The A47 North Tuddenham to Easton Development Consent Order 2022
- (7) Paragraphs (3) to (6) do not apply where the authorised development constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead—
- (a) the allowable costs of the relocation works are to be determined in accordance with section 85 (sharing of cost of necessary measures) of that Act and any regulations for the time being having effect under that section; and
- (b) the allowable costs are to be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.
- (8) In this article—
- “relocation works” means work executed, or apparatus provided, under paragraph (2); and
- “statutory utility” means a statutory undertaker for the purposes of the 1980 Act or a public communications provider as defined in section 151(1) of the Communications Act 2003[^f00073].
Recovery of costs of new connections
37
- (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 35 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
- (2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 35, any person who is—
- (a) the owner or occupier of premises the drains of which communicated with that sewer; or
- (b) the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
- (3) This article does not have effect in relation to apparatus to which article 36 (apparatus and rights of statutory undertakers in stopped up streets) ro Part 3 of the 1991 Act applies.
- (4) In this paragraph—
- “public communications provider” has the same meaning as in section 151(1) (interpretation of chapter 1) of the Communications Act 2003[^f00074]; and
- “public utility undertaker” means a gas, water, electricity or sewerage undertaker.
Special category land
38
- (1) On the exercise by the undertaker of the relevant Order powers, so much of the special category land as is required for the purposes of the exercise by the undertaker of the Order rights is discharged from all rights, trusts and incidents to which it was previously subject, so far as their continuance would be inconsistent with the exercise by the undertaker of the Order rights.
- (2) So far as the temporary use of land under article 33 (temporary use of land for carrying out the authorised development) is concerned, then the discharge in paragraph (1) is only for such time as the land is being used under that article.
- (3) In this article—
- “Order rights” means the rights and powers exercisable over the special category land by the undertaker under article 26 (compulsory acquisition of rights and imposition of restrictive covenants) and article 33; and
- “special category land” means the land identified as forming part of a public open space numbered 1/2f, 1/2i and 2/2a in the book of reference and on the plan entitled “special category land plans”.
PART 6 — OPERATIONS
Felling or lopping of trees and removal of hedgerows
39
- (1) The undertaker may fell or lop any tree or shrub, within or overhanging land within the Order limits, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—
- (a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or
- (b) from constituting a danger to persons using the authorised development.
- (2) In carrying out any activity authorised by paragraph (1) or (4), the undertaker must
- (a) do no unnecessary damage to any tree or shrub;
- (b) pay compensation to any person for any loss or damage arising from such activity; and
- (c) take steps to avoid a breach of the provisions of the Wildlife and Countryside Act 1981[^f00075] and the Conservation of Habitats and Species Regulations 2017[^f00076] or any successor acts and regulations.
- (3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined as if it were a dispute under Part 1 of the 1961 Act.
- (4) The undertaker may, for the purposes of carrying out the authorised development but subject to paragraph (2) —
- (a) remove any hedgerows within the Order limits and specified in Schedule 8 Part 1 (removal of hedgerows);
- (b) remove the important hedgerows as are within the Order limits and specified in Schedule 8 Part 2 (removal of important hedgerows); and
- (c) without limitation on the scope of sub-paragraph (a), and with the consent of the local authority in whose area the hedgerow is located, remove or translocate any hedgerow within the Order limits that is required to be removed.
- (5) The grant of consent of a local authority in terms of paragraph (4)(c) must not be unreasonably withheld.
- (6) If a local authority fails to notify the undertaker of its decision within 28 days of receiving an application for consent under paragraph (4)(c) the local authority is deemed to have granted consent.
- (7) Any application to which this article applies must include a statement that the provisions of paragraph (6) apply to that application.
- (8) In this article “hedgerow” and “important hedgerow” have the same meaning as in the Hedgerow Regulations 1997[^f00077].
Trees subject to tree preservation orders
40
- (1) The undertaker may fell or lop any tree within or overhanging land within the Order limits subject to a tree preservation order which was made after 24 July 2020, if the undertaker reasonably believes it to be necessary to do so to prevent the tree or shrub—
- (a) from obstructing or interfering with the construction, maintenance or operation of the authorised development or any apparatus used in connection with the authorised development; or
- (b) from constituting a danger to passengers or other persons using the authorised development.
- (2) In carrying out any activity authorised by paragraph (1)—
- (a) the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity;
- (b) the duty contained in section 206(1)[^f00078] (replacement of trees) of the 1990 Act is not to apply although where possible the undertaker is to seek to replace any trees which are removed; and
- (c) the undertaker must consult the relevant planning authority prior to that activity taking place.
- (3) The authority given in paragraph (1) constitutes a deemed consent under the relevant tree preservation order.
- (4) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
PART 7 — MISCELLANEOUS AND GENERAL
Application of landlord and tenant law
41
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
- (3) No such enactment or rule of law applies in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for purposes of the 1990 Act
42
Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) (cases in which land is to be treated as operational land for the purposes of that Act) of the 1990 Act.
Defence to proceedings in respect of statutory nuisance
43
- (1) Where proceedings are brought under section 82(1) (summary proceedings by person aggrieved by statutory nuisance) of the Environmental Protection Act 1990[^f00079] in relation to a nuisance falling within paragraphs (d), (fb), (g) or (ga) of section 79(1) (statutory nuisances and inspections therefor) of that Act no order is to be made, and no fine may be imposed, under section 82(2)[^f00080] of that Act if—
- (a) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction sites), or a consent given under section 61 (prior consent for work on construction sites), of the Control of Pollution Act 1974; or
- (ii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or
- (b) the defendant shows that the nuisance is a consequence of the use of the authorised development and that it cannot reasonably be avoided.
- (2) Section 61(9)[^f00081] (prior consent for work on construction sites) to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.
No double recovery
44
Compensation is not payable in respect of the same matter both under this Order and under any other enactment, any contract, or any rule of law, or under two or more different provisions of this Order.
Disregard of certain improvements etc.
45
- (1) In assessing the compensation payable to any person on the acquisition from that person of any land or right over any land under this Order, the tribunal must not take into account—
- (a) any interest in land; or
- (b) any enhancement of the value of any interest in land by reason of any building erected, works carried out or improvement or alteration made on the relevant land,
if the tribunal is satisfied that the creation of the interest, the erection of the building, the carrying out of the works or the making of the improvement or alteration as part of the authorised development was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.
- (2) In paragraph (1) “relevant land” means the land acquired from the person concerned or any other land with which that person is, or was at the time when the building was erected, the works constructed or the improvement or alteration made as part of the authorised development, directly or indirectly concerned.
Set off for enhancement in value of retained land
46
- (1) In assessing the compensation payable to any person in respect of the acquisition from that person under this Order of any land (including the subsoil) the tribunal must set off against the value of the land so acquired any increase in value of any contiguous or adjacent land belonging to that person in the same capacity which will accrue to that person by reason of the construction of the authorised development.
- (2) In assessing the compensation payable to any person in respect of the acquisition from that person of any new rights over land (including the subsoil) under article 26 (compulsory acquisition of rights and imposition of restrictive covenants), the tribunal must set off against the value of the rights so acquired—
- (a) any increase in the value of the land over which the new rights are required; and
- (b) any increase in value of any contiguous or adjacent land belonging to that person in the same capacity,
which will accrue to that person by reason of the construction of the authorised development.
- (3) The 1961 Act has effect, subject to paragraphs (1) and (2) as if this Order were a local enactment for the purposes of that Act.
Appeals relating to the Control of Pollution Act 1974
47
- (1) The undertaker may appeal in the event that a local authority issues a notice under section 60 (control of noise on construction sites), or does not give consent or grants consent but subject to conditions, under section 61 (prior consent for work on construction sites) of the Control of Pollution Act 1974[^f00082].
- (2) The appeal process is as follows—
- (a) any appeal by the undertaker must be made within 42 days of the date of the notice of the decision, or the date by which a decision was due to be made, as the case may be;
- (b) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the local authority and affix a notice to a conspicuous object on or near the site of the works which are the subject of such appeal, which must give details of the decision of the local authority and notice that an appeal has been made together with the address within the locality where the appeal documents may be inspected and details of the manner in which representations on the appeal may be made;
- (c) as soon as is practicable after receiving the appeal documentation, the Secretary of State must appoint a person to consider the appeal (“the appointed person”) and must notify the appeal parties of the identity of the appointed person, a start date and the address to which all correspondence for their attention should be sent;
- (d) the local authority must submit their written representations to the appointed person in respect of the appeal within 10 business days of the start date and must ensure that copies of their written representations and any other representations as sent to the appointed person are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (e) the appeal parties must make any counter-submissions to the appointed person within 10 business days of receipt of written representations under sub-paragraph (d); and
- (f) the appointed person must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable.
- (3) The appointment of the person under sub-paragraph (2)(c) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (4) In the event that the appointed person considers that further information is necessary to enable the appointed person to consider the appeal, the appointed person must as soon as practicable notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information is to be submitted.
- (5) Any further information required under paragraph (4) must be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person.
- (6) The appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day.
- (7) The revised timetable for the appeal must require submission of written representations to the appointed person within 10 business days of the agreed date but must otherwise be in accordance with the process and time limits set out in sub-paragraphs (2)(c) to (e).
- (8) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the local authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to the appointed person in the first instance.
- (9) The appointed person may proceed to a decision on an appeal taking into account such written representations as have been sent within the relevant time limits and in the sole discretion of the appointed person such written representations as have been sent outside the relevant time limits.
- (10) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.
- (11) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (12) Except where a direction is given under paragraph (13) requiring some or all of the costs of the appointed person to be paid by the local authority, the reasonable costs of the appointed person must be met by the undertaker.
- (13) The appointed person may give directions as to the costs of the appeal and as to the parties by whom such costs are to be paid.
- (14) In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to the relevant Planning Practice Guidance published by the Department for Levelling Up, Housing, and Communities or such guidance as may from time to time replace it.
Use of consecrated land
48
- (1) Section 239 (use and development of burial grounds) of the 1990 Act applies—
- (a) in relation to land, other than a right over land, acquired for the purposes of the authorised development (whether or not by agreement), so as to permit use by the undertaker in accordance with the provisions of this Order; and
- (b) in relation to a right over land so acquired (whether or not by agreement), or the temporary use of land pursuant to articles 33 (temporary use of land for constructing the authorised development) or 34 (temporary use of land for maintaining the authorised development), so as to permit the exercise of that right or the temporary use by the undertaker in accordance with the provisions of this Order,
and in section 240(3) of the 1990 Act reference to a “statutory undertaker” includes the undertaker and reference to “any other enactment” includes this Order.
- (2) The Town and Country Planning (Churches, Places of Religious Worship and Burial Grounds) Regulations 1950[^f00083] do not apply to the authorised development.
Protection of interests
49
Schedule 9 (protective provisions) to the Order has effect.
Certification of documents, etc.
50
- (1) As soon as practicable after the making of this Order, the undertaker must submit copies of each of the plans and documents set out in Schedule 10 (documents, etc to be certified) to the Secretary of State for certification as true copies of those plans and documents.
- (2) Where any plan or document set out in Schedule 10 requires to be amended to reflect the terms of the Secretary of State’s decision to make the Order, that plan or document in the form amended to the Secretary of State’s satisfaction is the version of the plan or document required to be certified under paragraph (1).
- (3) A plan or document so certified will be admissible in any proceedings as evidence of the contents of the document of which it is a copy.
Service of notices
51
- (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
- (a) by post;
- (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
- (c) with the consent of the recipient and subject to paragraphs (5) to (8) by electronic transmission.
- (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
- (3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978[^f00084] as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address, and otherwise—
- (a) in the case of the secretary or clerk of a body corporate, the registered or principal office of that body; and
- (b) in any other case, the last known address of that person at the time of service.
- (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
- (a) addressing it to that person by name or by the description of “owner”, or as the case may be “occupier”, of the land (describing it); and
- (b) either leaving it in the hands of a person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
- (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
- (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
- (b) the notice or document is capable of being accessed by the recipient;
- (c) the notice or document is legible in all material respects; and
- (d) the notice or document is in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that the recipient requires a paper copy of all or part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of electronic communication given by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than 7 days after the date on which the notice is given.
- (9) This article does not exclude the employment of any method of service not expressly provided for by it.
- (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of a notice or document in printed form.
Arbitration
52
Except where otherwise expressly provided for in this Order and unless otherwise agreed between the parties, any difference under any provision of this Order (other than a difference which falls to be determined by the tribunal) must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.
Crown Rights
53
- (1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and in particular, nothing in this Order authorises the undertaker to use, enter upon or in any manner interfere with any land or rights of any description—
- (a) belonging to Her Majesty in right of the Crown and forming part of The Crown Estate without the consent in writing of the Crown Estate Commissioners;
- (b) belonging to Her Majesty in right of the Crown and not forming part of The Crown Estate without the consent in writing of the government department having the management of that land; or
- (c) belonging to a government department or held in trust for Her Majesty for the purposes of a government department without the consent in writing of that government department.
- (2) Paragraph (1) does not apply to the exercise of any right under this Order for the compulsory purchase of any interest in any Crown land (as defined in the 2008 Act) for the time being held otherwise than by or on behalf of the Crown.
- (3) A consent under paragraph (1) may be given unconditionally or subject to terms and conditions; and is deemed to have been given in writing where it is sent electronically.
SCHEDULE 1 — AUTHORISED DEVELOPMENT
In the administrative areas of Norfolk County Council and Broadland, South Norfolk and Breckland District Councils.
The authorised development is a nationally significant infrastructure project as defined in sections 14 (nationally significant infrastructure projects: general) and 22 (highways)[^f00085] of the 2008 Act and associated development within the meaning of section 115(2)[^f00086] of the 2008 Act, comprising—
Work No. 1 – Alteration of the A47 of 9,169 metres in length from a point 370m west of Fox Lane overbridge to a point 180m west of Easton roundabout, including the construction of a mainline dual carriageway, footways, embankments, two laybys, police observation platform, maintenance accesses, approaches and associated drainage and noise barriers shown on sheet numbers 1, 2, 4 to 9 and 11 to 16 of the works plans;
Work No. 2 – a combination of re-surfaced, realigned and new carriageway from Main Road east for 380 metres to the new junction with Lyng Road (Work No. 4) and then 775 metres to re-join the existing A47 alignment at the altered junction with Low Road, including footways, embankments, approaches, associated drainage and flood protection bund shown on sheet numbers 1, 2 and 4 of the works plans;
Work No. 3 – a new driveable access track, associated earthworks and drainage, from an existing access onto Fox Lane and a new field access with passing places, running eastwards for 579 metres to a private property east of Oak Farm, shown on sheet number 1 of the works plans;
Work No. 4 – a combination of new and realigned carriageway, footways, embankments, approaches and associated drainage to form the realigned Lyng Road north of the junction with Work No. 2, shown on sheet number 2 of the works plans;
Work No. 5 – drainage works east of Oak Farm comprising an extension of the existing West Culvert under the proposed A47 mainline dual carriageway (Work No.1) and creation of the new West Culvert under Work No. 2 east of the new junction to the realigned Lyng Road (Work No. 4), shown on sheet number 2 of the works plans;
Work No. 6 – a new drainage basin south east of Oak Farm, plus associated drainage and driveable maintenance access track with an outfall into the local watercourse and a drainage connection to the basin on the southern side of the proposed A47 mainline dual carriageway (Work No.1), shown on sheet number 2 of the works plans;
Work No. 7 – a new drainage basin with associated drainage and driveable maintenance access track south from the A47 mainline dual carriageway (Work No. 1) with an outfall into the River Tud east of Whitford bridge and a drainage connection to the basin, shown on sheet 4 of the works plans;
Work No. 8 – a combination of new and widened carriageway, footways, embankments and associated drainage between the existing Mattishall Lane alignment and the proposed Mattishall Lane Link Road (Work No. 9), shown on sheet number 4 of the works plans;
Work No. 9 – a new carriageway, footways, approaches, drainage and underbridge with cycle track forming the new Mattishall Lane Link Road from the existing A47 471 metres south west to Mattishall Lane, shown on sheet number 4 of the works plans;
Work No. 10 – alteration of the existing A47 and Mattishall Lane junction including the provision of a ghost island and the creation and upgrade of footways on Mattishall Lane and the existing A47 between the new Mattishall Lane Link Road (Work No.9) junction to the west and the Hockering junction with the existing A47 to the east plus the creation of a new field access off Mattishall Lane, shown on sheet 4 of the works plans;
Work No. 11 – a new driveable access track with passing places, from Mattishall Lane south of the proposed A47 mainline dual carriageway (Work No. 1) running eastwards for 469 metres, shown on sheet numbers 4 and 5 of the works plans;
Work No. 12 – a new drainage basin, associated drainage and driveable maintenance access track and a new outfall into the River Tud between Work No. 11 and the River Tud with a drainage connection to the basin, shown on sheet number 5 of the works plans;
Work No. 13 – a new culvert at Newgate House, under the proposed A47 mainline dual carriageway (Work No. 1) south of Gypsy Lane, shown on sheet number 6 of the works plans;
Work No. 14 – a new drainage basin east of Gypsy Lane with associated drainage and a driveable maintenance access track north from the A47 mainline dual carriageway (Work No. 1) with an outfall into the River Tud to the south and a drainage connection under the proposed A47 mainline dual carriageway (Work No. 1) to the basin, shown on sheet number 6 of the works plans;
Work No. 15 – a new drainage basin, associated drainage, a wetland area east of Church Lane, and a driveable maintenance access track from Work No 16, with a new outfall into the River Tud east of Church Lane bridge and a drainage connection to the basin shown on sheet number 7 of the works plans;
Work No. 16 – a new driveable access track with passing place, associated earthworks and drainage, from Church Lane 469 metres east to Work No. 15 and Hillcrest Cottage, shown on sheet numbers 7 and 8 of the works plans;
Work No. 17 – a combination of re-surfaced, realigned and new carriageway with cycle track, embankments, approaches and associated drainage to form the new link road from the existing A47 east of Hockering 913 metres east to Wood Lane junction northern dumbbell roundabout (Work No. 20), shown on sheet numbers 7, 8 and 10 of the works plans;
Work No. 18 – a new carriageway, embankments and associated drainage to form the Wood Lane junction east bound off slip road to the northern dumbbell roundabout, shown on sheet numbers 8, 9 and 10 of the works plans;
Work No. 19 – a new carriageway, embankments and associated drainage to form the Wood Lane junction west bound on slip road from the southern dumbbell roundabout, shown on sheet numbers 8 and 9 of the works plans;
Work No. 20 – a new carriageway, embankments and associated drainage to form the Wood Lane junction northern dumbbell roundabout, shown on sheet number 10 of the works plans;
Work No. 21 – a new Wood Lane junction underbridge and associated carriageway, embankments and drainage between the dumbbell roundabouts (Work Nos. 20 and 22), shown on sheet numbers 9 and 10 of the works plans;
Work No. 22 – a new carriageway, embankments and associated drainage to form the Wood Lane junction southern dumbbell roundabout, shown on sheet number 9 of the works plans;
Work No. 23 – a new carriageway, embankments and associated drainage to form the Wood Lane junction east bound on slip road from the northern dumbbell roundabout, shown on sheet numbers 9 and 10 of the works plans;
Work No. 24 – a new carriageway, embankments and associated drainage to form the Wood Lane junction west bound off slip road to the southern dumbbell roundabout, shown on sheet numbers 9 and 11 of the works plans;
Work No. 25 –a combination of re-surfaced and new carriageway, footways, embankments and associated drainage to form the new B1535 Wood Lane junction with Work No. 17, shown on sheet number 10 of the works plans;
Work No. 26 – a new restricted byway from Hall Farm underpass (Work No. 30) west 781 metres to Work No. 26a the optional cycle track connection to the realigned Wood Lane, shown on sheet numbers 9, 10 and 11 of the works plans;
Work No. 26a – a new cycle track between the realigned B1535 Wood Lane (Work No. 25) and the start of the new restricted byway (Work No. 26) which meets the diverted restricted byway Honingham RB1, shown on sheet number 10 of the works plans;
Work No. 27 – a new drainage basin, associated drainage and driveable maintenance access track, between the existing A47 and proposed A47 mainline dual carriageway (Work No. 1) east of the proposed A47 Wood Lane junction southern dumbbell roundabout (Work No. 22), accessed from Work No. 32, shown on sheet number 9 of the works plans;
Work No. 28 – a combination of realigned and new carriageway with footways, embankments, approaches and associated drainage to form the link to Dereham Road, Honingham, from Work No. 32 and traffic calming measures at Dereham Road , shown on sheet numbers 9 of the works plans;
Work No. 29 – a new bridleway with new cycle track between Berrys Lane and Dereham Road to replace an existing parallel footpath, shown on sheet number 9 of the works plans;
Work No. 30 – a new Hall Farm underpass, access road to the existing A47 and new section of associated access ramps joining the new restricted byway from Wood Lane junction (Work No. 26), shown on sheet number 11 of the works plans;
Work No. 31 – a new drainage basin between the existing A47 and proposed A47 mainline dual carriageway (Work No. 1) and south east of Hall Farm underpass (Work No. 30), with associated drainage connections and a driveable maintenance access track to the Hall Farm access track (Work No. 30), shown on sheet number 11 of the works plans;
Work No. 32 – reconfiguration of the existing A47 carriageway north of Honingham with a new cycle track, embankments and associated drainage, including a ghost island at the existing A47 junction with the realigned Dereham Road (Work No.28) and modified Honingham bypass structure over the River Tud, between the Wood Lane junction southern dumbbell roundabout (Work No. 22) east 1,663 metres to the existing A47 Honingham roundabout , shown on sheet numbers 9, 11, 12 and 13 of the works plans;
Work No. 33 – a new driveable private access track with passing places, associated earthworks and drainage, connecting Hall Farm to Hall Farm underpass and access road (Work No. 30), shown on sheet number 11 of the works plans;
Work No. 34 – a new drainage basin, east of the proposed A47 mainline dual carriageway (Work No. 1) and north of the new A47 River Tud crossing (Work No. 35), with associated drainage and a driveable access track from Work No. 1, shown on sheet number 12 of the works plans;
Work No. 35 – a new bridge structure over the River Tud with new carriageway, embankments, approaches and associated drainage for the A47 River Tud crossing, with associated flood risk compensation earthworks south of the River Tud between the existing A47 and proposed A47 mainline dual carriageway (Work No. 1) including fences for the protection of bats shown on sheet number 12 of the works plans;
Work No. 36 – a new drainage basin and wetland area south of the River Tud crossing (Work No. 35), between the existing A47 and proposed A47 mainline dual carriageway (Work No. 1), with associated drainage connections and a new outfall to the River Tud west of the River Tud crossing and driveable maintenance access track from Work No. 32, shown on sheet number 12 of the works plans;
Work No. 37 – a new cycle track between Honingham roundabout and the existing A47 west of St Andrew’s Church (Work No. 39), new Honingham church underpass, embankments, and drainage shown on sheet number 13 of the works plans;
Work No. 38 – a replacement hardstanding area west of St Andrew’s Church, Honingham, and associated access road to the existing A47 (Work No. 39), shown on sheet number 13 of the works plans.
Work No. 39 –alteration and reconfiguration of the existing A47 between the proposed cycle track (Work No. 37) and Taverham Road to provide a single lane access road incorporating parking spaces, a vehicle turning area, a secure access gate and adjacent cycle track south east of St Andrew’s Church, shown on sheet numbers 13 and 14 of the works plans;
Work No. 40 – realigned new carriageway, footways, embankments, and drainage between Honingham roundabout and the proposed Norwich Road junction southern dumbbell roundabout (Work No. 46), shown on sheet numbers 13 and 14 of the works plans;
Work No. 41 – a new drainage basin and wetland area, associated drainage with new outfall to the River Tud and driveable access track, east of Taverham Road and between the River Tud and Work No. 47, shown on sheet 14 of the works plans;
Work No. 42 – a new carriageway, embankments and drainage to form the proposed Norwich Road junction eastbound off-slip road to the northern dumbbell roundabout, shown on sheet numbers 13 and 14 of the works plans;
Work No. 43 – a new carriageway, embankments and drainage to form the proposed Norwich Road junction westbound on-slip road from the southern dumbbell roundabout, shown on sheet numbers 13 and 14 of the works plans;
Work No. 44 – a new carriageway, embankments and drainage to form the proposed Norwich Road junction northern dumbbell roundabout, shown on sheet number 14 of the works plans;
Work No. 45 – a new Norwich Road junction underbridge and associated carriageway, embankments and drainage between the dumbbell roundabouts (Work Nos. 44 and 46), shown on sheet number 14 of the works plans;
Work No. 46 – a new carriageway, embankments and drainage to form the proposed Norwich Road junction southern dumbbell roundabout, shown on sheet number 14 of the works plans;
Work No. 47 – a new and altered carriageway, footways, embankment and drainage from the proposed Norwich Road junction northern dumbbell roundabout (Work No. 44) north 270 metres to Taverham Road, shown on sheet number 14 of the works plans;
Work No. 48 – new carriageway, embankments, approaches and drainage to form the proposed Norwich Road junction east bound on slip road from the northern dumbbell roundabout, shown on sheet numbers 14 and 15 of the works plans;
Work No. 49 – a new carriageway, embankments, approaches and drainage to form the proposed Norwich Road junction west bound off slip road to the southern dumbbell roundabout, shown on sheet numbers 14 and 15 of the works plans;
Work No. 50 – a realigned and new carriageway, embankments, approaches and drainage from the proposed Norwich Road junction southern dumbbell roundabout (Work No. 46) east 1,265 metres to Dereham Road, Easton, shown on sheet numbers 14, 15 and 16 of the works plans;
Work No. 51 – a new carriageway from the realigned Taverham Road (Work No. 47) to a new field access and a new cycle track to Church Lane, Easton, plus associated embankments and drainage, shown on sheet numbers 14, 15 and 16 of the works plans;
Work No. 52 – a new Easton footbridge, embankments, drainage and access ramps to carry a cycle track between Church Lane, north of the A47, and Dereham Road, Easton, shown on sheet numbers 15 and 16 of the works plans;
Work No. 53 – alterations to Church Lane carriageway, embankments and drainage to create a new driveable access road and new cycle track linking Work No. 52 with the junction of Church Lane with Ringland Road, shown on sheet number 16 of the works plans;
Work No. 54 – altering the southern corner of Rotten Row and Church Lane junction with associated drainage alterations, shown on sheet number 17 of the works plans;
Work No. 55 – southern end of a surface water drainage channel crossing the new driveable access track, between Church Lane and Hillcrest Cottage (Work No. 16) from the north side, shown on sheet number 8 of the works plans;
Work No. 56 – flood alleviation compensation and environmental mitigation area including earthworks, embankments, new ponds, new wetlands and watercourse alterations north of Work No. 2 and east of Lyng Road, shown on sheet 2 and sheet number 2 (inset A) of the works plans;
Work No. 57 – flood alleviation compensation and environmental mitigation area, including watercourse alterations and new wetlands, north of The Street and to the east of Hockering, shown on sheet number 6 and sheet number 6 (inset B) of the works plans;
Work No. 58 – a temporary material storage, management and processing area south of the proposed A47 mainline dual carriageway (Work No. 1), south east of Work No. 5, east of Lyng Road and north of Low Road, shown on sheet 2 of the works plans;
Work No. 59 – a traffic management site compound between the existing A47, Low Road, the proposed A47 mainline dual carriageway (Work No. 1) and the proposed Mattishall Lane Link Road (Work No. 9), shown on sheet 4 of the work plans;
Work No. 60 – a temporary material storage area between the existing A47, the proposed A47 mainline dual carriageway (Work No. 1), the proposed Mattishall Lane Link Road (Work No. 9) and existing Mattishall Lane, shown on sheet 4 of the works plans;
Work No. 61 – a temporary material storage, management and processing area, between the existing A47 and proposed A47 mainline dual carriageway (Work No.1) south east of Hockering, shown on sheet numbers 6 and 7 of the works plans;
Work No. 62 – a temporary compound area, including material storage, management and processing, south of the proposed A47 mainline dual carriageway (Work No. 1), east of Hillcrest Cottage and south west of the proposed A47 Wood Lane Junction southern dumbbell roundabout (Work No. 22), including a temporary connection to existing overhead 11kV electricity cables shown on sheets 8 and 9 of the works plans;
Work No. 63 – a temporary material storage area south and west of the proposed A47 Wood Lane Junction southern dumbbell roundabout (Work No. 22), shown on sheet 9 of the works plans;
Work No. 64 – a material storage area north of the proposed A47 mainline dual carriageway (Work No. 1) and east of the proposed A47 Wood Lane Junction northern dumbbell roundabout (Work No. 20), shown on sheet numbers 10 and 11 of the works plans;
Work No. 65 – a temporary main compound area, including material storage, management and processing, south of the existing A47 Honingham roundabout, shown on sheet 13 of the work plans;
Work No. 66 – a temporary material storage, management and processing area south of the existing A47 Honingham roundabout adjacent to east side of Work No. 65, shown on sheet 13 of the work plans;
Work No. 67 – a temporary material storage, management and processing area north east of the proposed A47 Norwich Road junction northern dumbbell roundabout (Work No. 44) and east of Work No. 41, shown on sheet 14 of the works plans;
Work No. 68 – a temporary material storage, management and processing area east of the proposed Norwich Road junction southern dumbbell roundabout (Work No. 46), shown on sheet numbers 14 and 15 of the works plans;
Work No. 69 –a temporary material storage, management and processing area north of the proposed A47 mainline dual carriageway (Work No. 1) situated between Work Nos. 93 and 94, shown on sheet number 15 of the works plans;
Work No. 70 –a temporary material storage, management and processing area north of the proposed A47 mainline dual carriageway (Work No. 1) situated between Work No. 93 and 94, shown on sheet number 15 of the works plans;
Work No. 71 – a temporary compound area north of the existing Easton roundabout and west of Church Lane, Easton, shown on sheet numbers 15 and 16 of the works plans;
Work No. 72 – a temporary material storage, management and processing area north of Work No. 71 and between Work No. 94 and Church Lane, Easton, shown on sheet numbers 15 and 16 of the works plans;
Work No. 73 – removal of the overhead electronic communications cables crossing Work No.1 and 2 between Poppy Wood and Oak Farm, shown on sheet numbers 1 and 2 of the works plans;
Work No. 74 – diversion of potable water pipes and overhead electronic communications and low voltage electricity utility cables along the route of and to the west of the existing Mattishall Lane and crossing Work Nos. 1, 8, 9, 10 and 11, shown on sheet number 4 of the works plans;
Work No. 75 – undergrounding an overhead electronic communications utility line along Mill Lane, Hockering, crossing Work No. 1, shown on sheet number 5 of the works plans;
Work No. 76 – diversion and undergrounding an overhead 11kV electricity line crossing Work No. 1 between the existing A47 and the River Tud, east of Mill Lane, Hockering, shown on sheet number 5 of the works plans;
Work No. 77 – diversion of a main effluent pipeline crossing Work No. 1 between Hockering Water Recycling Centre, Gypsy Lane, and the River Tud, shown on sheet number 6 of the works plans;
Work No. 78 – diversion and undergrounding of an overhead 11kV electricity line crossing Work No. 1 south east of Gypsy Lane and west of a private property at the western end of Trap’s Lane, shown on sheet numbers 6 and 7 of the works plans;
Work No. 79 – diversion and undergrounding of an overhead 11kV electricity line crossing Work No. 1 between the existing A47 and Trap’s Lane, west of Church Lane, shown on sheet number 7 of the works plans;
Work No. 80 – diversion of potable water pipeline and electronic communications cables crossed by Work No. 1, 15, 16 and 17 between the existing A47 and the Church Lane properties and between Church Lane and Hillcrest Cottage, shown on sheet numbers 7 and 8 of the works plans;
Work No. 81 – installation of ducts, cables and apparatus for utilities and electronic communications code operators in north side of the verge of Work No. 17 between the existing A47 and Wood Lane junction northern dumbbell roundabout (Work No. 20), shown on sheet numbers 7, 8 and 10 of the works plans;
Work No. 82 – removal of electronic communications overhead utility cables to Hillcrest Cottage replaced by Work Nos. 80 and 83, shown on sheet number 8 of the works plans;
Work No. 83 – installation of ducts, cables and apparatus for utilities electronic communications code operators along the track between Hillcrest Cottage and Wood Lane junction southern dumbbell roundabout (Work No. 22) crossing Work Nos 1 and 16, shown on sheet numbers 8 and 9 of the works plans;
Work No. 84 – diversion of a high pressure gas pipeline, potable water pipeline and overhead electronic communications and low voltage electricity utility cables along Wood Lane, the existing A47, Berrys Lane and Dereham Road, Honingham, affected by Works Nos. 1, 19, 22, 23, 24, 26, 27, 28, 29 and 32, shown on sheet numbers 9 and 10 of the works plans;
Work No. 85 – diversion and undergrounding of electronic communications overhead utility cables, east of Wood Lane, crossing Work Nos. 1, 17, 18, 20, 21, 22, 24, 25 and 26a, shown on sheet numbers 9 and 10 of the works plans;
Work No. 86 – diversion of 11kV electricity cables crossing the new junction between the new Hall Farm underpass and access road (Work No. 30) and the existing A47, shown on sheet number 11 of the works plans;
Work No. 87 – diversion and undergrounding of electronic communications overhead utility cables along the access track to Hall Farm from the existing A47 crossing Work Nos. 1 and 33, shown on sheet number 11 of the works plans;
Work No. 88 – diversion and undergrounding an overhead 11kV electricity cable crossing Work No. 1 between the existing A47 and Hall Farm, shown on sheet number 11 of the works plans;
Work No. 89 – diversion of a potable water pipeline, an effluent pipeline, overhead electronic communications and low voltage electricity utility cables between the existing Honingham roundabout and existing A47 east of St Andrew’s Church crossed by Works Nos. 1, 32, 37, 38, 39 and 40, shown on sheet numbers 12, 13 and 14 of the works plans;
Work No. 90 – diversion of electricity and electronic communications utility cables crossing the existing A47 and realigned Taverham Road (Works No. 39 and 47), shown on sheet number 14 of the works plans;
Work No. 91 – diversion of electronic communication utility cables crossed by Work Nos. 1, 39, 40, 42, 43 and 47, from Church Farm bridge south along Taverham Road and Blind Lane, then east along Red Barn Lane and Church Road to a connection beside Dereham Road, south-east of St Peter’s Church, Easton, shown on sheet numbers 14, 15, 16, 18 and 19 of the works plans;
Work No. 92 – diversions on the north side of the proposed A47 mainline dual carriageway (Work No. 1) of a potable water pipeline, an effluent pipeline and overhead electronic communications and low voltage electricity utility cables between Taverham Road and Dereham Road, Easton, crossed by the proposed A47 mainline dual carriageway (Work No. 1), Norwich Road junction northern dumbbell roundabout (Work No. 44) and connecting slip roads and side roads, shown on sheet numbers 14 and 15 of the works plans;
Work No. 93 – alterations to the overhead 132kV electricity line with associated temporary work areas between the pylons with temporary access routes to Taverham Road and Church Road, Easton, shown on sheet numbers 15, 19 and 20 of the works plans;
Work No. 94 – installation of the onshore connection works west of Easton consented as part of the Hornsea Three Offshore Wind Farm Order 2020, comprising up to six cable circuits and associated electrical circuit ducts under Works Nos. 1, 50 and 51, and associated link boxes, joint bays, cable ducts, cable protection, joint protection, manholes, marker posts, underground cable marker, tiles and tape, and lighting and other works associated with cable laying, haul roads, vehicular accesses and construction compounds or if horizontal direction drilling is to be used, horizontal direction drilling compounds shown on sheet numbers 15 and 19 of the works plans;
Work No. 95 – removal of existing 11kV overhead electricity utility cables and installation of new ground based sub-station beside Dereham Road with low voltage connection to existing network in highway boundary, shown on sheet numbers 15 and 16 of the works plans;
Work No. 96 – environmental mitigation, including watercourse improvements and creation of ponds and wetlands between the River Tud and proposed A47 mainline dual carriageway (Work No. 1), shown on sheet number 6 of the works plans;
Work No. 97 – River Tud crossing ecological and environmental mitigation, including earthworks, watercourse alterations and creation of ponds and wetlands between the River Tud, existing A47, the proposed A47 mainline dual carriageway (Work No. 1) and the drainage basin east of Hall Farm underpass (Work No. 31), shown on sheet numbers 11 and 12 of the works plans;
Work No. 98 – new carriageway 50m in length and associated embankments, approaches and drainage to provide the option for Norwich Western Link road to connect to the proposed A47 Wood Lane Junction northern dumbbell roundabout (Work No. 20), shown on sheet number 10 of the works plans;
Work No. 99 – temporary haul route from the new field access carriageway connecting to the realigned Taverham Road (Work No. 51) to land parcels between the River Tud, Taverham Road, the A47 mainline dual carriageway (Work No. 1) and Church Lane, north of Easton, to replace access for large vehicles following severance of direct A47 access from Church Lane, shown on sheet numbers 14 and 15 of the works plans;
And for the purposes of or in connection with the construction of any of those works mentioned above, further development within the Order limits which does not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement consisting of:
- (a) alteration to the layout of any street permanently or temporarily, including as part of de-trunking or stopping up orders, including but not limited to increasing or reducing the width of the carriageway of the street by reducing or increasing the width of any kerb, footpath, footway, cycle track or verge within the street; altering the level of any such kerb, footpath, footway, cycle track or verge; installing low noise surfacing; and landscaping sections of abandoned sections;
- (b) works required for the strengthening, improvement, maintenance or reconstruction of any street;
- (c) ramps, means of access, non-motorised links, footpaths, cycle tracks and crossing facilities;
- (d) embankments, viaducts, aprons, abutments, shafts, foundations, retaining walls, barriers, pumping stations, parapets, drainage, outfalls, ditches, wing walls, highway lighting, fencing and culverts;
- (e) street works, including breaking up or opening up a street, or any sewer, drain or tunnel under it; tunnelling or boring under a street;
- (f) works to place, alter, remove or maintain street furniture or apparatus in a street, or apparatus in other land, including mains, sewers, drains, soakaways, pipes, cables, ducts, traffic signals and lights;
- (g) works to alter the course of or otherwise interfere with a watercourse;
- (h) landscaping, noise bunds and barriers, works associated with the provision of ecological mitigation and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;
- (i) works for the benefit or protection of land affected by the authorised development;
- (j) site preparation works, site clearance (including fencing, vegetation removal, demolition of existing structures and the creation of alternative footpaths); earthworks (including soil stripping and storage, site levelling); remediation of contamination;
- (k) the felling of trees;
- (l) construction compounds and working sites, storage areas, temporary vehicle parking, construction fencing, perimeter enclosure, security fencing, construction-related buildings, temporary worker accommodation facilities, welfare facilities, construction lighting, haulage roads and other buildings, machinery, apparatus, works and conveniences;
- (m) the provision of other works including pavement works, kerbing and paved areas works, signing, signals, gantries, road markings works, traffic management measures including temporary roads and such other works as are associated with the construction of the authorised development; and
- (n) such other works, working sites, storage areas and works of demolition, as may be necessary or expedient for the purposes of, or for purposes ancillary to, the construction of the authorised development.
SCHEDULE 2 — REQUIREMENTS
PART 1 — REQUIREMENTS
Interpretation
1
In this Schedule—
- “completion or completed” means the relevant parts of the authorised development are completed and fully open to traffic;
- “contaminated land” has the same meaning as that term is given in section 78A of the Environmental Protection Act 1990[^f00087];
- “DMRB” means the Design Manual for Roads and Bridges, which accommodates all current standards, advice and other documents relating to the design, assessment and operation of trunk roads and motorways, or any equivalent replacement to the DMRB published;
- “drainage strategy” means the strategy in Appendix 13.2 of the environmental statement;
- “ecological works” means Work Nos. 56 and 97;
- “EMP (Second Iteration)” means the second iteration of the environmental management plan produced in accordance with the DMRB, which is to be a refined version of the EMP (First Iteration) including more detailed versions of the outline plans contained or listed within the EMP (First Iteration) or any other plans as required;
- “EMP (Third Iteration)” means the third iteration of the environmental management plan produced in accordance with the DMRB, which is a refined version of the EMP (Second Iteration) and which relates to the operational and maintenance phase of the authorised development;
- “European protected species” has the same meaning as in regulations 42 (European protected species of animals) and 46 (European protected species of plants) of the Conservation of Habitats and Species Regulations 2017[^f00088];
- “the environmental masterplan” means the document certified as the masterplan under article 50 (certification of documents, etc.);
- “lead local flood authority” has the same meaning as in the Flood and Water Management Act 2010;
- “IDB” means the Norfolk Rivers Drainage Board;
- “the Manual of Contract Documents for Highway Works” means the document of that name published electronically by or on behalf of the strategic highway authority for England or any equivalent replacement published for that document;
- “nationally protected species” means any species protected under the Wildlife and Countryside Act 1981[^f00089]; and
- “REAC” means the Register of Environmental Actions and Commitments forming table 3.1 of the EMP (First Iteration).
Time limits
2
The authorised development must commence no later than the expiration of 5 years beginning with the date that this Order comes into force.
Detailed design
3
- (1) The authorised development must be designed in detail and carried out so that it is compatible with the preliminary scheme design shown on the works plans and engineering drawings and sections unless otherwise agreed in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority on matters related to its functions, provided that the Secretary of State is satisfied that any amendments to the engineering drawings and sections showing departures from the preliminary scheme design would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
- (2) Where amended details are approved by the Secretary of State under sub-paragraph (1), those details are deemed to be substituted for the corresponding engineering drawings and sections and the undertaker must make those amended details available in electronic form for inspection by members of the public.
Environmental Management Plan
4
- (1) No part of the authorised development, except for the ecological works, is to commence until an EMP (Second Iteration) for that part, substantially in accordance with the EMP (First Iteration) has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority, local highway authority, lead local flood authority, the Environment Agency and Natural England to the extent that the content of the EMP (Second Iteration) relates to matters relevant to their functions.
- (2) The EMP (Second Iteration) for a part must be written in accordance with ISO14001 and so far as is relevant to that part of the authorised development, must reflect the mitigation measures required by the REAC and set out in the environmental statement and must include as many of the following plans and strategies as are applicable to the part of the authorised development to which it relates—
- (a) Site waste management plan;
- (b) Materials management plan;
- (c) Soil handling management plan;
- (d) Construction noise and dust management plan;
- (e) Construction communication strategy;
- (f) Landscape and ecology management plan;
- (g) Biosecurity management plan;
- (h) Water monitoring and management plan;
- (i) Detailed heritage Written Scheme of Investigation;
- (j) Temporary surface water drainage strategy;
- (k) INNS management plan; and
- (l) Operational UXO emergency plan.
- (3) The relevant part of the authorised development must be constructed in accordance with the approved EMP (Second Iteration).
- (4) On completion of construction of each part of the authorised development the EMP (Third Iteration) relating to that part must be submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority and the relevant local highway authority to the extent that the content of the EMP (Third Iteration) relates to matters relevant to their functions.
- (5) The relevant part of the authorised development must be operated and maintained in accordance with the EMP (Third Iteration).
Landscaping
5
- (1) The authorised development must be landscaped in accordance with a landscaping scheme which sets out details of all proposed hard and soft landscaping works and which has been submitted to and approved in writing by the Secretary of State, following consultation with—
- (a) the relevant planning authority; and
- (b) Natural England.
- (2) The landscaping scheme must reflect the mitigation measures set out in the REAC and must be based on the environmental masterplan.
- (3) The landscaping scheme prepared under sub-paragraph (1) must include details of—
- (a) location, number, species mix, size and planting density of any proposed planting;
- (b) cultivation, importing of materials and other operations to ensure plant establishment;
- (c) existing trees to be retained, with measures for their protection during the construction period;
- (d) proposed finished ground levels;
- (e) implementation timetables for all landscaping works; and
- (f) measures for the replacement, in the first available planting season, of any tree or shrub planted as part of the landscaping scheme that, within a period of 5 years after the completion of the part of the authorised development to which the relevant landscaping scheme relates, dies, becomes seriously diseased or is seriously damaged.
- (4) All landscaping works must be carried out to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other more suitable recognised codes of good practice, provided these meet or exceed the appropriate British Standards.
Contaminated land and groundwater
6
- (1) In the event that contaminated land, including groundwater, is found at any time when carrying out the authorised development which was not previously identified in the environmental statement, it must be reported as soon as reasonably practicable to the Secretary of State, the relevant planning authority and the Environment Agency, and the undertaker must complete a risk assessment of the contamination in consultation with the relevant planning authority and the Environment Agency.
- (2) Where the risk assessment prepared in accordance with sub-paragraph (1) determines that remediation of the contaminated land is necessary, a written scheme and programme for the remedial measures to be taken to render the land fit for its intended purpose and to prevent any impacts on controlled waters must be submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority on matters related to its function and the Environment Agency.
- (3) Remediation must be carried out in accordance with the approved scheme.
Protected species
7
- (1) No part of the authorised development is to commence until, for that part, final preconstruction survey work has been carried out to establish whether European or nationally protected species are present on any of the land affected or likely to be affected by that part of the relevant works, or in any of the trees and shrubs to be lopped or felled as part of the relevant works.
- (2) Following pre-construction survey work or at any time when carrying out the authorised development, where—
- (a) a protected species is shown to be present, or where there is a reasonable likelihood of it being present;
- (b) application of the relevant assessment methods used in the environmental statement show that a significant effect is likely to occur which was not previously identified in the environmental statement; and
- (c) that effect is not addressed by any prior approved scheme of protection and mitigation established in accordance with this paragraph,
the relevant parts of the relevant works must cease until a scheme of protection and mitigation measures has been submitted to and approved in writing by the Secretary of State.
- (3) The undertaker must consult with Natural England on the scheme referred to in subparagraph (2) prior to submission to the Secretary of State for approval, except where a suitably qualified and experienced ecologist, holding where relevant and appropriate a licence relating to the species in question, determines that the relevant works do not require a protected species licence.
- (4) The relevant works under sub-paragraph (2) must be carried out in accordance with the approved scheme, unless otherwise agreed by the Secretary of State after consultation by the undertaker with Natural England, and under any necessary licences.
Surface water drainage
8
- (1) No part of the authorised development, except for the ecological works, is to commence until, for that part, written details of the surface water drainage system, reflecting the drainage strategy and the mitigation measures set out in the REAC including means of pollution control, have been submitted and approved in writing by the Secretary of State following consultation by the undertaker with the lead local flood authority, IDB and the Environment Agency on matters related to their functions.
- (2) The surface water drainage system must be constructed in accordance with the approved details, unless otherwise agreed in writing by the Secretary of State following consultation by the undertaker with the lead local flood authority, IDB and the Environment Agency on matters related to its function, provided that the Secretary of State is satisfied that any amendments to the approved details would not give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.
Archaeological remains
9
- (1) No part of the authorised development, is to commence until, for that part, a written scheme of investigation of areas of archaeological interest, reflecting the relevant mitigation measures set out in the REAC, has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant planning authority, Norfolk County Council Historic Strategy and Advice Team and Historic England on matters related to their functions.
- (2) The authorised development must be carried out in accordance with the scheme referred to in sub-paragraph (1).
Traffic management
10
- (1) No part of the authorised development comprising the construction, alteration or improvement of Work No. 1 is to commence until a traffic management plan substantially in accordance with the outline traffic management plan, for that part has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant highway authority on matters related to its function.
- (2) The authorised development must be implemented in accordance with the traffic management plan referred to in sub-paragraph (1).
Fencing
11
Any permanent and temporary fencing and other means of enclosure for the authorised development must be constructed and installed in accordance with Manual of Contract Documents for Highway Works maintained by or on behalf of the undertaker except where any departures from that manual are agreed in writing by the Secretary of State in connection with the authorised development.
Ecological works
12
- (1) No part of the ecological works is to commence until the siting, design, method of construction and timetable for delivery of the new ponds and ditches to be included within Work Nos. 56 and 97 have been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority and Natural England.
- (2) The construction of the ponds and ditches forming part of the ecological works must thereafter be carried out in accordance with the approved details.
Ørsted works
13
- (1) No part of Work No. 94 is to commence without the written approval of Ørsted and all works must be carried out in accordance with requirements 10, 17, 18 and 22 in Schedule 1 Part 3 of the Hornsea Three Order.
Approvals and amendments to approved details
14
With respect to any requirement which requires the authorised development to be carried out in accordance with the details or schemes approved under this Schedule, the approved details or schemes are taken to include any amendments that may subsequently be approved in writing by the Secretary of State.
PART 2 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Applications made under requirements
15
- (1) Where an application has been made to the Secretary of State for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement) included in this Order, the Secretary of State must give notice to the undertaker of the decision on the application within a period of 8 weeks beginning with—
- (a) the day immediately following that on which the application is received by the Secretary of State;
- (b) the day immediately following that on which further information has been supplied by the undertaker under paragraph 15 (further information); or
- (c) such longer period as may be agreed between the parties.
- (2) Subject to sub-paragraph (3), in the event that the Secretary of State does not determine an application within the period set out in sub-paragraph (1), the Secretary of State is taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) Where—
- (a) an application has been made to the Secretary of State for any consent, agreement or approval required by a requirement included in this Order;
- (b) the Secretary of State does not determine such application within the period set out in sub-paragraph (1); and
- (c) the application is accompanied by a report from a body required to be consulted by the undertaker under the requirement that considers it likely that the subject matter of the application would give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement,
the application is taken to have been refused by the Secretary of State at the end of that period.
Further information
16
- (1) In relation to any part of an application made under this Schedule, the Secretary of State has the right to request such further information from the undertaker as is necessary to enable the Secretary of State to consider the application.
- (2) In the event that the Secretary of State considers such further information to be necessary the Secretary of State must, within 21 business days of receipt of the application, notify the undertaker in writing specifying the further information required and (if applicable) to which part of the application it relates.
- (3) In the event that the Secretary of State does not give such notification within that 21 day business period the Secretary of State is deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
- (4) Where further information is requested under this paragraph in relation to part only of an application, that part is treated as separate from the remainder of the application for the purposes of calculating the time periods referred to in paragraph 14 (applications made under requirements) and in this paragraph.
- (5) In this paragraph, “business day” means a day other than Saturday or Sunday, which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 1971[^f00090].
Register of requirements
17
- (1) The undertaker must, as soon as practicable following the making of this Order, establish and maintain in an electronic form suitable for inspection by members of the public a register of those requirements contained in Part 1 of this Schedule that provide for further approvals to be given by the Secretary of State.
- (2) The register must set out in relation to each such requirement the status of the requirement, in terms of whether any approval to be given by the Secretary of State has been applied for or given, providing an electronic link to any document containing any approved details.
- (3) The register must be maintained by the undertaker for a period of 3 years following completion of the authorised development.
Anticipatory steps towards compliance with any requirement
18
If before the coming into force of this Order the undertaker or any other person has taken any steps that were intended to be steps towards compliance with any provision of Part 1 of this Schedule, those steps may be taken into account for the purpose of determining compliance with that provision if they would have been valid steps for that purpose had they been taken after this Order came into force.
Details of consultation
19
In relation to any provision of this Schedule requiring details to be submitted to the Secretary of State for approval following consultation by the undertaker with another party, the undertaker must provide such other party with not less than 15 business days for any response to the consultation and thereafter the details submitted to the Secretary of State for approval must be accompanied by a summary report setting out the consultation undertaken by the undertaker to inform the details submitted and the undertaker’s response to that consultation.
SCHEDULE 3 — CLASSIFICATIONS OF ROADS, ETC.
PART 1 — TRUNK ROADS
| (1) Area | (2) Length of road |
|---|---|
| The classification of roads plans – sheets 1-2, 4-9 and 11-16 | The classification of roads plans – sheets 1-2, 4-9 and 11-16 |
| North Tuddenham Parish Hockering Parish East Tuddenham Parish Honingham Parish Easton Parish | A 9.169 kilometre length of new highway to be classified as part of the A47 Trunk Road. On the eastbound carriageway from point A 368 metres east of the centreline of the Fox Lane overbridge in an easterly direction to point B (sheet 16) for a distance of 9.169 kilometres. On the westbound carriageway from point C 368 metres east of the centreline of the Fox Lane overbridge in an easterly direction to point D (sheet 16) for a distance of 9.169 kilometres. |
| The classification of roads plans – sheet 7 | The classification of roads plans – sheet 7 |
| East Tuddenham Parish Honingham Parish | New eastbound diverge slip road A 794 metre length of carriageway to be classified as part of the A47 Trunk Road from point U 132 metres east of the centreline of the Church Lane junction in a north-easterly direction to point V (sheet 10). |
| The classification of roads plans – sheet 8 | The classification of roads plans – sheet 8 |
| East Tuddenham Parish | New westbound merge slip road A 644 metre length of carriage way to be classified as part of the A47 Trunk Road from point W 285 metres east of the centreline of the Church Lane junction in a south-easterly direction to point X (sheet 9) a distance of 644 metres. |
| The classification of roads plans – sheet 9 | The classification of roads plans – sheet 9 |
| East Tuddenham Parish Honingham Parish | New westbound diverge slip road A 664 metre length of carriageway to be classified as part of the A47 Trunk Road from point AI 693 metres north west of the River Tud in an easterly direction to point AJ (sheet 11). |
| The classification of roads plans – sheet 10 | The classification of roads plans – sheet 10 |
| Honingham Parish | New eastbound merge slip road A 609 metre length of carriageway to be classified as part of the A47 Trunk Road from point AG 185 metres north of the junction of the B1535 with the existing A47 in an easterly direction to point AH (sheet 11). |
| The classification of roads plans – sheet 13 | The classification of roads plans – sheet 13 |
| Honingham Parish | New eastbound diverge slip road A 707 metre length of new carriageway to be classified as part of the A47 mainline dual carriageway from point AS 233 metres east of the centrepoint of the roundabout with Norwich Road in a south-easterly direction to point AT (sheet 14). |
| Honingham Parish | New westbound merge slip road A 763 metre length of carriageway to be classified as part of the A47 Trunk Road from point AQ 223 metres east of the centrepoint of the roundabout with Norwich Road in a south-easterly direction to point AR (sheet 14). |
| The classification of roads plans – sheet 15 | The classification of roads plans – sheet 15 |
| Honingham Parish Easton Parish | New eastbound merge slip road A 716 metre length of carriageway to be classified as part of the A47 Trunk Road from point BB 403m west of the centrepoint of the A47 roundabout with Dereham Road in an westerly direction to point BA (sheet 14). |
| Honingham Parish Easton Parish | New westbound diverge slip road A 620 metre length of carriageway to be classified as part of the A47 Trunk Road from point BD 518m west of the centrepoint of the A47 roundabout with Dereham Road in an westerly direction to point BC (sheet 14). |
PART 2 — CLASSIFIED B ROADS
| (1) Area | (2) Length of road |
|---|---|
| The classification of roads plans – sheet 9 | The classification of roads plans – sheet 9 |
| East Tuddenham Parish | New roundabout to be classified as B Road with reference AB, 980 metres east of the centreline of the existing A47/Church Lane junction with the existing A47. |
| The classification of roads plans – sheet 10 | The classification of roads plans – sheet 10 |
| East Tuddenham Parish | New roundabout to be classified as B Road with reference AA, 990 metres east of the centreline of the existing A47/Church Lane junction. |
| East Tuddenham Parish Honingham Parish | New roundabout connector road A 111 metre length of carriageway to be classified as B Road from point AC, 953 metres east of the centreline of the existing A47/Church Lane junction, in a south-easterly direction to point AD (sheet 9). |
| East Tuddenham Parish | Link to Wood Lane A 305 metre length of new carriageway to be classed as B Road from point S, 145 metres west of the centrepoint of the proposed Wood Lane junction northern roundabout, in a northern direction to point T. |
| East Tuddenham Parish | Link Road to existing A47 A 95 metre length of new carriageway to be classed as B Road from point R1 at the junction with the proposed link to Wood Lane, in an easterly direction to point R. |
| The classification of roads plans – sheet 14 | The classification of roads plans – sheet 14 |
| Honingham Parish | New roundabout to be classified as B Road with reference AY, the centrepoint of the roundabout is 118 metres east of the centreline of Blind Lane. |
| Honingham Parish | New roundabout to be classified as B Road with reference AZ, the centrepoint of the roundabout is 103 metres east of the centreline of Blind Lane. |
| Honingham Parish | New roundabout connector road A 144 metre length of carriageway to be classified as B Road from point AX 82 metres east of the centreline of Blind Lane in a northerly direction to point AW. |
PART 2A — CLASSIFIED C ROADS
| (1) Area | (2) Length of road |
|---|---|
| The classification of roads plans – sheet 1 | The classification of roads plans – sheet 1 |
| North Tuddenham Parish Hockering Parish | Link Road to existing A47 A 1154 metre length of new carriageway to be classed as C Road. From point G 493 metres east of the Fox Lane overbridge in an easterly direction to point H (sheet 4). |
| The classification of roads plans – sheet 2 | The classification of roads plans – sheet 2 |
| North Tuddenham Parish Hockering Parish | Link to B1147 (Lyng Road) A 168 metre length of new carriageway to be classified as C Road from point E at the north side of the existing pond between the B1147 and the existing A47, in a southerly direction to point F on the B1147. |
| The classification of roads plans – sheet 4 | The classification of roads plans – sheet 4 |
| East Tuddenham Parish Hockering Parish | Existing A47 A 2090 metre length of de-trunked carriageway to be classed as C Road from point H 140 metres north west of the Matishall Lane Link Road junction in a south easterly direction to point Q (sheet 7). |
| Hockering Parish | Proposed Mattishall Lane Link Road A 471 metre length of new carriageway to be classified as C Road from point L, 160 metres north west of the centreline of the existing A47 / Mattishall Lane junction, in a south westerly direction to point K. |
| The classification of roads plans – sheet 7 | The classification of roads plans – sheet 7 |
| East Tuddenham Parish | Link Road to existing A47 A 820 metre length of new carriageway to be classed as C Road from point Q, 12.5 metres east of the centreline of the existing A47/Church Lane junction, in an easterly direction to point R1 (sheet 10). |
| The classification of roads plans – sheet 9 | The classification of roads plans – sheet 9 |
| Honingham Parish | Link to Dereham Road A 266 metre length of new carriageway to be classified as C Road from point AM, 269 metres south east of the centreline of the existing A47 / Berrys Lane junction, in a south then south easterly direction to point AN. |
| East Tuddenham Parish Honingham Parish | Link Road to existing A47 A 1680 metre length of new carriageway to be classed as C Road from point AK 38 metres south of the existing A47/Berrys Lane junction in an south easterly direction to point AL (sheet 13). |
| The classification of roads plans – sheet 13 | The classification of roads plans – sheet 13 |
| Honingham Parish | Link to Norwich Road A 1029 metre length of new carriageway to be classified as C Road from point AE, 46 metres east of the centrepoint of the Honingham roundabout in a south easterly direction to point AF (sheet 14). |
| Honingham Parish | Existing roundabout to be classified as C Road with reference BI the centrepoint of the roundabout is 375 metres west of the access to St Andrew’s Church. |
| The classification of roads plans – sheet 14 | The classification of roads plans – sheet 14 |
| Honingham Parish | Link to Taverham Road A 247 metre length of new carriageway to be classified as C Road from point AU, 29 metres south of the access to Church House Farm in a south easterly direction to point AV. |
| Honingham Parish Easton Parish | Link to Dereham Road A 1264 metre length of new carriageway to be classified as C Road from point BE, 29 metres south east of the centrepoint of the proposed Norwich Road junction southern roundabout in an easterly direction to point BF (sheet 16). |
| The classification of roads plans – sheet 17 | The classification of roads plans – sheet 17 |
| Easton Parish | Realignment of Rotten Row A 55 metre length of new carriageway to be classified as C Road from point BG, 55 metres west of the centreline of the Rotten Row / Church Lane junction to point BH. |
PART 3 — UNCLASSIFIED ROADS
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.