818e48a6012bfefcee81a9b621bfd17]: Sch. 2 para. 16 in force at 29.12.2022, see art. 1
[^key-a7ccfd3a4f7b5f685fc02cf5df94a85b]: Sch. 2 para. 17 in force at 29.12.2022, see art. 1
[^key-2399475fd17133ef619a4c23361266e8]: Sch. 2 para. 18 in force at 29.12.2022, see art. 1
[^key-cc8f7b7840e323bf5138eb9623334892]: Sch. 2 para. 19 in force at 29.12.2022, see art. 1
[^key-027e7b71204288d69cc7a1d7fc20a6ec]: Sch. 2 para. 20 in force at 29.12.2022, see art. 1
[^key-2142ea0dd5cdc88b9f4c50b26c8bfc00]: Sch. 2 para. 21 in force at 29.12.2022, see art. 1
[^key-a2b1271f31fcbdaa07279974b8b8734b]: Sch. 2 para. 22 in force at 29.12.2022, see art. 1
[^key-40da756eef39ee341611116455b22fa4]: Sch. 2 para. 23 in force at 29.12.2022, see art. 1
[^key-ac4504a868c4b12ab174f459a6e568ff]: Sch. 2 para. 24 in force at 29.12.2022, see art. 1
[^key-547f5711f1fe6b471a41edae45c64151]: Sch. 2 para. 25 in force at 29.12.2022, see art. 1
[^key-5de5cd5adfbd5b97c9baf1f4275cd6fa]: Sch. 2 para. 26 in force at 29.12.2022, see art. 1
[^key-78453757ee0e66ab34a189379218141f]: Sch. 2 para. 27 in force at 29.12.2022, see art. 1
[^key-fb0dc6e85b76ba984c3e2ce3c731991f]: Sch. 2 para. 28 in force at 29.12.2022, see art. 1
[^key-0e04b1a26b99b32f95fc209d8cce4eeb]: Sch. 2 para. 29 in force at 29.12.2022, see art. 1
[^key-8d741d44b7636791272dcadd220400ad]: Sch. 2 para. 30 in force at 29.12.2022, see art. 1
[^key-6d5c4335b7ee34974847828220efd0a9]: Sch. 2 para. 31 in force at 29.12.2022, see art. 1
[^key-75fab9cb6158bc9072beb9ed0287e77b]: Sch. 2 para. 32 in force at 29.12.2022, see art. 1
[^key-1b29acf9682b901c11a34c0734904ab9]: Sch. 2 para. 33 in force at 29.12.2022, see art. 1
[^key-481cff9d5d3dfcbeaf3e9df016b8ff8c]: Sch. 2 para. 34 in force at 29.12.2022, see art. 1
[^key-dd4d6e31f6c5cfbb4ef789cd34d1d8d5]: Sch. 2 para. 35 in force at 29.12.2022, see art. 1
[^key-446737fe1b2cce13ffeeeb21a90c89f2]: Sch. 2 para. 36 in force at 29.12.2022, see art. 1
[^key-0db932185c9f8bb2e559a4c68629bcd5]: Sch. 2 para. 37 in force at 29.12.2022, see art. 1
[^key-e3873d27870d0e50daf95f74bfb7cf34]: Sch. 2 para. 38 in force at 29.12.2022, see art. 1
[^key-9ea882e8ccc982af423caee1470a213e]: Sch. 2 para. 39 in force at 29.12.2022, see art. 1
[^key-4caf92dd3cd91d515703138fc01f0366]: Sch. 2 para. 40 in force at 29.12.2022, see art. 1
[^key-a0dc7b44693093999c96ccfefaf64529]: Sch. 2 para. 41 in force at 29.12.2022, see art. 1
[^key-5cfcb4b6bc44dd944e1463b2ce914450]: Sch. 6 para. 1 in force at 29.12.2022, see art. 1
[^key-90250256c4c99ffcdb72ba6649213cfa]: Sch. 7 para. 1 in force at 29.12.2022, see art. 1
[^key-8933baeb8657f1768c73f4eeb543cdf1]: Sch. 7 para. 2 in force at 29.12.2022, see art. 1
[^key-91107b8030d326fa6c5667cb2a9c7d23]: Sch. 7 para. 3 in force at 29.12.2022, see art. 1
[^key-215c65a5952686e2bd65aa274ce543a7]: Sch. 7 para. 4 in force at 29.12.2022, see art. 1
[^key-429f49eeb6932b897b6e158be2597887]: Sch. 7 para. 5 in force at 29.12.2022, see art. 1
[^key-c97b4c2cfe3898e68c6d1945ad1845dd]: Sch. 9 para. 1 in force at 29.12.2022, see art. 1
[^key-f1d521b124b375d490bf166cedb033b0]: Sch. 9 para. 2 in force at 29.12.2022, see art. 1
[^key-2a4b5714f6d577ab0447b83c1da50d07]: Sch. 9 para. 3 in force at 29.12.2022, see art. 1
[^key-ae0f0dc2d63867545960f833479075a5]: Sch. 9 para. 4 in force at 29.12.2022, see art. 1
[^key-4f938f9803340c47b727ce7544d9f5be]: Sch. 9 para. 5 in force at 29.12.2022, see art. 1
[^key-276789534819471744c5fc9f8a457e04]: Sch. 10 para. 1 in force at 29.12.2022, see art. 1
[^key-b8b71e54d13988052a91a88152a1137c]: Sch. 10 para. 2 in force at 29.12.2022, see art. 1
[^key-c4172efed477a29765572d8a8672ca1c]: Sch. 10 para. 3 in force at 29.12.2022, see art. 1
[^key-25ac6a129b99270e57cd1dd77f95b7bf]: Sch. 10 para. 4 in force at 29.12.2022, see art. 1
[^key-c287ca0d709bb46cac736425ab79460c]: Sch. 10 para. 5 in force at 29.12.2022, see art. 1
[^key-2f95d2f7929db663247c615781d5619d]: Sch. 10 para. 6 in force at 29.12.2022, see art. 1
[^key-49d41f4e84465bc7395f12b0537faa9c]: Sch. 10 para. 7 in force at 29.12.2022, see art. 1
[^key-89ab0aa61c5a995e2fbde998823d70e0]: Sch. 10 para. 8 in force at 29.12.2022, see art. 1
[^key-c10e98e53d5a04a44b3c2c92320a3fa6]: Sch. 10 para. 9 in force at 29.12.2022, see art. 1
[^key-4883a002188af70c61c2f16047de29de]: Sch. 10 para. 10 in force at 29.12.2022, see art. 1
[^key-7a95dcdcdc4022f2f14c99d2b7b26c90]: Sch. 10 para. 11 in force at 29.12.2022, see art. 1
[^key-9399c4619b8f7de598d354b3013052f4]: Sch. 10 para. 12 in force at 29.12.2022, see art. 1
[^key-54f99a7266e57c6a3d595c4136786459]: Sch. 10 para. 13 in force at 29.12.2022, see art. 1
[^key-d60b3606e97ee6bdd59b593245c34161]: Sch. 10 para. 14 in force at 29.12.2022, see art. 1
[^key-a3135632e932408b7194513eaa2e6a12]: Sch. 10 para. 15 in force at 29.12.2022, see art. 1
[^key-d2cbb142f6ea9a85de25e1e10e88a1fc]: Sch. 10 para. 16 in force at 29.12.2022, see art. 1
[^key-edbacdfecf9f6a74c9463fdc78d6dce0]: Sch. 10 para. 17 in force at 29.12.2022, see art. 1
[^key-86fd60560603aa28d6acd7330ba1d05d]: Sch. 10 para. 18 in force at 29.12.2022, see art. 1
[^key-b2a218fe94c259a94505d1612599e9a2]: Sch. 10 para. 19 in force at 29.12.2022, see art. 1
[^key-a71d123e70b1ecd6b77a46f49fc611a5]: Sch. 10 para. 20 in force at 29.12.2022, see art. 1
[^key-9f9cca5a991a19f83923c90057acf093]: Sch. 10 para. 21 in force at 29.12.2022, see art. 1
[^key-e269a0f773f3dcd61ff29e50a4abda83]: Sch. 10 para. 22 in force at 29.12.2022, see art. 1
[^key-1c5e1c0423334b788acaf9376281e0f0]: Sch. 10 para. 23 in force at 29.12.2022, see art. 1
[^key-a4aba08a671deff5d43b9915fcd76e56]: Sch. 10 para. 24 in force at 29.12.2022, see art. 1
[^key-4492c9b61735570ce1f85a5a78c110e4]: Sch. 10 para. 25 in force at 29.12.2022, see art. 1
[^key-bea8a53274864ddab5d981c62ad7a6ef]: Sch. 10 para. 26 in force at 29.12.2022, see art. 1
[^key-8397ae396c240e7515e1fba449693871]: Sch. 10 para. 27 in force at 29.12.2022, see art. 1
[^key-24a4f47f884bc6dca030927788e30d5a]: Sch. 10 para. 28 in force at 29.12.2022, see art. 1
[^key-d0345257164f7b4b6c96e468da4c21ab]: Sch. 10 para. 29 in force at 29.12.2022, see art. 1
[^key-77425d4db53377eccb9839eb34988979]: Sch. 10 para. 30 in force at 29.12.2022, see art. 1
[^key-65f946b94a979d702a1489994a01b94c]: Sch. 10 para. 31 in force at 29.12.2022, see art. 1
[^key-5649f00ee5947a01a5535491c7caa92a]: Sch. 10 para. 32 in force at 29.12.2022, see art. 1
[^key-333b1b8fbc6905b0a2835899cd653f49]: Sch. 10 para. 33 in force at 29.12.2022, see art. 1
[^key-3508c5ff94e6fd0235e2b7475e6da0e9]: Sch. 10 para. 34 in force at 29.12.2022, see art. 1
[^key-c778c5bfe0d5a69a242678850ce1830e]: Sch. 10 para. 35 in force at 29.12.2022, see art. 1
[^key-f34abf88b7d643dd82c2d6b50ffdf1c2]: Sch. 10 para. 36 in force at 29.12.2022, see art. 1
[^key-abb7e41849a8ff463d198d36e3c82053]: Sch. 10 para. 37 in force at 29.12.2022, see art. 1
[^key-ff06984abb8dd42c7f440362ab9b3c2a]: Sch. 10 para. 38 in force at 29.12.2022, see art. 1
[^key-bbf7fe291b6c70e90b7078c334d6ed52]: Sch. 10 para. 39 in force at 29.12.2022, see art. 1
[^key-a55ca39a639cbf8ced1deaa408a2c43e]: Sch. 10 para. 40 in force at 29.12.2022, see art. 1
[^key-fa5d99577f7239aac32e0ed3df0098e5]: Sch. 10 para. 41 in force at 29.12.2022, see art. 1
[^key-e9bbf41e2625734a0e7f03c7715e77bc]: Sch. 10 para. 42 in force at 29.12.2022, see art. 1
[^key-dd6b158f01db317b0e5e54a41ef3daff]: Sch. 10 para. 43 in force at 29.12.2022, see art. 1
[^key-f8475492d2919c98178e8e788c3e5c66]: Sch. 10 para. 44 in force at 29.12.2022, see art. 1
[^key-394e2087e19f8c04cd759991fc9a8425]: Sch. 10 para. 45 in force at 29.12.2022, see art. 1
[^key-12981a0573a4e3b033d587bcb99d5f68]: Sch. 10 para. 46 in force at 29.12.2022, see art. 1
[^key-dc755df204186787854b3c1bf1a30f84]: Sch. 10 para. 47 in force at 29.12.2022, see art. 1
[^key-90b50b72599169c9723b87e0e9709004]: Sch. 10 para. 48 in force at 29.12.2022, see art. 1
[^key-903acc4e3717dd559d9e7c7f63e1dd32]: Sch. 10 para. 49 in force at 29.12.2022, see art. 1
[^key-9f0a4a4cab914b367e53a733cc1f71e0]: Sch. 10 para. 50 in force at 29.12.2022, see art. 1
[^key-54c3677e6f038b734470d928d91f117a]: Sch. 10 para. 51 in force at 29.12.2022, see art. 1
[^key-7d093002c24612e20f3dce69db09ef90]: Sch. 10 para. 52 in force at 29.12.2022, see art. 1
[^key-96fddf26e53403296faa3ba91e3d9828]: Sch. 10 para. 53 in force at 29.12.2022, see art. 1
[^key-5f0481b8e69c886265398217673cebba]: Sch. 10 para. 54 in force at 29.12.2022, see art. 1
[^key-4ef8d3c97dd81bdf8846bf96e44a6983]: Sch. 10 para. 55 in force at 29.12.2022, see art. 1
[^key-08a80f600b1f9e782e82a351603f1439]: Sch. 10 para. 56 in force at 29.12.2022, see art. 1
[^key-449b98abf882183bb3ac3df535c64477]: Sch. 10 para. 57 in force at 29.12.2022, see art. 1
[^key-8f998f44e26623cb97e5d98f88c9a1e4]: Sch. 10 para. 58 in force at 29.12.2022, see art. 1
[^key-7abb9bb9722c08e08dd8421ebbd7e6c5]: Sch. 10 para. 59 in force at 29.12.2022, see art. 1
[^key-ad017ddce04afcdfa825d845020ff71b]: Sch. 10 para. 60 in force at 29.12.2022, see art. 1
[^key-9bbf55236f9c9e071d674c0cae17bb5f]: Sch. 10 para. 61 in force at 29.12.2022, see art. 1
[^key-2c510b4be22c033dd090a7a09f62dc6c]: Sch. 10 para. 62 in force at 29.12.2022, see art. 1
[^key-6e1132af4c15fa44bc501839dc71aef3]: Sch. 10 para. 63 in force at 29.12.2022, see art. 1
[^key-f38ec70409809aa7aa99b000e5c42f19]: Sch. 10 para. 64 in force at 29.12.2022, see art. 1
[^key-1e8d058e2c230de9cc438fb4934a9cdd]: Sch. 10 para. 65 in force at 29.12.2022, see art. 1
[^key-95cb0a657acdb79adcc384c6fad0fe12]: Sch. 10 para. 66 in force at 29.12.2022, see art. 1
[^key-d5073c90b8746aaad69e1411dcecd086]: Sch. 10 para. 67 in force at 29.12.2022, see art. 1
[^key-accf23b365af71e215f157abe4b80296]: Sch. 10 para. 68 in force at 29.12.2022, see art. 1
[^key-deb0d9ba07a40bf03f9c2d934b0e66a2]: Sch. 10 para. 69 in force at 29.12.2022, see art. 1
[^key-8a870893d9ef5f11cbaa0aa092268bf7]: Sch. 10 para. 70 in force at 29.12.2022, see art. 1
[^key-9b46ce07633de034fbfbb4d3b96bd6d3]: Sch. 10 para. 71 in force at 29.12.2022, see art. 1
[^key-c164f61cfe72a3627ac6b0c9844fb686]: Sch. 10 para. 72 in force at 29.12.2022, see art. 1
[^key-45662dcaae8834cf26521388f7bf647d]: Sch. 10 para. 73 in force at 29.12.2022, see art. 1
[^key-8881044846ce336e46e38dd43fe3fc2c]: Sch. 10 para. 74 in force at 29.12.2022, see art. 1
[^key-12d5db6fdf1e7c8669258bc4358fc223]: Sch. 10 para. 75 in force at 29.12.2022, see art. 1
[^key-c037780a33832fd985cbc69a4a56b564]: Sch. 10 para. 76 in force at 29.12.2022, see art. 1
[^key-825090da223caf9f865e25c40c85125f]: Sch. 10 para. 77 in force at 29.12.2022, see art. 1
[^key-ce8b76d224d28ef10ba827af5a03b709]: Sch. 10 para. 78 in force at 29.12.2022, see art. 1
[^key-0419611fbc204781dc517753aeb4dc63]: Sch. 10 para. 79 in force at 29.12.2022, see art. 1
[^key-85d0c68dccc0e812503912001d95015d]: Sch. 10 para. 80 in force at 29.12.2022, see art. 1
[^key-47ee9ad67cc895455affa2283510be48]: Sch. 10 para. 81 in force at 29.12.2022, see art. 1
[^key-54c29a5cb6e2fab16d0227a00bccbc78]: Sch. 10 para. 82 in force at 29.12.2022, see art. 1
[^key-fd822efc88bbfaf3795588226ec7f625]: Sch. 10 para. 83 in force at 29.12.2022, see art. 1
[^key-8bf2c9718ec6639b0cf5053449fc8e44]: Sch. 10 para. 84 in force at 29.12.2022, see art. 1
[^key-a70b292e0c8f9a8cd5714217d2531478]: Sch. 10 para. 85 in force at 29.12.2022, see art. 1
[^key-10354a99e528e1964ce3f5ac8b68456f]: Sch. 10 para. 86 in force at 29.12.2022, see art. 1
[^key-7c4cfda58738694948d48e1b2c4245a2]: Sch. 10 para. 87 in force at 29.12.2022, see art. 1
[^key-4f45fc7116dddd989a2ffd9cc6c84fa0]: Sch. 10 para. 88 in force at 29.12.2022, see art. 1
[^key-b76fb1f181f3af9b371b58efe098b0e5]: Sch. 10 para. 89 in force at 29.12.2022, see art. 1
[^key-aefb232dc07f56e37a0b9a4c4ce42d41]: Sch. 10 para. 90 in force at 29.12.2022, see art. 1
[^key-a458b1fa72d13d7a04eb24ff0dc66072]: Sch. 10 para. 91 in force at 29.12.2022, see art. 1
[^key-aae36b7a553d69ca5ef83456f7a3c8af]: Sch. 10 para. 92 in force at 29.12.2022, see art. 1
[^key-d1aae4e9e565dcee3e82805d8b7f816e]: Sch. 10 para. 93 in force at 29.12.2022, see art. 1
[^key-11d729d6945ed3aab714cd0ac1a061fe]: Sch. 10 para. 94 in force at 29.12.2022, see art. 1
[^key-ee264698a2d7be28d28f91507ac9d80f]: Sch. 10 para. 95 in force at 29.12.2022, see art. 1
[^key-dbd15cd4056d14db49aa271dc58b1776]: Sch. 10 para. 96 in force at 29.12.2022, see art. 1
[^key-fc6b49a23eb4f6921f97a510440f4def]: Sch. 10 para. 97 in force at 29.12.2022, see art. 1
[^key-ea829edfb9b146d930a156c460f8d700]: Sch. 10 para. 98 in force at 29.12.2022, see art. 1
[^key-55d23f5e18fa67f4ecab059ec9bfcea8]: Sch. 10 para. 99 in force at 29.12.2022, see art. 1
[^key-2de3ea0f12aa757e504306e6f43dd5d2]: Sch. 10 para. 100 in force at 29.12.2022, see art. 1
[^key-8808d518efc77407ae88214b467e1e6a]: Sch. 10 para. 101 in force at 29.12.2022, see art. 1
[^key-cd1eaa32fb1cc03972338a24d7b7a341]: Sch. 10 para. 102 in force at 29.12.2022, see art. 1
[^key-3ebc0898258d4b87a3d07e1adcb5d7dd]: Sch. 10 para. 103 in force at 29.12.2022, see art. 1
[^key-9c9ca9ef537e034a055e29f255126d1b]: Sch. 10 para. 104 in force at 29.12.2022, see art. 1
[^key-c9af986c1d5853ef7ac20c47c2be825a]: Sch. 10 para. 105 in force at 29.12.2022, see art. 1
[^key-061a416cd928263c94d0d6a37a986f05]: Sch. 11 para. 1 in force at 29.12.2022, see art. 1
[^key-f276caf2e711da6e19a66aef078f615d]: Sch. 11 para. 2 in force at 29.12.2022, see art. 1
[^key-496c0f8d435196d9daf856a6bccb256a]: Sch. 11 para. 3 in force at 29.12.2022, see art. 1
[^key-0e406f0aa86df9dadc9c663c84a3d2d3]: Sch. 11 para. 4 in force at 29.12.2022, see art. 1
[^key-e652420da6b5200175fa14744f6fd228]: Sch. 13 para. 1 in force at 29.12.2022, see art. 1
[^key-99b5acecf41265ef0c6ca748ea8d180e]: Sch. 13 para. 2 in force at 29.12.2022, see art. 1
[^key-e026cd3264e618044e96b8da7f1c08b9]: Sch. 13 para. 3 in force at 29.12.2022, see art. 1
[^key-429658b7c1a8fdf668ca4191a06d9056]: Sch. 13 para. 4 in force at 29.12.2022, see art. 1
[^key-d54f838ab7fb3e35f3abf5a19460525a]: Sch. 13 para. 5 in force at 29.12.2022, see art. 1
[^key-2c6e3f1ffaafef2e879688a7de91bcb2]: Sch. 13 para. 6 in force at 29.12.2022, see art. 1
[^key-6bb3049a50859b7e1ffe91120ede4803]: Sch. 13 para. 7 in force at 29.12.2022, see art. 1
[^key-392074af443d9755c646884f54500373]: Sch. 13 para. 8 in force at 29.12.2022, see art. 1
[^key-f8674f4b8eb4b37ce4babe537408df84]: Sch. 13 para. 9 in force at 29.12.2022, see art. 1
[^key-afd5211f6520cb8b9675f27cb83c50d1]: Sch. 13 para. 10 in force at 29.12.2022, see art. 1
[^key-04abcf20b567b8fabb3f54da0f2dfee1]: Sch. 13 para. 11 in force at 29.12.2022, see art. 1
[^key-3c93fd76079b63c97cedf1017ca81b53]: Sch. 13 para. 12 in force at 29.12.2022, see art. 1
[^key-8ec16a3e233108faf191c1255b0b727f]: Sch. 13 para. 13 in force at 29.12.2022, see art. 1
[^key-c1347581af5e05ad91a299347151a8d2]: Sch. 13 para. 14 in force at 29.12.2022, see art. 1
[^key-efda39f3398148735c5e5502b9d44ebd]: Sch. 13 para. 15 in force at 29.12.2022, see art. 1
[^key-754efd36a8f7c6eb27ac14886f9fcffc]: Sch. 13 para. 16 in force at 29.12.2022, see art. 1
[^key-d68ea0f4d3481ff5e47fb589d62aafa0]: Sch. 13 para. 17 in force at 29.12.2022, see art. 1
[^key-ab3dca9b6493b11b51b1eb7027859974]: Sch. 13 para. 18 in force at 29.12.2022, see art. 1
[^key-629cc57799425db8d8ab21ed97356e82]: Sch. 13 para. 19 in force at 29.12.2022, see art. 1
[^key-f77da794439dc28ad56dad638a967de6]: Sch. 13 para. 20 in force at 29.12.2022, see art. 1
[^key-bc8430fd7047a2b81907ce92d96f1ef4]: Sch. 13 para. 21 in force at 29.12.2022, see art. 1
[^key-b4f3a7028f21e1899a0bd0e3890005e2]: Sch. 13 para. 22 in force at 29.12.2022, see art. 1
[^key-dcac56019ff4e37962d20ad654851dc2]: Sch. 13 para. 23 in force at 29.12.2022, see art. 1
[^key-b6fb9f453305c1ffdd8486192aa9a6db]: Sch. 13 para. 24 in force at 29.12.2022, see art. 1
[^key-8b1d8bf3a3dbe6382c6cec1902bcc348]: Sch. 13 para. 25 in force at 29.12.2022, see art. 1
[^key-717a1168c6ecc16056a1e4405d6669d9]: Sch. 13 para. 26 in force at 29.12.2022, see art. 1
[^key-d727c49da25941c0c987808ed835061f]: Sch. 13 para. 27 in force at 29.12.2022, see art. 1
[^key-b6f523c8579fec609a4135201480ddae]: Sch. 1 in force at 29.12.2022, see art. 1
[^key-d5c48ed4c5536c9cd0240e36f53d011e]: Sch. 3 in force at 29.12.2022, see art. 1
[^key-b555b7a006582a923cd10bfe5ef500db]: Sch. 4 in force at 29.12.2022, see art. 1
[^key-826630eb3c4cafa27a9c516eed9bef9d]: Sch. 5 in force at 29.12.2022, see art. 1
[^key-6f0a82aa96db9b0f2c9f14a0a153744e]: Sch. 8 in force at 29.12.2022, see art. 1
[^key-d95d86f19956088caf5516198d9458d2]: Sch. 12 in force at 29.12.2022, see art. 1
[^key-5e685b12a99d476aecc7e5547d8ec781]: Words in art. 2 added (20.4.2023) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023 (S.I. 2023/442), art. 1, Sch.
[^key-93b3f4d82b6ffee1c7c7db7639d78d0e]: Words in art. 21(3) substituted (20.4.2023) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023 (S.I. 2023/442), art. 1, Sch.
[^key-d2eecb10fe1c28bba6fe33e5aef350ac]: Words in art. 21(3) added (20.4.2023) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023 (S.I. 2023/442), art. 1, Sch.
[^key-94e9e70490d4e8723217e5db0b2192d1]: Word in Sch. 9 para. 4(2)(b)(ii) substituted (20.4.2023) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023 (S.I. 2023/442), art. 1, Sch.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.