The Awel y Môr Offshore Wind Farm Order 2023
- (12) On application by the relevant planning authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to the Welsh Government’s ‘Development Management Manual Section 12 Annex: Award of costs’ or any circular or guidance which may from time to time replace it.
SCHEDULE 12 — Arbitration rules
Primary objective
1
- (1) The primary objective of these arbitration rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within four months from the date the arbitrator is appointed pursuant to article 44 (arbitration) of the Order.
- (2) The parties will first use their reasonable endeavours to settle a dispute amicably through negotiations undertaken in good faith by the senior management of the parties. Any dispute which is not resolved amicably by the senior management of the parties within twenty business days of the dispute arising, or such longer period as agreed in writing by the parties, will be subject to arbitration in accordance with the terms of this Schedule.
- (3) The arbitration will be deemed to have commenced when a party (the “claimant”) serves a written notice of arbitration on the other party (the “respondent”).
Time periods
2
- (1) All time periods in these arbitration rules will be measured in business days and this will exclude weekends and bank holidays.
- (2) Time periods will be calculated from the day after the arbitrator is appointed which will be either—
- (a) the date the arbitrator notifies the parties in writing of his/her acceptance of an appointment by agreement of the parties; or
- (b) the date the arbitrator is appointed by the Secretary of State.
Timetable
3
- (1) The timetable for the arbitration will be that set out in sub-paragraphs (2) to (4) below unless amended in accordance with paragraph 5(3).
- (2) Within 15 days of the arbitrator being appointed, the claimant must provide both the respondent and the arbitrator with—
- (a) a written statement of claim which describes the nature of the difference between the parties, the legal and factual issues, the claimant’s contentions as to those issues, and the remedy it is seeking; and
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports.
- (3) Within 15 days of receipt of the claimant’s statements under sub-paragraph (2) by the arbitrator and respondent, the respondent must provide the claimant and the arbitrator with—
- (a) a written statement of defence responding to the claimant’s statement of claim, its statement in respect of the nature of the difference, the legal and factual issues in the claimant’s claim, its acceptance of any element(s) of the claimant’s claim, its contentions as to those element(s) of the claimant’s claim it does not accept;
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports; and
- (c) any objections it wishes to make to the claimant’s statements, comments on the claimant’s expert report(s) (if submitted by the claimant) and explanations for the objections.
- (4) Within five days of the respondent serving its statements sub-paragraph (3), the claimant may make a statement of reply by providing both the respondent and the arbitrator with—
- (a) a written statement responding to the respondent’s submissions, including its reply in respect of the nature of the difference, the issues (both factual and legal) and its contentions in relation to the issues;
- (b) all statements of evidence and copies of documents in response to the respondent’s submissions;
- (c) any expert report in response to the respondent’s submissions;
- (d) any objections to the statements of evidence, expert reports or other documents submitted by the respondent; and
- (e) its written submissions in response to the legal and factual issues involved.
Procedure
4
- (1) The arbitrator will make an award on the substantive difference based solely on the written material submitted by the parties unless the arbitrator decides that a hearing is necessary to explain or resolve any matters.
- (2) Either party may, within two days of delivery of the last submission, request a hearing giving specific reasons why it considers a hearing is required.
- (3) Within five days of receiving the last submission, the arbitrator will notify the parties whether a hearing is to be held and the length of that hearing.
- (4) Within ten days of the arbitrator advising the parties that he will hold a hearing, the date and venue for the hearing will be fixed by agreement with the parties, save that if there is no agreement the arbitrator must direct a date and venue which he considers is fair and reasonable in all the circumstances. The date for the hearing must not be less than 35 days from the date of the arbitrator’s direction confirming the date and venue of the hearing.
- (5) A decision will be made by the arbitrator on whether there is any need for expert evidence to be submitted orally at the hearing. If oral expert evidence is required by the arbitrator, then any expert(s) attending the hearing may be asked questions by the arbitrator.
- (6) There will be no process of examination and cross-examination of experts, but the arbitrator will invite the parties to ask questions of the experts by way of clarification of any answers given by the expert(s) in response to the arbitrator’s questions. Prior to the hearing the procedure for the expert(s) will be that—
- (a) at least 20 days before a hearing, the arbitrator will provide a list of issues to be addressed by the expert(s);
- (b) if more than one expert is called, they will jointly confer and produce a joint report or reports within ten days of the issues being provided; and
- (c) the form and content of a joint report will be as directed by the arbitrator and must be provided at least five days before the hearing.
- (7) Within ten days of a hearing or a decision by the arbitrator that no hearing is to be held the parties may by way of exchange provide the arbitrator with a final submission in connection with the matters in dispute and any submissions on costs. The arbitrator will take these submissions into account in the award.
- (8) The arbitrator may make other directions or rulings as considered appropriate in order to ensure that the parties comply with the timetable and procedures to achieve an award on the substantive difference within four months of the date on which they are appointed, unless both parties otherwise agree to an extension to the date for the award.
- (9) If a party fails to comply with the timetable, procedure or any other direction then the arbitrator may continue in the absence of a party or submission or document, and may make a decision on the information before them attaching the appropriate weight to any evidence submitted beyond any timetable or in breach of any procedure and/or direction.
- (10) The arbitrator’s award must include reasons. The parties will accept that the extent to which reasons are given is to be proportionate to the issues in dispute and the time available to the arbitrator to deliver the award.
Arbitrator’s powers
5
- (1) The arbitrator has all the powers of the Arbitration Act 1996[^f00048], including the non-mandatory sections, save where modified in this Schedule.
- (2) There will be no discovery or disclosure, except that the arbitrator has the power to order the parties to produce such documents as are reasonably requested by another party no later than the statement of reply, or by the arbitrator, where the documents are manifestly relevant, specifically identified and the burden of production is not excessive. Any application and orders should be made by way of a Redfern Schedule without any hearing.
- (3) Any time limits fixed in accordance with this procedure or by the arbitrator may be varied by agreement between the parties, subject to any such variation being acceptable to and approved by the arbitrator. In the absence of agreement, the arbitrator may vary the timescales and/or procedure—
- (a) if the arbitrator is satisfied that a variation of any fixed time limit is reasonably necessary to avoid a breach of the rules of natural justice and then; and
- (b) only for such a period that is necessary to achieve fairness between the parties.
- (4) On the date the award is made, the arbitrator will notify the parties that the award is completed, signed and dated, and that it will be issued to the parties on receipt of cleared funds for the arbitrator’s fees and expenses.
Costs
6
- (1) The costs of the arbitration will include the fees and expenses of the arbitrator, the reasonable fees and expenses of any experts and the reasonable legal and other costs incurred by the parties for the arbitration.
- (2) Subject to sub-paragraph (3), the arbitrator will award recoverable costs on the general principle that each party should bear its own costs.
- (3) The arbitrator may depart from the general principle in sub-paragraph (2) and make such other costs award as it considers reasonable where a party has behaved unreasonably as defined within the National Planning Practice Guidance or such other guidance as may replace it.
Confidentiality
7
- (1) Subject to sub-paragraphs (2) and (3), any arbitration hearing and documentation shall be open and accessible by the public.
- (2) The arbitrator may direct that the whole or part of a hearing is to be private or any documentation to be confidential where it is necessary in order to protect commercially sensitive information.
- (3) Nothing in this paragraph prevents any disclosure of a document by a party pursuant to an order of a court in England and Wales or where disclosure is required under any enactment.
SCHEDULE 13 — Documents to be certified
The following documents in Table 5 are the list referred to in article 40—
| Document Number | Examination Library Reference | Name | Version | Date |
|---|---|---|---|---|
| 3a.11 | REP3a-011 | Land plan (Offshore) | B | 16 December 2022 |
| 2.3 | REP6-028 | Land plan (Onshore) | E | 20 February 2023 |
| 2.5 | REP6-029 | Works Plan | D | 20 February 2023 |
| 4.3 | REP8-025 | Book of Reference | I | 15 March 2023 |
| Environmental Statement | Environmental Statement | Environmental Statement | Environmental Statement | Environmental Statement |
| 6.7.1. | APP-293 | Non Technical Summary | B | 20 April 2022 |
| 6.7.2. | APP-294 | Non-Technical Summary (Welsh Language Version) | B | 20 April 2022 |
| 6.8.1. | APP-295 | Scoping Opinion | A | 20 April 2022 |
| Volume 1 – Introductory Chapters | Volume 1 – Introductory Chapters | Volume 1 – Introductory Chapters | Volume 1 – Introductory Chapters | Volume 1 – Introductory Chapters |
| 6.1.1. | AS-024 | Volume 1, Chapter 1: Introduction | C | 31 May 2022 (cover incorrectly states April 2022) |
| 6.1.2. | APP-040 | Volume 1, Chapter 2: Policy and Legislation | B | 20 April 2022 |
| 6.1.3. | REP8-056 | Volume 1, Chapter 3: Environmental Impact Assessment Methodology | C | 15 March 2023 |
| 6.1.4. | APP-044 | Volume 1, Chapter 4: Site Selection and Alternatives | B | 20 April 2022 |
| 6.1.3.1. | APP-042 | Volume 1, Annex 3.1: Cumulative Effects Assessment | B | 20 April 2022 |
| 6.1.3.2. | APP-043 | Volume 1, Annex 3.2: Transboundary Screening | B | 20 April 2022 |
| 6.1.4.1. | APP-045 | Volume 1, Annex 4.1: SSA Identification of Area of Search Report | B | 20 April 2022 |
| 6.1.4.2. | APP-046 | Volume 1, Annex 4.2: SSA Shortlisting Outcomes Report | B | 20 April 2022 |
| Volume 2 – Offshore Chapters | Volume 2 – Offshore Chapters | Volume 2 – Offshore Chapters | Volume 2 – Offshore Chapters | Volume 2 – Offshore Chapters |
| 6.2.1. | APP-047 | Volume 2, Chapter 1: Offshore Project Description | B | 20 April 2022 |
| 6.2.2. | REP8-084 | Volume 2, Chapter 2: Marine Geology, Oceanography and Physical Processes | C | 15 March 2023 |
| 6.2.3. | APP-049 | Volume 2, Chapter 3: Marine Water and Sediment Quality | B | 20 April 2022 |
| 6.2.4. | REP8-085 | Volume 2, Chapter 4: Offshore Ornithology | C | 15 March 2023 |
| 6.2.5. | APP-051 | Volume 2, Chapter 5: Benthic Subtidal and Intertidal Ecology | B | 20 April 2022 |
| 6.2.6. | REP8-057 | Volume 2, Chapter 6: Fish and Shellfish Ecology | C | 15 March 2023 |
| 6.2.7. | REP8-081 | Volume 2, Chapter 7: Marine Mammals | D | 15 March 2023 |
| 6.2.8. | REP8-086 | Volume 2, Chapter 8: Commercial Fisheries | C | 15 March 2023 |
| 6.2.9. | APP-055 | Volume 2, Chapter 9: Shipping and Navigation | B | 20 April 2022 |
| 6.2.10. | REP8-082 | Volume 2, Chapter 10: Seascape, Landscape and Visual Impact Assessment | D | 15 March 2023 |
| 6.2.11. | REP8-058 | Volume 2, Chapter 11: Offshore Archaeology and Cultural Heritage | C | 15 March 2023 |
| 6.2.12. | APP-058 | Volume 2, Chapter 12: Other Marine Users and Activities | B | 20 April 2022 |
| 6.2.13. | APP-059 | Volume 2, Chapter 13: Military and Civil Aviation | B | 20 April 2022 |
| 6.2.14. | REP8-059 | Volume 2, Chapter 14: Inter-relationships | C | 15 March 2023 |
| 6.2.15. | AS-028 | Volume 2, Chapter 15: Offshore Conclusions | C (Document states Rev B, but is different to Rev B as submitted as APP-061) | 31 May 2022 (Document states March 2022 but is different to Rev B APP-061) |
| Volume 3 – Onshore Chapters | Volume 3 – Onshore Chapters | Volume 3 – Onshore Chapters | Volume 3 – Onshore Chapters | Volume 3 – Onshore Chapters |
| 6.3.1. | REP8-060 | Volume 3, Chapter 1: Onshore Project Description | C | 15 March 2023 |
| 6.3.2. | REP8-087 | Volume 3, Chapter 2: Landscape and Visual Impact Assessment | D | 15 March 2023 |
| 6.3.3. | REP8-088 | Volume 3, Chapter 3: Socio-Economics | D | 15 March 2023 |
| 6.3.4. | APP-065 | Volume 3, Chapter 4: Tourism and Recreation | B | 20 April 2022 |
| 6.3.5. | REP8-061 | Volume 3, Chapter 5: Onshore Biodiversity and Nature Conservation | C | 15 March 2023 |
| 6.3.6. | REP8-062 Document 8.47 of the Applicant’s Deadline 8 submission | Volume 3, Chapter 6: Ground Conditions and Land Use | C | 15 March 2023 |
| 6.3.7. | REP8-063 | Volume 3, Chapter 7: Hydrology, Hydrogeology and Flood Risk | C | 15 March 2023 |
| 6.3.8. | REP8-064 | Volume 3, Chapter 8: Onshore Archaeology and Cultural Heritage | C | 15 March 2023 |
| 6.3.9. | APP-070 | Volume 3, Chapter 9: Traffic and Transport | B | 20 April 2022 |
| 6.3.10. | REP8-065 Document 8.50 of the Applicant’s Deadline 8 submission | Volume 3, Chapter 10: Noise and Vibration | C | 15 March 2023 |
| 6.3.11. | AS-030 | Volume 3, Chapter 11: Air Quality | C | 31 May 2022 (cover incorrectly states April 2022) |
| 6.3.12. | APP-073 | Volume 3, Chapter 12: Public Health | B | 20 April 2022 |
| 6.3.13. | REP8-066 | Volume 3, Chapter 13: Onshore Conclusions | C | 15 March 2023 |
| Volume 4 – Offshore Annexes | Volume 4 – Offshore Annexes | Volume 4 – Offshore Annexes | Volume 4 – Offshore Annexes | Volume 4 – Offshore Annexes |
| 6.4.2.1. | APP-075 | Volume 4, Annex 2.1: Physical Processes Baseline Technical Report | B | 20 April 2022 |
| 6.4.2.2. | APP-076 | Volume 4, Annex 2.2: Physical Processes Model Calibration | B | 20 April 2022 |
| 6.4.2.3. | APP-077 | Volume 4, Annex 2.3: Physical Processes Modelling Results | B | 20 April 2022 |
| 6.4.2.4.1 | APP-078 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 1) | A | 20 April 2022 |
| 6.4.2.4.2 | APP-079 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 2) | A | 20 April 2022 |
| 6.4.2.4.3 | APP-080 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 3) | A | 20 April 2022 |
| 6.4.2.4.4 | APP-081 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 4) | A | 20 April 2022 |
| 6.4.2.4.5 | APP-082 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 5) | A | 20 April 2022 |
| 6.4.2.4.6 | APP-083 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 6) | A | 20 April 2022 |
| 6.4.2.4.7 | APP-084 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 7) | A | 20 April 2022 |
| 6.4.2.4.8 | APP-085 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 8) | A | 20 April 2022 |
| 6.4.2.4.9 | APP-086 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 9) | A | 20 April 2022 |
| 6.4.2.4.10 | APP-087 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 10) | A | 20 April 2022 |
| 6.4.2.4.11 | APP-088 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 11) | A | 20 April 2022 |
| 6.4.2.4.12 | APP-089 | Volume 4, Annex 2.4: Seafloor and Shallow Geological Results (Array) (Part 12) | A | 20 April 2022 |
| 6.4.2.5.1 | APP-090 | Volume 4, Annex 2.5: Seafloor and Shallow Geological Results (Offshore ECC) (Part 1) | A | 20 April 2022 |
| 6.4.2.5.2 | APP-091 | Volume 4, Annex 2.5: Seafloor and Shallow Geological Results (Offshore ECC) (Part 2) | A | 20 April 2022 |
| 6.4.2.5.3 | APP-092 | Volume 4, Annex 2.5: Seafloor and Shallow Geological Results (Offshore ECC) (Part 3) | A | 20 April 2022 |
| 6.4.2.5.4 | APP-093 | Volume 4, Annex 2.5: Seafloor and Shallow Geological Results (Offshore ECC) (Part 4) | A | 20 April 2022 |
| 6.4.3.1. | REP8-067 | Volume 4, Annex 3.1: Water Framework Directive Compliance Assessment | C | 15 March 2023 |
| 6.4.4.1. | APP-095 | Volume 4, Annex 4.1: Offshore Ornithology Baseline Characterisation Report | B | 20 April 2022 |
| 6.4.4.2. | APP-096 | Volume 4, Annex 4.2: Offshore Ornithology Displacement | B | 20 April 2022 |
| 6.4.4.3. | APP-097 | Volume 4, Annex 4.3: Offshore Ornithology Collision Risk Modelling | B | 20 April 2022 |
| 6.4.4.4. | APP-098 | Volume 4, Annex 4.4: Migratory Collision Risk Modelling | B | 20 April 2022 |
| 6.4.4.5. | APP-099 | Volume 4, Annex 4.5: Offshore Ornithology Scoping and Consultation Responses | A | 20 April 2022 |
| 6.4.4.6. | APP-100 | Volume 4, Annex 4.6: Offshore Ornithology Population Viability Analysis | B | 20 April 2022 |
| 6.4.5.1. | APP-101 | Volume 4, Annex 5.1: Benthic Ecology Subtidal Characterisation (Array) | A | 20 April 2022 |
| 6.4.5.2. | APP-102 | Volume 4, Annex 5.2: Benthic Ecology Subtidal Characterisation (Offshore ECC) | A | 20 April 2022 |
| 6.4.5.3. | APP-103 | Volume 4, Annex 5.3: Benthic Ecology Intertidal Characterisation | A | 20 April 2022 |
| 6.4.6.1. | APP-104 | Volume 4, Annex 6.1: Fish and Shellfish Ecology Technical Baseline | B | 20 April 2022 |
| 6.4.6.2. | APP-105 | Volume 4, Annex 6.2: Underwater Noise Technical Report | B | 20 April 2022 |
| 6.4.7.1. | REP8-068 | Volume 4, Annex 7.1: Marine Mammal Baseline Characterisation | C | 15 March 2023 |
| 6.4.7.2. | REP8-069 | Volume 4, Annex 7.2: Draft Outline Marine Mammal Mitigation Protocol | C | 15 March 2023 |
| 6.4.7.3. | APP-108 | Volume 4, Annex 7.3: Marine Mammal Quantitative Assessment Assumptions | B | 20 April 2022 |
| 6.4.8.1. | APP-109 | Volume 4, Annex 8.1: Commercial Fisheries Baseline Report | B | 20 April 2022 |
| 6.4.8.2. | APP-110 | Volume 4, Annex 8.2: Commercial Fisheries Consultation Record | B | 20 April 2022 |
| 6.4.9.1. | APP-111 | Volume 4, Annex 9.1: Navigation Risk Assessment | B | 20 April 2022 |
| 6.4.10.1. | APP-112 | Volume 4, Annex 10.1: SLVIA Methodology | A | 20 April 2022 |
| 6.4.10.2. | APP-113 | Volume 4, Annex 10.2: SLVIA Consultation | A | 20 April 2022 |
| 6.4.10.3. | APP-114 | Volume 4, Annex 10.3: SLVIA Simple Assessment | B | 20 April 2022 |
| 6.4.10.4. | APP-115 | Volume 4, Annex 10.4: SLVIA Visibility Data | B | 20 April 2022 |
| 6.4.10.5. | APP-116 | Volume 4, Annex 10.7: SLVIA Legislation and Policy | A | 20 April 2022 |
| 6.4.11.1. | APP-117 | Volume 4: Annex 11.1: Offshore Archaeology Desk Based Assessment | B | 20 April 2022 |
| 6.4.12.1. | APP-118 | Volume 4, Annex 12.1: Charter Angling Baseline Report | B | 20 April 2022 |
| 6.4.12.1.1 | APP-119 | Volume 4, Annex 12.1: Charter Angling Baseline Report Annex B (Confidential) | N/A | 20 April 2022 |
| Volume 5 – Onshore Annexes | Volume 5 – Onshore Annexes | Volume 5 – Onshore Annexes | Volume 5 – Onshore Annexes | Volume 5 – Onshore Annexes |
| 6.5.1.1. | APP-121 | Volume 5, Annex 1.1: Crossing Schedule | B | 20 April 2022 |
| 6.5.2.1. | APP-122 | Volume 5, Annex 2.1: LANDMAP Assessment | B | 20 April 2022 |
| 6.5.4.1. | APP-123 | Volume 5, Annex 4.1: Baseline information relating to recreation resources | B | 20 April 2022 |
| 6.5.4.2. | APP-124 | Volume 5, Annex 4.2: Seaside Tourism Economics Employment Evidence | A | 20 April 2022 |
| 6.5.5.1. | REP8-070 | Volume 5, Annex 5.1: Preliminary Ecological Appraisal Report; | C | 15 March 2023 |
| 6.5.5.2. | APP-125 | Volume 5, Annex 5.2: Habitat and Hedgerow Survey Report. | A | 20 April 2022 |
| 6.5.5.3. | APP-126 | Volume 5, Annex 5.3: Wintering Bird Survey Report. | A | 20 April 2022 |
| 6.5.5.4. | APP-127 | Volume 5, Annex 5.4: Reptile Survey Report. | A | 20 April 2022 |
| 6.5.5.5. | APP-128 | Volume 5, Annex 5.5: Otter and Watervole Survey Report. | A | 20 April 2022 |
| 6.5.5.6. | APP-129 | Volume 5, Annex 5.6: Great Crested Newt Survey Report. | A | 20 April 2022 |
| 6.5.5.7. | REP8-071 | Volume 5, Annex 5.7: Dormouse Survey Report. | B | 15 March 2023 |
| Environmental Statement Volume 5, Annex 5.8. | AS-031 | Volume 5, Annex 5.8: Breeding Bird Survey Report. | B | 31 May 2022 |
| 6.5.5.8.1 | AS-032 | Volume 5, Annex 5.8: Appendix 4 CONFIDENTIAL Barn Owl Survey Results | A | 31 May 2022 |
| 6.5.5.9. | APP-132, APP-133 | Volume 5, Annex 5.9: Badger Survey Report (Confidential and Public). | N/A | 20 April 2022 |
| 6.5.5.10. | APP-134 | Volume 5, Annex 5.10: Bat Survey Report. | N/A | 20 April 2022 |
| 6.5.5.11. | APP-135 | Volume 5, Annex 5.11: Noise Modelling for Important Ornithological Features (Onshore) | A | 20 April 2022 |
| 6.5.5.12. | APP-136 | Volume 5, Annex 5.12: Consultation Feedback | A | 20 April 2022 |
| 1.41 | REP1-042 | Volume 5, Annex 7.1: Onshore ECC Flood Consequence Assessment; | C | 24 October 2022 |
| 1.43 | REP1-044 | Volume 5, Annex 7.2: Onshore Substation Flood Consequence Assessment; | C | 24 October 2022 |
| 1.43 Appendix A | REP1-045 | Volume 5, Annex 7.2: Onshore Substation Flood Consequence Assessment - Appendix A Outline Drainage Strategy | C | 24 October 2022 |
| 6.5.7.3. | APP-139 | Volume 5, Annex 7.3: Landfall HDD crossing Groundwater Risk Assessment; | A | 20 April 2022 |
| 6.5.7.4. | APP-140 | Volume 5, Annex 7.4: A525 HDD crossing Groundwater Risk Assessment; | A | 20 April 2022 |
| 6.5.7.5. | APP-141 | Volume 5, Annex 7.5: River Clwyd HDD crossing Groundwater Risk Assessment; | A | 20 April 2022 |
| 6.5.7.6. | APP-142 | Volume 5, Annex 7.6: A55 HDD crossing Groundwater Risk Assessment; | A | 20 April 2022 |
| 6.5.8.1. | APP-143 | Volume 5, Annex 8.1: Archaeological Desk-Based Assessment | B | 20 April 2022 |
| 6.5.8.2. | APP-144 | Volume 5, Annex 8.2: Designated Heritage Assets Scoping Exercise | B | 20 April 2022 |
| 6.5.8.3. | APP-145 | Volume 5, Annex 8.3: Detailed Gradiometer Survey Report | B | 20 April 2022 |
| 6.5.8.4. | APP-146 | Volume 5, Annex 8.4: Outline Onshore Archaeological Watching Brief 2021 | B | 20 April 2022 |
| 6.5.8.5. | APP-147 | Volume 5, Annex 8.5: Onshore WSI | A | 20 April 2022 |
| 6.5.9.1. | APP-148 | Volume 5, Annex 9.1: Traffic and Transport Technical Baseline Report; | B | 20 April 2022 |
| 6.5.9.2. | APP-149 | Volume 5, Annex 9.2: Trip Generation and Distribution Calculations; | A | 20 April 2022 |
| 6.5.9.3. | APP-150 | Volume 5, Annex 9.3: Percentage Impact Calculations and Assessment Screening; | B | 20 April 2022 |
| 6.5.10.1. | APP-151 | Volume 5, Annex 10.1: Sound Level Meter Calibration Certificates. | A | 20 April 2022 |
| 6.5.10.2. | APP-152 | Volume 5, Annex 10.2: Sound Survey Results. | A | 20 April 2022 |
| 6.5.10.3. | APP-153 | Volume 5, Annex 10.3: Construction Plant Sound Levels. | A | 20 April 2022 |
| 6.5.10.4. | APP-154 | Volume 5, Annex 10.4: Operational Substation Noise Modelling Results. | A | 20 April 2022 |
| 6.5.12.1. | APP-155 | Volume 5, Annex 12.1: Technical Note – Electro-Magnetic Frequencies | A | 20 April 2022 |
| Volume 6 – S/LVIA | Volume 6 – S/LVIA | Volume 6 – S/LVIA | Volume 6 – S/LVIA | Volume 6 – S/LVIA |
| 6.6.2.2.1 | APP-156 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.1 (Site Location and Study Area) | A | 20 April 2022 |
| 6.6.2.2.2 | APP-157 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.2 (Landform) | A | 20 April 2022 |
| 6.6.2.2.3 | APP-158 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.3a (Landscape Character (National)) | A | 20 April 2022 |
| 6.6.2.2.4 | APP-159 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.3b (Landscape Character (Regional)) | A | 20 April 2022 |
| 6.6.2.2.5 | APP-160 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.4 (Landscape Designations) | A | 20 April 2022 |
| 6.6.2.2.6 | APP-161 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.5 (Principle Visual Receptors) | A | 20 April 2022 |
| 6.6.2.2.7 | REP7-039 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.6 (Aerial Mapping with Proposed Development) | C | 08 March 2023 |
| 6.6.2.2.8 | APP-163 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.7 (Context Photos) | A | 20 April 2022 |
| 6.6.2.2.9 | APP-164 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.8a (Substation Bare Ground ZTV with Viewpoints) | A | 20 April 2022 |
| 6.6.2.2.10 | APP-165 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.8b (Substation Screened ZTV with Viewpoints) | A | 20 April 2022 |
| 6.6.2.2.11 | APP-166 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.8c (Substation Screened ZTV with Viewpoints) | A | 20 April 2022 |
| 6.6.2.2.12 | APP-167 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.9a (LANDMAP Aspect Areas: Geological Landscape) | A | 20 April 2022 |
| 6.6.2.2.13 | APP-168 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.9b (LANDMAP Aspect Areas: Geological Landscape and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.14 | APP-169 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.10a (LANDMAP Aspect Areas: Landscape Habitats) | A | 20 April 2022 |
| 6.6.2.2.15 | APP-170 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.10b (LANDMAP Aspect Areas: Landscape Habitats and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.16 | APP-171 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.11a (LANDMAP Aspect Areas: Cultural Landscape Services) | A | 20 April 2022 |
| 6.6.2.2.17 | APP-172 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.11b (LANDMAP Aspect Areas: Cultural Landscape Services and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.18 | APP-173 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.12a (LANDMAP Aspect Areas: Historic Landscape) | A | 20 April 2022 |
| 6.6.2.2.19 | APP-174 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.12b (LANDMAP Aspect Areas: Historic Landscape and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.20 | APP-175 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.13a (LANDMAP Aspect Areas: Visual and Sensory) | A | 20 April 2022 |
| 6.6.2.2.21 | APP-176 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.13b (LANDMAP Aspect Areas: Visual and Sensory and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.22 | APP-177 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.14 (Landscape Character: Landscape Designations and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.23 | APP-178 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.15 (Principal Visual Receptors and Screened ZTV) | A | 20 April 2022 |
| 6.6.2.2.24 | APP-179 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.16 (Outline Landscape Mitigation Principles) | A | 20 April 2022 |
| 6.6.2.2.25 | APP-180 | Volume 6, Annex 2.2: LVIA Figures - Figure 2.17 (Cumulative Developments) | A | 20 April 2022 |
| 6.6.2.3.1 | REP8-072 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.18 (Viewpoint 1: Bridlepath nr Faenol-broper) | B | 15 March 2023 |
| 6.6.2.3.2 | REP8-073 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.19 (Viewpoint 2: St Asaph, Business Park) | B | 15 March 2023 |
| 6.6.2.3.3 | REP8-074 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.20 (Viewpoint 3: Glascoed Rd) | B | 15 March 2023 |
| 6.6.2.3.4 | REP8-075 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.21 (Viewpoint 4: A55) | B | 15 March 2023 |
| 6.6.2.3.5 | REP8-076 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.22 (Viewpoint 5: Minor Rd, Groesffordd) | B | 15 March 2023 |
| 6.6.2.3.6 | REP8-077 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.23 (Viewpoint 6: Bodelwyddan Castle) | B | 15 March 2023 |
| 6.6.2.3.7 | REP8-078 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.24 (Viewpoint 7: St Asaph) | B | 15 March 2023 |
| 6.6.2.3.8 | REP8-079 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.25 (Viewpoint 8: Rhuddlan) | B | 15 March 2023 |
| 6.6.2.3.9 | REP8-080 | Volume 6, Annex 2.3: LVIA Visualisations - Figure 2.26 (Viewpoint 9: Y Foel) | B | 15 March 2023 |
| 6.6.10.4.1 | APP-190 | Volume 6, Annex 10.4: SLVIA Figures - Figure 1 (Array area and SLVIA Study Area with Cumulative Developments) | A | 20 April 2022 |
| 6.6.10.4.2 | APP-191 | Volume 6, Annex 10.4: SLVIA Figures - Figure 2a (Maximum Design Scenario A (332m blade tip)) | A | 20 April 2022 |
| 6.6.10.4.3 | APP-192 | Volume 6, Annex 10.4: SLVIA Figures - Figure 2b (Maximum Design Scenario B (252m blade tip)) | A | 20 April 2022 |
| 6.6.10.4.4 | APP-193 | Volume 6, Annex 10.4: SLVIA Figures - Figure 2c (Snowdonia National Park and Areas of Outstanding Natural Beauty) | A | 20 April 2022 |
| 6.6.10.4.5 | APP-194 | Volume 6, Annex 10.4: SLVIA Figures - Figure 3 (Landform) | A | 20 April 2022 |
| 6.6.10.4.6 | APP-195 | Volume 6, Annex 10.4: SLVIA Figures - Figure 4 (Seascape Character (National)) | A | 20 April 2022 |
| 6.6.10.4.7 | APP-196 | Volume 6, Annex 10.4: SLVIA Figures - Figure 5 (Seascape Character (Wales, Regional)) | A | 20 April 2022 |
| 6.6.10.4.8 | APP-197 | Volume 6, Annex 10.4: SLVIA Figures - Figure 6 (Landscape Character (National)) | A | 20 April 2022 |
| 6.6.10.4.9 | APP-198 | Volume 6, Annex 10.4: SLVIA Figures - Figure 7a (Landscape Character (Wales, Regional)) | A | 20 April 2022 |
| 6.6.10.4.10 | APP-199 | Volume 6, Annex 10.4: SLVIA Figures - Figure 7b (Landscape Character (Wales, Regional) - Legend) | A | 20 April 2022 |
| 6.6.10.4.11 | APP-200 | Volume 6, Annex 10.4: SLVIA Figures - Figure 8 (Landscape Planning Designations) | A | 20 April 2022 |
| 6.6.10.4.12 | APP-201 | Volume 6, Annex 10.4: SLVIA Figures - Figure 9 (LANDMAP - Visual and Sensory Evalation) | A | 20 April 2022 |
| 6.6.10.4.13 | APP-202 | Volume 6, Annex 10.4: SLVIA Figures - Figure 10a (Baseline Light Pollution) | A | 20 April 2022 |
| 6.6.10.4.14 | APP-203 | Volume 6, Annex 10.4: SLVIA Figures - Figure 10b (Tranquility) | A | 20 April 2022 |
| 6.6.10.4.15 | APP-204 | Volume 6, Annex 10.4: SLVIA Figures - Figure 11 (Visual Receptors and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.16 | APP-205 | Volume 6, Annex 10.4: SLVIA Figures - Figure 12a (Blade Tip ZTV for MDS A) | A | 20 April 2022 |
| 6.6.10.4.17 | APP-206 | Volume 6, Annex 10.4: SLVIA Figures - Figure 12b (Hub height ZTV for MDS A) | A | 20 April 2022 |
| 6.6.10.4.18 | APP-207 | Volume 6, Annex 10.4: SLVIA Figures - Figure 12c (Comparative Blade Tip ZTV MDS A (PEIR) and MDS A (ES)) | A | 20 April 2022 |
| 6.6.10.4.19 | APP-208 | Volume 6, Annex 10.4: SLVIA Figures - Figure 13a (Blade Tip ZTV for MDS B) | A | 20 April 2022 |
| 6.6.10.4.20 | APP-209 | Volume 6, Annex 10.4: SLVIA Figures - Figure 13b (Hub Height ZTV for MDS B) | A | 20 April 2022 |
| 6.6.10.4.21 | APP-210 | Volume 6, Annex 10.4: SLVIA Figures - Figure 13c (Comparative Blade Tip ZTV MDS B (PEIR) and MDS B (ES)) | A | 20 April 2022 |
| 6.6.10.4.22 | APP-211 | Volume 6, Annex 10.4: SLVIA Figures - Figure 14 (Horizontal Angle ZTV for MDS A) | A | 20 April 2022 |
| 6.6.10.4.23 | APP-212 | Volume 6, Annex 10.4: SLVIA Figures - Figure 15 (Seascape Character (Wales, Regional) with Blade Tip ZTV) | A | 20 April 2022 |
| 6.6.10.4.24 | APP-213 | Volume 6, Annex 10.4: SLVIA Figures - Figure 16a-b (Blade Tip ZTV (MDS A) with Landscape Character and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.25 | APP-214 | Volume 6, Annex 10.4: SLVIA Figures - Figure 16c (Blade Tip ZTV (MDS A) with Landscape Character and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.26 | APP-215 | Volume 6, Annex 10.4: SLVIA Figures - Figure 17.1a-b (Blade Tip ZTV (MDS A) with Visual Receptors and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.27 | APP-216 | Volume 6, Annex 10.4: SLVIA Figures - Figure 17.1c (Blade Tip ZTV (MDS A) with Visual Receptors and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.28 | APP-217 | Volume 6, Annex 10.4: SLVIA Figures - Figure 17.2a-b (Hub Height Tip ZTV (MDS A) with Visual Receptors and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.29 | APP-218 | Volume 6, Annex 10.4: SLVIA Figures - Figure 17.2c (Hub Height Tip ZTV (MDS A) with Visual Receptors and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.30 | APP-219 | Volume 6, Annex 10.4: SLVIA Figures - Figure 18a-b (Blade Tip ZTV (MDS A) with Landscape Designations and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.31 | APP-220 | Volume 6, Annex 10.4: SLVIA Figures - Figure 18c-d (Blade Tip ZTV (MDS A) with Landscape Designations and Viewpoint Locations) | A | 20 April 2022 |
| 6.6.10.4.32 | APP-221 | Volume 6, Annex 10.4: SLVIA Figures - Figure 19 (Wales Coast Path with Blade Tip ZTV (MDS A)) | A | 20 April 2022 |
| 6.6.10.4.33 | APP-222 | Volume 6, Annex 10.4: SLVIA Figures - Figure 20 (Blade Tip ZTV (MDS) with Met Office Visibility Range Bands) | A | 20 April 2022 |
| 6.6.10.4.34 | APP-223 | Volume 6, Annex 10.4: SLVIA Figures - Figure 21a-b (Hub Height Aviation Lighting ZTV (MDS A)) | A | 20 April 2022 |
| 6.6.10.4.35 | APP-224 | Volume 6, Annex 10.4: SLVIA Figures - Figure 22a-b (Hub Height Aviation Lighting ZTV (MDS B)) | A | 20 April 2022 |
| 6.6.10.4.36 | APP-225 | Volume 6, Annex 10.4: SLVIA Figures - Figure 23 (Comparative Blade Tip ZTV - MDS A and MDS B) | A | 20 April 2022 |
| 6.6.10.4.37 | APP-226 | Volume 6, Annex 10.4: SLVIA Figures - Figure 24 (Combined Cumulative Blade Tip ZTV for Operations Offshore Wind Farms) | A | 20 April 2022 |
| 6.6.10.4.38 | APP-227 | Volume 6, Annex 10.4: SLVIA Figures - Figure 25 (Blade Tip ZTVs for MDS A and Combined Cumulative OWFs) | A | 20 April 2022 |
| 6.6.10.4.39 | APP-228 | Volume 6, Annex 10.4: SLVIA Figures - Figure 26 (Combined Cumulative ZTV for Onshore Wind Farms (Isle of Anglesey)) | A | 20 April 2022 |
| 6.6.10.4.40 | APP-229 | Volume 6, Annex 10.4: SLVIA Figures - Figure 27 (Combined Cumulative ZTV for Onshore Wind Farms (Conwy and Denbighshire) | A | 20 April 2022 |
| 6.6.10.5.1 | APP-230 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 28 (Viewpoint 1 - Bull Bay near Amlwch - Wales Coast Path) | A | 20 April 2022 |
| 6.6.10.5.2 | APP-231 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 29 (Viewpoint 2 - Point Lynas - PRoW to North of Lighthouse) | A | 20 April 2022 |
| 6.6.10.5.3 | APP-232 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 30 (Viewpoint 3 - Mynydd Eilian - Near Trig Point) | A | 20 April 2022 |
| 6.6.10.5.4 | APP-233 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 31 (ViewPoint 4 - Moelfre Headland at Sculpture) | A | 20 April 2022 |
| 6.6.10.5.5 | APP-234 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 32 (ViewPoint 5 - Red Wharf Bay) | A | 20 April 2022 |
| 6.6.10.5.6 | APP-235 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 33 (ViewPoint 6 - Bwrdd Arthur - North of Trig Point) | A | 20 April 2022 |
| 6.6.10.5.7 | APP-236 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 34 (ViewPoint 7 - Penmon Point - North-East of Parking) | A | 20 April 2022 |
| 6.6.10.5.8 | APP-237 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 35 (ViewPoint 8 - Beaumaris - Wales Coast Path) | A | 20 April 2022 |
| 6.6.10.5.9 | APP-238 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 36 (ViewPoint 9 - Bangor Pier - (Southern End)) | A | 20 April 2022 |
| 6.6.10.5.10 | APP-239 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 37 (ViewPoint 10 - Carnedd Llewelyn) | A | 20 April 2022 |
| 6.6.10.5.11 | APP-240 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 38 (ViewPoint 11 - Llanfairfechan) | A | 20 April 2022 |
| 6.6.10.5.12 | APP-241 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 39 (ViewPoint 12 - Conwy Mountain) | A | 20 April 2022 |
| 6.6.10.5.13 | APP-242 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 40 (ViewPoint 13 - Great Orme - Near Summit Complex) | A | 20 April 2022 |
| 6.6.10.5.14 | APP-243 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 41 (ViewPoint 14 - Wales Coast Path Near Penrhyn (Traeth yr Ora)) | A | 20 April 2022 |
| 6.6.10.5.15 | APP-244 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 42 (ViewPoint 15 - Great Orme – Café) | A | 20 April 2022 |
| 6.6.10.5.16 | APP-245 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 43 (ViewPoint 16 - Benlech Bay View Road) | A | 20 April 2022 |
| 6.6.10.5.17 | APP-246 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 44 (ViewPoint 17 - Penrhyn Castle Terrace) | A | 20 April 2022 |
| 6.6.10.5.18 | APP-247 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 45 (ViewPoint 18 - Llandudno Paddling Pool) | A | 20 April 2022 |
| 6.6.10.5.19 | APP-248 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 46 (ViewPoint 19 - Rhos-on-Sea) | A | 20 April 2022 |
| 6.6.10.5.20 | APP-249 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 47 (ViewPoint 20 - Bryn Euryn) | A | 20 April 2022 |
| 6.6.10.5.21 | APP-250 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 48 (ViewPoint 21 - Mynydd Marian) | A | 20 April 2022 |
| 6.6.10.5.22 | APP-251 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 49 (ViewPoint 22 - Abergele Promenade) | A | 20 April 2022 |
| 6.6.10.5.23 | APP-252 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 50 (ViewPoint 23 - Rhyl Aquarium) | A | 20 April 2022 |
| 6.6.10.5.24 | APP-253 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 51 (ViewPoint 24 - Graig Fawr) | A | 20 April 2022 |
| 6.6.10.5.25 | APP-254 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 52 (ViewPoint 25 - Prestatyn Nova Centre) | A | 20 April 2022 |
| 6.6.10.5.26 | APP-255 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 53 (ViewPoint 26 - Bryn-Ilwyn Viewpoint (Prestatyn Hillside Viewpoint, Gwaenysgor)) | A | 20 April 2022 |
| 6.6.10.5.27 | APP-256 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 54 (ViewPoint 27 - Point of Ayr) | A | 20 April 2022 |
| 6.6.10.5.28 | APP-257 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 55 (ViewPoint 28 - Trwyn y Penrhyn Parking Layby) | A | 20 April 2022 |
| 6.6.10.5.29 | APP-258 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 56 (ViewPoint 29 - Colwyn Bay Promenade) | A | 20 April 2022 |
| 6.6.10.5.30 | APP-259 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 57 (ViewPoint 30 - Hilbre Point) | A | 20 April 2022 |
| 6.6.10.5.31 | APP-260 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 58 (ViewPoint 31 - Crosby) | A | 20 April 2022 |
| 6.6.10.5.32 | APP-261 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 59 (ViewPoint 32 - Formby Lifeboat Station (Formby Point)) | A | 20 April 2022 |
| 6.6.10.5.33 | APP-262 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 60 (ViewPoint 33 - Southport (pier)) | A | 20 April 2022 |
| 6.6.10.5.34 | APP-263 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 61 (ViewPoint 34 - Snowdon Summit) | A | 20 April 2022 |
| 6.6.10.5.35 | APP-264 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 62 (ViewPoint 35 - Blackpool Tower) | A | 20 April 2022 |
| 6.6.10.5.36 | APP-265 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 63 (ViewPoint 36 - Tal y Fan) | A | 20 April 2022 |
| 6.6.10.5.37 | APP-266 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 64 (ViewPoint 37 - Cefn Coch Stone Circle) | A | 20 April 2022 |
| 6.6.10.5.38 | APP-267 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 65 (ViewPoint 38 - Foel Fras) | A | 20 April 2022 |
| 6.6.10.5.39 | APP-268 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 66 (ViewPoint 39 - North Wales Path at Garreg Fawr) | A | 20 April 2022 |
| 6.6.10.5.40 | APP-269 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 67 (ViewPoint 40 - Above Capelulo – North Wales Path) | A | 20 April 2022 |
| 6.6.10.5.41 | APP-270 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 68 (ViewPoint 41 - Wales Coast Path North-East of Rhôs-Mynach-Fawr) | A | 20 April 2022 |
| 6.6.10.5.42 | APP-271 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 69 (ViewPoint 42 - Mynydd Bodafon - Trig Point) | A | 20 April 2022 |
| 6.6.10.5.43 | APP-272 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 70 (ViewPoint 43 - Mynydd y Garn) | A | 20 April 2022 |
| 6.6.10.5.44 | APP-273 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 71 (ViewPoint 44 - Beaumaris Castle) | A | 20 April 2022 |
| 6.6.10.5.45 | APP-274 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 72 (ViewPoint 45 - Conwy Castle – Chapel Tower) | A | 20 April 2022 |
| 6.6.10.5.46 | APP-275 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 73 (ViewPoint 49 - Menai Suspension Bridge) | A | 20 April 2022 |
| 6.6.10.5.47 | APP-276 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 74 (ViewPoint 50 - Gwrych Castle – Terrace) | A | 20 April 2022 |
| 6.6.10.5.48 | APP-277 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 75 (ViewPoint 52 - Pen-y-Dinas Camp at Interpretation Sign) | A | 20 April 2022 |
| 6.6.10.5.49 | APP-278 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 76 (ViewPoint 53 - Puffin Island) | A | 20 April 2022 |
| 6.6.10.5.50 | APP-279 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 77 (ViewPoint 54 - y Foel (Common land and hill east of Dyserth)) | A | 20 April 2022 |
| 6.6.10.5.51 | APP-280 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 78 (ViewPoint 55 - Footpath Above Cilgwyn Mawr) | A | 20 April 2022 |
| 6.6.10.5.52 | APP-281 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 79 (ViewPoint 56 - Pen-y-corddyn-mawr) | A | 20 April 2022 |
| 6.6.10.5.53 | APP-282 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 80 (ViewPoint 57 - Moelfre Isaf) | A | 20 April 2022 |
| 6.6.10.5.54 | APP-283 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 81 (ViewPoint 58 - Little Orme on the Wales Coast Path) | A | 20 April 2022 |
| 6.6.10.5.55 | APP-284 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 82 (ViewPoint 59 - Llandundo Promenade - Lifeboat Slipway) | A | 20 April 2022 |
| 6.6.10.5.56 | APP-285 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 83 (ViewPoint 60 - Foel Lus) | A | 20 April 2022 |
| 6.6.10.5.57 | APP-286 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 84 (ViewPoint 61 - Llandudno Promenade near Venue Cymru) | A | 20 April 2022 |
| 6.6.10.5.58 | APP-287 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 85 a-e (ViewPoint 62 -Great Orme – Marine Drive, Wales Coast Path near Toll Booth) | A | 20 April 2022 |
| 6.6.10.5.59 | APP-288 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 86 (ViewPoint 63 - A55 at Penmaenmawr) | A | 20 April 2022 |
| 6.6.10.5.60 | APP-289 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 87 (ViewPoint 64 - A55 at Puffin Roundabout, Dwygyfylch) | A | 20 April 2022 |
| 6.6.10.5.61 | APP-290 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 88 (ViewPoint 65 - A55 at jetty north of Penmaen Rhos) | A | 20 April 2022 |
| 6.6.10.5.62 | APP-291 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 89 (ViewPoint 66 - Liverpool to Dublin Ferry route north of Great Orme) | A | 20 April 2022 |
| 6.6.10.5.63 | APP-292 | Volume 6, Annex 10.5: SLVIA Visualisations - Figure 90 (ViewPoint 67 - Liverpool to Dublin Ferry route north of Conwy Bay) | A | 20 April 2022 |
| Outline Code of Construction Practice | Outline Code of Construction Practice | Outline Code of Construction Practice | Outline Code of Construction Practice | Outline Code of Construction Practice |
| 8.13 | REP7-018 | Outline Code of Construction Practice | G | 08 March 2023 |
| 8.13.1 | REP7-020 | Outline CoCP, Appendix 1,Outline Construction Method Statement | H | 08 March 2023 |
| 2.20 | REP2-020 | Outline CoCP, Appendix 2, Outline Noise and Vibration Management Plan | C | 09 November 2022 |
| 2.31 | REP2-031 | Outline CoCP, Appendix 3, Outline Air Quality Management Plan | C | 09 November 2022 |
| 8.13.4 | REP7-022 | Outline CoCP, Appendix 4, Outline Soil Management Plan | G | 08 March 2023 |
| 2.35 | REP2-035 | Outline CoCP, Appendix 5, Outline Site Waste Management Plan | C | 09 November 2022 |
| 2.37 | REP2-037 | Outline CoCP, Appendix 6, Outline Pollution Prevention and Emergency Incident Response Plan | C | 09 November 2022 |
| 8.13.7 | REP4-035 | Outline CoCP, Appendix 7, Outline Construction Traffic Management Plan | D | 30 January 2023 |
| 8.13.8 | REP7-024 | Outline CoCP, Appendix 8, Outline Public Access Management Plan | F | 08 March 2023 |
| 8.13.9 | APP-321 | Outline CoCP, Appendix 9, Outline Travel Plan | B | 20 April 2022 |
| 2.45 | REP2-045 | Outline CoCP, Appendix 10, Outline Artificial Light and Emissions Plan | C | 09 November 2022 |
| 8.13.11 | REP8-040 | Outline CoCP, Appendix 11, Outline Invasive Non-Native Species Management Plan | E | 15 March 2023 |
| 8.13.12 | REP6-042 | Outline CoCP, Appendix 12, Outline Communication Plan | C | 20 February 2023 |
| Other documents | Other documents | Other documents | Other documents | Other documents |
| 8.8 | REP7-028 | Design Principles Document | E | 08 March 2023 |
| 8.4 | REP7-026 | Outline Landscape and Ecology Management Plan | E | 08 March 2023 |
| 2.6 | REP6-030 | Street Works and Access Plan | D | 20 February 2023 |
| 2.7 | REP6-031 | Temporary Stopping Up of Public Rights of Way Plan | D | 20 February 2023 |
| 2.12 | REP6-036 | Hedgerow and Protected Tree Plan | D | 20 February 2023 |
| 2.1 | REP8-090 | Location Plan | E | 15 March 2023 |
| 2.4 | REP6-027 | Special Category Land Plan | D | 20 February 2023 |
| 4.7 | REP4-007 | Outline Skills and Employment Strategy | B | 30 January 2023 |
| 6.31 | REP6-041 | Outline Offshore Piling Noise Monitoring Plan | B | 20 February 2023 |
| 8.78 | REP8-093 | Landscape Enhancement Scheme Principles | A | 15 March 2023 |
| 6.14 | REP6-023 | Community Linguistic Statement | B | 20 February 2023 |
Signed
Signed by authority of the Secretary of State for Energy Security and Net Zero
David Wagstaff — Deputy Director, Energy Infrastructure Planning — Department for Energy Security and Net Zero — 19th September 2023
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order grants development consent for, and authorises the construction, operation and maintenance of an offshore wind farm generating station located approximately 11km from the coast of Denbighshire, together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory acquisition of land (including rights in land) and the right to use land and to override easements and other rights.
A copy of the plans and book of reference referred to in this Order and certified in accordance with article 40 (certification of plans, etc.) together with a copy of any guarantee or alternative form of security approved by the Secretary of State pursuant to article 31 (funding), may be inspected free of charge at the offices of RWE at Windmill Hill Business Park, Whitehill Way, Swindon Wiltshire, SN5 6PB.
Footnotes
[^f00001]: 2008 c. 29. Section 37 was amended by sections 128(2) and 137(5) and Schedule 13, Part 1, paragraphs 1 to 5 of the Localism Act 2011 (c. 20).
[^f00002]: S.I. 2010/103. This instrument was amended by S.I. 2012/635.
[^f00003]: S.I. 2017/572.
[^f00004]: 1961 c. 33.
[^f00005]: 1965 c. 56.
[^f00006]: 1980 c. 66.
[^f00007]: 1981 c. 66.
[^f00008]: 1989 c. 29.
[^f00009]: 1990 c. 8.
[^f00010]: 1991 c. 22.
[^f00011]: 2003 c. 21.
[^f00012]: 2004 c. 20. Section 105 was amended by section 69 of the Energy Act 2008 (c. 32).
[^f00013]: 2009 c. 23.
[^f00014]: 1971 c. 80.
[^f00015]: 1981 c. 67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c. 34). There are other amendments to the 1981 Act which are not relevant to this Order.
[^f00016]: Section 48 was amended by section 124 (1) and (2) of the Local Transport Act 2008 (c. 26).
[^f00017]: “Street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c. 7).
[^f00018]: 1991 c. 57. Paragraph 5 was amended by section 100(1) and (2) of the Natural Environment and Rural Communities Act 2006 (c. 16), section 84 of, and paragraph 3 of Schedule 11 to, the Marine and Coastal Access Act 2009 (c. 23), paragraph 49 of Schedule 25 to the Flood and Water Management Act 2010 (c. 29) and S.I. 2013/755. Paragraph 6 was amended by paragraph 26 of Schedule 15 to the Environment Act 1995 (c. 25), section 224 of, and paragraph 24 of Schedule 16, and Part 5(B) of Schedule 22, to, the Marine and Coastal Access Act 2009 and S.I. 2013/755. Paragraph 6A was inserted by section 103(3) of the Environment Act 1995.
[^f00019]: 1991 c. 59. Section 66 was amended by paragraph 38 of Schedule 2 to the Flood and Water Management Act 2010 (c. 29) and section 86(3) of the Water Act 2014 (c. 21).
[^f00020]: 1991 c. 59. Section 23 was amended by section 120(1) of and the paragraph 192 of Schedule 22 to, the Environment Act 1995 and section 31 of, and paragraphs 25 and 32 of Schedule 2 to, the Flood and Water Management Act 2010 (c. 29).
[^f00021]: 2017 c. 20.
[^f00022]: 1990 c. 43. Amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c. 16). There are other amendments not relevant to this Order.
[^f00023]: 1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15 of Schedule 15 to the Environmental Protection Act 1990 and Schedule 24 to the Environment Act 1995. There are other amendments to the 1974 Act which are not relevant to the Order.
[^f00024]: 1974 c. 40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15 of Schedule 3 to the Environmental Protection Act 1990 and Paragraph 1 of Schedule 24 to the Environment Act 1995.
[^f00025]: Sections 55, 57, 60, 68 and 69 were amended by the Traffic Management Act 2004 (c. 18).
[^f00026]: 1991 c. 56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c. 43) and sections 99 and 36(2) of the Water Act 2003 (c. 37). There are other amendments to this section which are not relevant to this Order.
[^f00027]: S.I. 2016/1154.
[^f00028]: 1857 c. 81.
[^f00029]: Section 4 was amended by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c. 22).
[^f00030]: Section 11(1) was amended by paragraph 14(3) of Schedule 4 to the Acquisition of Land Act 1981 (c. 67) paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and section 186(2) of the Housing and Planning Act 2016 (c. 22).
[^f00031]: Section 13 was amended by sections 139 of, and paragraph 28 of Schedule 13, and paragraph 1 of Schedule 23 to the Tribunals Courts and Enforcement Act 2007 (c. 15).
[^f00032]: 2003 c. 21.
[^f00033]: S.I. 1997/1160.
[^f00034]: Section 105(2) was substituted by section 69(2) of the Energy Act 2008 (c. 32).
[^f00035]: 1978 c. 30.
[^f00036]: 1973 c. 26.
[^f00037]: Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
[^f00038]: Section 11B was inserted by section 187(2) of the above Act.
[^f00039]: 1989 c. 29.
[^f00040]: 1986 c. 44.
[^f00041]: 1991 c. 56.
[^f00042]: Section 104 was amended by section 42(3) of the Flood and Water Management Act 2010 (c. 29).
[^f00043]: 2003 c. 21.
[^f00044]: Section 106 was amended by section 4 of the Digital Economy Act 2017 (c. 30).
[^f00045]: 1993 c. 43.
[^f00046]: 2006 c. 46.
[^f00047]: S.I. 2015/1522 (W.179)
[^f00048]: 1996 c. 23.
Editorial notes
[^key-73f98bd21d74d216ce43825cc0daa83e]: Art. 1 in force at 11.10.2023, see art. 1
[^key-2c7dbb6b0b9aa8a11ad486d56c26749a]: Art. 2 in force at 11.10.2023, see art. 1
[^key-1f5cf9463cf7e0ddbe21627937483662]: Art. 3 in force at 11.10.2023, see art. 1
[^key-4bdb3e4d1706004b44e24f8475c0beb6]: Art. 4 in force at 11.10.2023, see art. 1
[^key-29ab2216fd9e8ed1f443318e73cb9f0e]: Art. 5 in force at 11.10.2023, see art. 1
[^key-1f98f89cd05a87b7a23562708538db2b]: Art. 6 in force at 11.10.2023, see art. 1
[^key-5ea405e4614a22fdea961bf3a328cb25]: Art. 7 in force at 11.10.2023, see art. 1
[^key-d749becf54e6990677d947d166f7b840]: Art. 8 in force at 11.10.2023, see art. 1
[^key-8599be47331c50440d4047b6c554eec7]: Art. 9 in force at 11.10.2023, see art. 1
[^key-1956be40a837c28ff59f26e7879c50a2]: Art. 10 in force at 11.10.2023, see art. 1
[^key-d5b4fbc79fc376feff3b8ae9f3952743]: Art. 11 in force at 11.10.2023, see art. 1
[^key-644c1fe907e9b5a2b8c534b6eedb7ebb]: Art. 12 in force at 11.10.2023, see art. 1
[^key-b050dcfa08b9dd4fda217c61bde97371]: Art. 13 in force at 11.10.2023, see art. 1
[^key-dd05aa8d86f0912ef57e1425dcc95851]: Art. 14 in force at 11.10.2023, see art. 1
[^key-eae5bc2be3fc96a440f6e3250a870a33]: Art. 15 in force at 11.10.2023, see art. 1
[^key-8a3feae552fdda20deba01f7a329b338]: Art. 16 in force at 11.10.2023, see art. 1
[^key-34d0e82d8a421c8f419aefb5f8cad191]: Art. 17 in force at 11.10.2023, see art. 1
[^key-dcb27ce9859d5236bfa97e788c9d412c]: Art. 18 in force at 11.10.2023, see art. 1
[^key-e447f4376c1fac93f800e364a8ef4732]: Art. 19 in force at 11.10.2023, see art. 1
[^key-798df7e25d48b41136d5e5770099e445]: Art. 20 in force at 11.10.2023, see art. 1
[^key-78566716aa506349404aee628eaf4982]: Art. 21 in force at 11.10.2023, see art. 1
[^key-c96b2fa8acf1842d40ce046626a077a3]: Art. 22 in force at 11.10.2023, see art. 1
[^key-85683bb93cd5e37e3ef96e7d1a532867]: Art. 23 in force at 11.10.2023, see art. 1
[^key-01396af2a76d5763d7309afed991aa51]: Art. 24 in force at 11.10.2023, see art. 1
[^key-fd0c6fe2a9795bc4f3c8c3818230fc0f]: Art. 25 in force at 11.10.2023, see art. 1
[^key-06c206cb11881986467633661a2cd7d1]: Art. 26 in force at 11.10.2023, see art. 1
[^key-bd2538b99b2f73121ef636e6315aad6a]: Art. 27 in force at 11.10.2023, see art. 1
[^key-d7f67ede11c0c9dafd03ab3e3c79d3d7]: Art. 28 in force at 11.10.2023, see art. 1
[^key-d936db8f22475e3be7d79a9b57d5fc77]: Art. 29 in force at 11.10.2023, see art. 1
[^key-78902b0340f4bc9d1b51d9972bc59a92]: Art. 30 in force at 11.10.2023, see art. 1
[^key-dd6f6eb7d3e105bf6672f93f3c8b7ebf]: Art. 31 in force at 11.10.2023, see art. 1
[^key-56594ff72dc989d3a8b28e57499525fa]: Art. 32 in force at 11.10.2023, see art. 1
[^key-3bd8ee169f15ff72877fa3c7d2cc12fa]: Art. 33 in force at 11.10.2023, see art. 1
[^key-0468dfd22c65b4f8bc016e242eb4b8a5]: Art. 34 in force at 11.10.2023, see art. 1
[^key-a2adc4b268e8e7fd185237b5584fb676]: Art. 35 in force at 11.10.2023, see art. 1
[^key-fa5341e0deb257306f05b4e8ce015d66]: Art. 36 in force at 11.10.2023, see art. 1
[^key-9dba64ec00a8213e6c4ca47a3722503c]: Art. 37 in force at 11.10.2023, see art. 1
[^key-5a38a7a4d602b259f84a03d7e86b789c]: Art. 38 in force at 11.10.2023, see art. 1
[^key-ce78b1204709bee5ffeb332e807e22bb]: Art. 39 in force at 11.10.2023, see art. 1
[^key-2e1ddd4b5b0d8e64402c4fdfda4eaf33]: Art. 40 in force at 11.10.2023, see art. 1
[^key-a920fe1fae7da8d54c8243070631f14e]: Art. 41 in force at 11.10.2023, see art. 1
[^key-0cc664783d3b3b787e2f550a6aed636b]: Art. 42 in force at 11.10.2023, see art. 1
[^key-dbc7da6939a4ef9a28345fcc50a1810a]: Art. 43 in force at 11.10.2023, see art. 1
[^key-b16a66dacdda948acb3125cd16602610]: Art. 44 in force at 11.10.2023, see art. 1
[^key-4aedb3ef1cb1432405c49f4c4b3971f5]: Sch. 2 para. 1 in force at 11.10.2023, see art. 1
[^key-dcc1bb5e59d8c9af623732a540259df5]: Sch. 2 para. 2 in force at 11.10.2023, see art. 1
[^key-9867399792d07f234abad05d6f127d3d]: Sch. 2 para. 3 in force at 11.10.2023, see art. 1
[^key-5eaee53e1aadf6462e344e707a266eaa]: Sch. 2 para. 4 in force at 11.10.2023, see art. 1
[^key-a32c5ff69be81a3fa213bee161651ed3]: Sch. 2 para. 5 in force at 11.10.2023, see art. 1
[^key-cfd448da924fa18190f8f802cbb033f0]: Sch. 2 para. 6 in force at 11.10.2023, see art. 1
[^key-8d5bbdb3e457a3848f4b75ba2470b42f]: Sch. 2 para. 7 in force at 11.10.2023, see art. 1
[^key-be6595f3bcc457a0a5ecd365909507c4]: Sch. 2 para. 8 in force at 11.10.2023, see art. 1
[^key-1c01eb37abc3fc795b43a840db089850]: Sch. 2 para. 9 in force at 11.10.2023, see art. 1
[^key-a5e4caf7d8cc22d28235cb7ddb393d70]: Sch. 2 para. 10 in force at 11.10.2023, see art. 1
[^key-d26ac7ac0640e78075a2ee6f34f177e2]: Sch. 2 para. 11 in force at 11.10.2023, see art. 1
[^key-bbcd0b3a63cf7ec4d39ab8e8ecbb4230]: Sch. 2 para. 12 in force at 11.10.2023, see art. 1
[^key-0df901d2291b20d146ef2bce25af2e2a]: Sch. 2 para. 13 in force at 11.10.2023, see art. 1
[^key-bcbbbe179bd183708b682c995299005c]: Sch. 2 para. 14 in force at 11.10.2023, see art. 1
[^key-bcfcd84b12b1ddedd20fe0037e84031d]: Sch. 2 para. 15 in force at 11.10.2023, see art. 1
[^key-ada7edb495a57af1d179f607801d47d8]: Sch. 2 para. 16 in force at 11.10.2023, see art. 1
[^key-2520ab56623ab4fe74bb6e6cf11c67ad]: Sch. 2 para. 17 in force at 11.10.2023, see art. 1
[^key-4ba8a028e7197c97cb12eefe16e41bad]: Sch. 2 para. 18 in force at 11.10.2023, see art. 1
[^key-de30ca330b7056110f0d281d9095b327]: Sch. 2 para. 19 in force at 11.10.2023, see art. 1
[^key-332c42c495bba0b294c4f27ca72dd8c1]: Sch. 2 para. 20 in force at 11.10.2023, see art. 1
[^key-64b8dfb3d0232ae2d47c260cba4d5497]: Sch. 2 para. 21 in force at 11.10.2023, see art. 1
[^key-8319022ee71e02df34a67f47c393ec7e]: Sch. 2 para. 22 in force at 11.10.2023, see art. 1
[^key-f29f601bfab7024cc3cd36374726b4d2]: Sch. 2 para. 23 in force at 11.10.2023, see art. 1
[^key-cc54098eaa14725b1166ee56225d7a5f]: Sch. 2 para. 24 in force at 11.10.2023, see art. 1
[^key-0d36dcc471bd58edfb81667bdd162c09]: Sch. 2 para. 25 in force at 11.10.2023, see art. 1
[^key-0273212ed7a782d9e896ea171b3d8ff2]: Sch. 2 para. 26 in force at 11.10.2023, see art. 1
[^key-c779dbd018b662aaa0f679677360c2c3]: Sch. 2 para. 27 in force at 11.10.2023, see art. 1
[^key-45d769e40c13cdcc711a52fcd9834ef5]: Sch. 8 para. 1 in force at 11.10.2023, see art. 1
[^key-e4e2489405acae0dc0a28d4b7cfbd2c7]: Sch. 8 para. 2 in force at 11.10.2023, see art. 1
[^key-70946cccc013d8b31f5f811a2a5ddb2e]: Sch. 8 para. 3 in force at 11.10.2023, see art. 1
[^key-07ead8b61a16dc7fdf84a82e28704d8f]: Sch. 8 para. 4 in force at 11.10.2023, see art. 1
[^key-c688c075c416ec2495138ea4ed2e61e9]: Sch. 8 para. 5 in force at 11.10.2023, see art. 1
[^key-5698398107cf9745aabc60273ae5d291]: Sch. 8 para. 6 in force at 11.10.2023, see art. 1
[^key-0ca374988ab9b2ca6d713d50a7333e5f]: Sch. 8 para. 7 in force at 11.10.2023, see art. 1
[^key-9c006d17785caffbc582b276074c86cb]: Sch. 8 para. 8 in force at 11.10.2023, see art. 1
[^key-3fdcbca93410810beec2e530cd17dc03]: Sch. 8 para. 9 in force at 11.10.2023, see art. 1
[^key-e476c967d05ce8783a4b360021715f2f]: Sch. 8 para. 10 in force at 11.10.2023, see art. 1
[^key-1a59413d50fa6400859f3b2153b92f98]: Sch. 8 para. 11 in force at 11.10.2023, see art. 1
[^key-089587c3521695c7a8155398729bd33e]: Sch. 9 para. 1 in force at 11.10.2023, see art. 1
[^key-53520bc67a54ac960b65ae7f1d7fe8f1]: Sch. 9 para. 2 in force at 11.10.2023, see art. 1
[^key-deeea3b9e9011b383ed7fa283bc787cd]: Sch. 9 para. 3 in force at 11.10.2023, see art. 1
[^key-59467931c1083fd42e46dbd57470303c]: Sch. 9 para. 4 in force at 11.10.2023, see art. 1
[^key-c25d035c021cbbbab1b45012104ea2dd]: Sch. 9 para. 5 in force at 11.10.2023, see art. 1
[^key-daa1490b164ec3d23cf2d4a2ed0699c4]: Sch. 9 para. 6 in force at 11.10.2023, see art. 1
[^key-68276729c0add9eb0ac4b58815c80c99]: Sch. 9 para. 7 in force at 11.10.2023, see art. 1
[^key-21d909fdc5af19fdde600d3c3abf0a61]: Sch. 9 para. 8 in force at 11.10.2023, see art. 1
[^key-64c38bdbd7e68e0575157400c1faffbf]: Sch. 9 para. 9 in force at 11.10.2023, see art. 1
[^key-45836be586da73dbcee0dd542662945e]: Sch. 9 para. 10 in force at 11.10.2023, see art. 1
[^key-8626659ee0f0e7099b4bcc1e9f84b55e]: Sch. 9 para. 11 in force at 11.10.2023, see art. 1
[^key-768c51b174795690f73984043253e6c2]: Sch. 9 para. 12 in force at 11.10.2023, see art. 1
[^key-b34cd41ad81e38641d9c97a2662dfb0f]: Sch. 9 para. 13 in force at 11.10.2023, see art. 1
[^key-5d33db276d14f6fc6243f9fdaa3250e7]: Sch. 9 para. 14 in force at 11.10.2023, see art. 1
[^key-018d7831bbeadcbd92bc23c7e0d39d1c]: Sch. 9 para. 15 in force at 11.10.2023, see art. 1
[^key-fe4cb6f025b9e4b860068b07a1d65986]: Sch. 9 para. 16 in force at 11.10.2023, see art. 1
[^key-8b463500943341582a1c8f16cd9cb0e3]: Sch. 9 para. 17 in force at 11.10.2023, see art. 1
[^key-cc4bfb63a363d3329549e685431a9f72]: Sch. 9 para. 18 in force at 11.10.2023, see art. 1
[^key-e1025ede76aad13127c7a2fa7aaa823e]: Sch. 9 para. 19 in force at 11.10.2023, see art. 1
[^key-f1eaaf8a45c2191b5565643c9fa6514b]: Sch. 9 para. 20 in force at 11.10.2023, see art. 1
[^key-348f67dcf35c7cf93964146aa7f93ef6]: Sch. 9 para. 21 in force at 11.10.2023, see art. 1
[^key-281ab5624a6b223c059d4d4e5483d5f9]: Sch. 9 para. 22 in force at 11.10.2023, see art. 1
[^key-f2fd0c653d7cc77f3a12b9fb816a3466]: Sch. 9 para. 23 in force at 11.10.2023, see art. 1
[^key-91be8bcfb30a54c68d67fa9c4ab30cad]: Sch. 9 para. 24 in force at 11.10.2023, see art. 1
[^key-7ebdbd614894fc19275821f98f0fcdc7]: Sch. 9 para. 25 in force at 11.10.2023, see art. 1
[^key-bd84bc052b2af50b0acb2734461b5682]: Sch. 9 para. 26 in force at 11.10.2023, see art. 1
[^key-8e1fc06e1ee318b9e53ba873ec64475a]: Sch. 9 para. 27 in force at 11.10.2023, see art. 1
[^key-26f1462628c7de6286ce2886e1b1c59b]: Sch. 9 para. 28 in force at 11.10.2023, see art. 1
[^key-2c237709430db5f9a596c54bf8686574]: Sch. 9 para. 29 in force at 11.10.2023, see art. 1
[^key-13f1bbf136b6d22cd27ae4a78d8faeec]: Sch. 9 para. 30 in force at 11.10.2023, see art. 1
[^key-93935fe001315d9cb1f83e95e6d745b9]: Sch. 9 para. 31 in force at 11.10.2023, see art. 1
[^key-dcc2270bf57795ba80c7a7156bff9d54]: Sch. 9 para. 32 in force at 11.10.2023, see art. 1
[^key-3c0a17810d12f59fb5c6b40f5201a18e]: Sch. 9 para. 33 in force at 11.10.2023, see art. 1
[^key-2c87acf2136719f0e401db2970309c36]: Sch. 9 para. 34 in force at 11.10.2023, see art. 1
[^key-db72ee2110644c8d35f8a222b45af5ff]: Sch. 9 para. 35 in force at 11.10.2023, see art. 1
[^key-cb804fb70376db53a93f4f604471e3af]: Sch. 9 para. 36 in force at 11.10.2023, see art. 1
[^key-c308abf5629275e644535738878c2383]: Sch. 9 para. 37 in force at 11.10.2023, see art. 1
[^key-4dc37957d94f7417ca10e941f8bd1eeb]: Sch. 9 para. 38 in force at 11.10.2023, see art. 1
[^key-1736bc96a3fc013c191666e61705d66f]: Sch. 9 para. 39 in force at 11.10.2023, see art. 1
[^key-75cd7b6ac99987d5f8f56295805cfa45]: Sch. 9 para. 40 in force at 11.10.2023, see art. 1
[^key-9c66f8acca1bab55edbe1d3269445086]: Sch. 9 para. 41 in force at 11.10.2023, see art. 1
[^key-6455d26cdd2e34e69bc9c09417238a2b]: Sch. 9 para. 42 in force at 11.10.2023, see art. 1
[^key-1b1824048678224debf62a94edfc9b68]: Sch. 9 para. 43 in force at 11.10.2023, see art. 1
[^key-db8c36afe5dff29a28d169cb7f2ca75a]: Sch. 9 para. 44 in force at 11.10.2023, see art. 1
[^key-22f32bb46da63a5164c44f12e50a8698]: Sch. 9 para. 45 in force at 11.10.2023, see art. 1
[^key-2eb558159990b3b35e97fa23672326e5]: Sch. 9 para. 46 in force at 11.10.2023, see art. 1
[^key-a7a43a080c87b336118d5bffd5339887]: Sch. 9 para. 47 in force at 11.10.2023, see art. 1
[^key-f090d439d4cff0070a4e95904d93d4f6]: Sch. 9 para. 48 in force at 11.10.2023, see art. 1
[^key-ceed41cf8748cb39f30d0baa39a93f2f]: Sch. 9 para. 49 in force at 11.10.2023, see art. 1
[^key-2b99948b282286c3ac5f063dd36e4e6f]: Sch. 9 para. 50 in force at 11.10.2023, see art. 1
[^key-b9e77e3f47dea9286994e70a8e432045]: Sch. 9 para. 51 in force at 11.10.2023, see art. 1
[^key-e3c591f618620b146586bb7284cc22c6]: Sch. 9 para. 52 in force at 11.10.2023, see art. 1
[^key-efca676abbfdbe8e9b9dee412c7282d8]: Sch. 9 para. 53 in force at 11.10.2023, see art. 1
[^key-be93cb75e15d7f9fefd89818234ed082]: Sch. 9 para. 54 in force at 11.10.2023, see art. 1
[^key-47915556fae136d279baf0c93318b9fe]: Sch. 9 para. 55 in force at 11.10.2023, see art. 1
[^key-ed31436669e51ba60e69cb34264ee3ec]: Sch. 9 para. 56 in force at 11.10.2023, see art. 1
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.